Solicitation
GRCA 257282 - Replace Wastewater Plant at South Ri
Department of the Interior · National Park Service
A newer version of this notice was posted Nov 16, 2026. It moves the due date from Nov 2, 2026 to Dec 18, 2026, which is the date shown on this page. See the latest version.
AI summary Beta
Summary of the version posted Sep 18, 2026. The notice was amended Nov 16, 2026. The due date moved from Nov 2, 2026 to Dec 18, 2026. Check what else changed on SAM.gov. This summary may miss requirements: 30 of 42 attachments weren't read (B09_Amendment_01_GRCA257282_CD_Specifications_June2025_01.pdf, B09_Amendment_01_RCA257282_Access_Road_100P_Final_CD_Specifications_01.pdf and 28 more). Check the attachments on SAM.gov.
The National Park Service (Denver Service Center) wants a contractor to build a new 0.65 MGD membrane bio-reactor wastewater treatment plant at the South Rim Village of Grand Canyon National Park, Arizona, and tear down the old plant afterward. The job also includes a compost facility, access road improvements and a 12-month operational support period, and is described as more than $10 million of construction. It is open to all businesses (no set-aside) and is currently unfunded, with performance planned for 02/01/2027 to 02/01/2030.
Who can bid (7)
- Open to all businesses; no small business set-aside (small businesses still get maximum credit on the Small Business Participation factor) From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Bid guarantee: submit an SF 24 bid bond (or other suitable guarantee) with Volume II From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Performance and payment bonds appear to be required: the bonds clause is listed and the schedule refers to 'the required performance and payment bonds' (amounts and due dates were in parts not provided) From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
Show all 7Show fewer
- Active SAM.gov registration at the time you submit your offer From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Name your Project Manager, Job Site Superintendent, QC Manager and Safety Manager (key personnel), and your firms for four key trades: process, mechanical/plumbing, electrical and civil. These assignments are locked unless the Contracting Officer approves a change. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Relevant wastewater plant experience: up to 5 projects in the last 8 years for the prime, with the prime self-performing at least 40% of contract cost (excluding materials) to count as prime experience; key subcontractors submit up to 3 projects from the last 5 years From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Large businesses must submit an acceptable small business subcontracting plan (small businesses do not) From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
How to submit: Email only, to Contracting Officer Tim Burger (timothy_burger@ios.doi.gov), Contract Specialist Kristin Tauber (Kristin_tauber@ios.doi.gov) and CS_DSC_Proposal_Submission@nps.gov, due November 2, 2026, 2:00 PM Mountain Time (SAM response deadline; the SF 1442 also shows 11/02/2026 and 1400). The Amendment 5 form was unreadable, so any later change to the date is unknown.. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
- Serious: SAM.gov and the solicitation disagree on the set-aside. SAM.gov lists no set-aside, but the solicitation the AI read says a set-aside for small businesses. Ask the contracting officer which applies before you bid.
- Serious: Currently unfunded. The government says the project has no funding yet, so award may be delayed or may not happen even after you spend heavily on a proposal. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Serious: Large, complex job needing bonding and proven experience. Construction over $10 million with a bid bond, performance and payment bonds, and a requirement to show wastewater plant startup and commissioning experience makes this hard for a small firm without a strong bonding line and relevant projects.
Show all 10Show fewer
- Worth checking: Notice-to-proceed date conflict. The solicitation assumes a February 1, 2027 notice to proceed (with a 1,095-day completion deadline and POP to 02/01/2030), but Amendment 2 changed the assumed date for the Factor 2 schedule to April 1, 2027, so check the latest amendments for the real dates. From Sol_140P2026R0101_Amd_0002.pdf
- Worth checking: Liquidated damages. Late completion costs $5,856.43 for each calendar day of delay, which can add up quickly on a remote site. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Worth checking: Remote, constrained site with seasonal limits. The Technical Approach must address Grand Canyon winter weather, freeze/thaw, access restrictions, limited staging space and high visitor volumes, and schedules that ignore this are rated higher risk.
- Worth checking: The site visit was Sep 16, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From Sol_140P2026R0101_Amd_0004.pdf
- Worth checking: Lots of required documents not reviewed. The specifications, drawings, Q&A answers, wage determination, hazardous materials report, geotechnical report and price schedule were too large or unsupported to read, and the amendments say they are contractually binding. From Sol_140P2026R0101_Amd_0005.pdf
- Minor: Award possible without discussions. The government may award from initial proposals, so your first submission must have your best technical and price terms. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Minor: Email-only submission with strict formatting. Proposals sent any other way are not accepted, files and emails have size limits, and you must verify receipt yourself. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
Read from the notice and 12 attachments. 30 of 42 not read. Show which files.
