Solicitation
Triennial Circuit Breaker and Feeder Testing
Department of Veterans Affairs
AI summary says SDVOSB set-aside · NV
A newer version of this notice was posted Nov 20, 2026. It moves the due date from Nov 9, 2026 to Dec 4, 2026, which is the date shown on this page. See the latest version.
AI summary Beta
Summary of the version posted Oct 9, 2026. The notice was amended Nov 20, 2026. The due date moved from Nov 9, 2026 to Dec 4, 2026. Check what else changed on SAM.gov. This summary may miss requirements: 2 of 4 attachments weren't read (Facility Floor Plan.pdf, Wage Determination 2015-5595 Washoe County.pdf). Check the attachments on SAM.gov.
The VA's Network Contracting Office 21 wants a contractor to do the three-year (triennial) testing of the electrical power system at the Reno VA Medical Center in Nevada: circuit breakers, feeder cables, medium-voltage switches and transformers. The work also includes infrared and standard photos, an updated coordination study and arc flash analysis, and a final report. The solicitation says it is a total set-aside for certified service-disabled veteran-owned small businesses (SDVOSBs), with an award based on price only.
Who can bid (10)
- Certified service-disabled veteran-owned small business (SDVOSB), listed in the SBA certification database at the time of offer and at award; verified in SBA DSBS at submission per the notice text. From 36C26127Q0067_1.docx
- Offers from firms that are not certified SDVOSBs in the SBA database at the time of offer will not be considered. From 36C26127Q0067_1.docx
- Small under NAICS 238210, with a size standard shown as $19 Million.
Show all 10Show fewer
- All contractor technicians must be NETA-certified (or equivalent) with OSHA 10-Hour training; the superintendent needs OSHA 30-Hour. From 36C26127Q0067_1.docx
- At least 5 continuous years of experience testing electrical power distribution systems in healthcare, industrial, educational and commercial facilities, including low and medium voltage switchgear. From 36C26127Q0067_1.docx
- Technicians must be NFPA 70E Qualified Persons with electrical safety training; certificates go to the Contracting Officer before work starts.
- Current calibration documentation for all instruments, test equipment, tools and PPE before work begins. From 36C26127Q0067_1.docx
- Insurance: general liability of $1,000,000 per occurrence, automobile liability, workers' compensation and employer's liability of at least $100,000; general liability cannot have an asbestos exclusion. From 36C26127Q0067_1.docx
- Comply with limitations on subcontracting: the certificate is checked for special trade construction, so no more than 75% of the amount paid may go to firms that are not certified SDVOSBs. From 36C26127Q0067_1.docx
- Hold all licenses and certifications required by local, state and federal authorities, and be registered in SAM.
How to submit: Email to alex.arter@va.gov (Alex Arter, 279-944-5640). Contracting Officer is Charee Harris., due Nov 9, 2026 at 12:00 PM Pacific time (SF 1449 shows 11-09-2026, 12PM PST; SAM.gov shows 12:00 at UTC-08:00). What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (8)
- Serious: Set-aside status conflicts with SAM.gov listing. SAM.gov lists the set-aside as none, but the solicitation attachment says it is a total SDVOSB set-aside, so a non-SDVOSB bid would be rejected. From 36C26127Q0067_1.docx
- Worth checking: Price-only award with no credit for qualifications. Only price decides the award, so a firm with strong credentials gets no advantage and must price a large, detailed scope accurately without seeing the equipment counts in a readable form. From 36C26127Q0067_1.docx
- Worth checking: Overnight work in an active hospital. Most testing runs 6PM to 6AM and on weekends in a working hospital, with outages to coordinate 2 weeks ahead and infrared scans on energized equipment, which raises labor cost and safety risk. From 36C26127Q0067_1.docx
Show all 8Show fewer
- Worth checking: Specialized staff and training requirements. Every technician must be NETA-certified with OSHA 10 and NFPA 70E training, the superintendent needs OSHA 30, and the firm needs 5 years of matching experience, which many small electrical firms will not have. From 36C26127Q0067_1.docx
- Worth checking: Broad scope beyond routine testing. The job also includes a facility-wide coordination study, redrawn one-line diagrams in PDF and CAD, an arc flash analysis with new labels, medium-voltage cable work and replacement estimates, which usually needs an engineering partner. From 36C26127Q0067_1.docx
- Minor: Repairs are excluded but must be priced as estimates. The contractor does not fix failed components but must report them immediately and provide repair cost estimates, so failures will not bring extra paid work under this contract. From 36C26127Q0067_1.docx
- Minor: Short report deadline. A full written report with photos and test data is due within 7 days of finishing the survey. From 36C26127Q0067_1.docx
- Minor: Subcontracting limit written two ways. The FAR clause lists 50% for services and 75% for special trade construction, and the signed certificate marks the 75% special trade box, so ask the Contracting Officer which limit applies before teaming.
Read from the notice and 2 attachments. 2 of 4 not read. Show which files.
- 36C26127Q0067_1.docx (read)
- Facility Single Line Diagram.pdf (read)
- Facility Floor Plan.pdf: not summarized: open it on SAM.gov
- Wage Determination 2015-5595 Washoe County.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Test and exercise the electrical distribution system, including all 225-amp, 3-pole and larger circuit breakers, plus liquid-filled and air-cooled transformers, as marked on the color-coded one-line diagrams
- Test medium-voltage switches (oil-cooled) and test existing medium-voltage cables with very low frequency (VLF) procedures; inspect every vault
- Torque busing and lug connections, megger low-voltage feeder cables, and clean all electrical connections
- Take standard photos and infrared photos of each item tested (JPEG, under 4MB each); coordinate re-torquing of hot spots with the VA and re-scan
- Do an overcurrent protective device coordination study for the whole facility, update the one-line diagrams (PDF and CAD), and update the arc flash analysis and labels
- Label tested equipment with test date and firm name, and remove old test labels
- Deliver a complete written PDF report within 7 days of finishing, including repair and medium-voltage cable replacement cost estimates
- Follow the VA's suggested multi-day testing schedule, mostly overnight, and report failed items to the COR right away
- Contract type
- Firm-fixed-price, one lump-sum line item (quantity 1, unit JB); commercial services order on SF 1449
- Period of performance
- Work to be done as soon as possible after Notice to Proceed. The VA's suggested schedule is about 12 testing days, mostly overnight and weekend shifts, with a few backup days. No option years are mentioned.
- Place of performance
- Reno VA Medical Center (VA Sierra Nevada Health Care System), 975 Kirman Ave, Reno, NV 89502
- Estimated value
- Not stated
- How they'll choose
- Price only. The award goes to the responsible offeror whose conforming offer is most advantageous to the Government, with price as the only evaluation factor.
- Offers due
- Nov 9, 2026 at 12:00 PM Pacific time (SF 1449 shows 11-09-2026, 12PM PST; SAM.gov shows 12:00 at UTC-08:00) (from the version posted Oct 9, 2026; amended since)
- How to submit
- Email to alex.arter@va.gov (Alex Arter, 279-944-5640). Contracting Officer is Charee Harris.
What they'll judge offers on
- Price only
What to include when you submit
- Submit a signed and dated offer that includes the solicitation number, your name, address and phone, and your UEI
- Complete SF 1449 blocks 12, 17, 23, 24 and 30 and fill in the unit price and total on line item 0001
- Include a statement of how far you agree with all solicitation terms and conditions
- Return the signed VAAR 852.219-75 limitations on subcontracting certification with the offer; offers without it will not be evaluated
- Be verified in the SBA certification database (and SBA DSBS, per the notice text) when you submit the offer
- Hold prices firm for 60 calendar days after the due date
- Complete the other representations and certifications not already in SAM, and acknowledge any amendments
- Before award, give the Contracting Officer proof of general liability insurance with no asbestos exclusion
Not in the notice text
- Exact number and size of breakers, feeders, transformers and switches to price; the floor plan and wage determination files could not be read and the one-line diagrams are only partly readable
- Contract value or budget
- Actual start date and whether the VA's suggested testing schedule is fixed
- Whether a site visit or pre-bid questions period is offered
- Which limitations-on-subcontracting percentage (50% or 75%) governs
- Wage determination 2015-5595 for Washoe County rates, which are in a scanned file; the solicitation lists indicative rates of about $33.69 for an electrician (wage plus fringe) but says they are for information only
- Whether SAM.gov's 'no set-aside' entry or the SDVOSB set-aside in the attachment is correct for your business
More to check before you bid
- The notice names requirements:
- The AI summary says this is set aside for service-disabled veteran-owned small businesses (SDVOSBs), but SAM.gov lists no set-aside. Check the notice before you bid.
Notice details
Notice type, codes, versions and files
- Posted
- Oct 9, 2026
- Notice type
- Solicitation
- Office
- 261-Network Contract Office 21 (36C261), Mather, CA
- Product/service code
- J061 · Maint/Repair/Rebuild of Equipment – Electric Wire and Power Distribution Equipment
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 238210)
- Versions
17 versions have been posted, newest first.
- Nov 20, 2026 · Amendment 0015Due Dec 4, 2026
- Nov 19, 2026 · Amendment 0014Due Dec 4, 2026 (changed)
- Nov 6, 2026 · Amendment 0013Due Nov 20, 2026
- Nov 6, 2026 · Amendment 0012Due Nov 20, 2026
- Nov 6, 2026 · Amendment 0011Due Nov 20, 2026
- Nov 2, 2026 · Amendment 0010Due Nov 20, 2026
- Nov 2, 2026 · Amendment 0009Due Nov 20, 2026
- Nov 2, 2026 · Amendment 0008Due Nov 20, 2026
- Oct 23, 2026 · Amendment 0007Due Nov 20, 2026
- Oct 23, 2026 · Amendment 0006Due Nov 20, 2026
- Oct 23, 2026 · Amendment 0005Due Nov 20, 2026 (changed)
- Oct 19, 2026 · Amendment 0004Due Nov 9, 2026
- Oct 15, 2026 · Amendment 0003Due Nov 9, 2026
- Oct 14, 2026 · Amendment 0002Due Nov 9, 2026
- Oct 9, 2026 · Amendment 0001 (this version)Due Nov 9, 2026
- Oct 9, 2026 · SolicitationDue Nov 9, 2026 (changed)
- Sep 25, 2026 · Sources SoughtDue Oct 2, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- TVHS Generator PM/Bank Testing Base+4The Department of Veterans Affairs (VA), Network Contracting Office 9, wants yearly preventive maintenance and load bank testing (running each generator against a test load) on…
- LEX Triannual Energy Study and ARC Flash TestingOnly Service-Disabled Veteran-Owned Small Business (SDVOSB) firms can bid.
- Supply, Installation, Testing, and Commissioning of Audiovisual Systems for the Multi-Purpose Room and Executive Conference Room at the U.S. Embassy in Malé, MaldivesThe U.S. Embassy in Colombo, Sri Lanka, wants a turnkey audiovisual system (equipment, installation, programming, testing, commissioning and training) for two rooms at the U.S.…
- WTX Elevator Inspections and Load Testing Services - Amended