- B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf (read)
- Sol_140P2026R0101_Amd_0005.pdf (read)
- B09_Amendment_05_SF_30_0005.pdf (read)
- Sol_140P2026R0101_Amd_0004.pdf (read)
- B09_Amendment_04_SF30_0004.pdf (read)
- Sol_140P2026R0101_Amd_0003.pdf (read)
- B09_Amendment_03_SF30_0003.pdf (read)
- Sol_140P2026R0101_Amd_0002.pdf (read)
- B09_Amendment_02_SF30_0002.pdf (read)
- Sol_140P2026R0101_Amd_01.pdf (read)
- B09_Amendment_01_SF30_01.pdf (read)
- Sol_140P2026R0101.pdf (read)
- B09_Amendment_01_GRCA257282_CD_Specifications_June2025_01.pdf: not summarized: open it on SAM.gov
- B09_Amendment_01_RCA257282_Access_Road_100P_Final_CD_Specifications_01.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_Answers_to_Questions_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_02_SCADA_wSeal_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_04_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_05_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA_Final_Individual_Specs_0005.zip: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B09_Amendment_03_Answers_to_Questions_0003.pdf: not summarized: open it on SAM.gov
- B09_Amendment_03_GRCA257282_FinalCD_Addendum_03_Compiled_wSeal_0003.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_What_Evaluators_Will_Ask_for_Each_Factor_2_0002.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_GRCA_257282_SR_WWTP_PreBid_Mtg_presentation_(8-11-26)_FINAL_0002.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_GRCA_257282_Precon_SignIn_0002.pdf: not summarized: open it on SAM.gov
- B08_Att_03_GRCA257282_100P_FinalCD_Addendum_1.pdf: not summarized: open it on SAM.gov
- B08_Att_04_GRCA257282_Geotechnical_Recommendation_TM_May2025.pdf: not summarized: open it on SAM.gov
- B08_Att_09_Solit_PSP_Vol_I_PastPerf_REQD.pdf: not summarized: open it on SAM.gov
- B08_Att_10_Solit_PSP_Vol_II_BidBond.pdf: not summarized: open it on SAM.gov
- B08_Att_13_Solit_PSP_Vol_II_SubKPlan_REQD_RELEASED_v2_Mar25.pdf: not summarized: open it on SAM.gov
- B08_Att_08_Solit_PSP_Vol_I_Exp_REQD.pdf: not summarized: open it on SAM.gov
- B08_Att_11_Solit_PSP_Vol_II_Equals.pdf: not summarized: open it on SAM.gov
- B08_Att_12_Solit_PSP_Vol_II_GenRefs.pdf: not summarized: open it on SAM.gov
- B08_Att_07_GRCA_257282_Price_Schedule.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B09_Amendment_01_GRCA257282_Access_Road_100P_Final_CD_DRAWINGS_01.pdf: not summarized: open it on SAM.gov
- B08_Att_06_Wage_Determination_(1).pdf: not summarized: open it on SAM.gov
- B08_Att_01c_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part3.pdf: not summarized: open it on SAM.gov
- B08_Att_01a_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part1.pdf: not summarized: open it on SAM.gov
- B08_Att_01b_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part2.pdf: not summarized: open it on SAM.gov
- B08_Att_01d_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part4.pdf: not summarized: open it on SAM.gov
- B08_Att_01e_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part5_1.pdf: not summarized: open it on SAM.gov
- B08_Att_01e_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part5.pdf: not summarized: open it on SAM.gov
- B08_Att_05_Hazardous_Materials_Investigation_Report_South_Rim_WWTP.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Build a new 0.65 MGD membrane bio-reactor wastewater treatment plant at the existing plant site, including utilities, site power, electrical, instrumentation and controls, and admin/support buildings
- Keep the existing plant running (by NPS staff) until the new plant is accepted, then fully demolish and remove the old plant
- Build a compost facility at the plant (CLIN 0020)
- Improve and extend the access road to the facility (CLIN 0040)
- Provide 12 months of operations and maintenance support after startup (CLIN 0030)
- Site work: grading, paving, fencing and relocation of existing storage
- Startup and commissioning of the treatment process, including operator training and regulatory coordination
- Priced options: radon gas testing (Option A) and an active radon mitigation system (Option B)
- Contract type
- Firm-fixed-price construction contract (negotiated RFP, best value tradeoff), with two priced option line items
- Period of performance
- 02/01/2027 to 02/01/2030 per the solicitation; work must start within 10 days of notice to proceed and be complete 1,095 days after notice to proceed. See red flags: Amendment 2 changed the assumed notice-to-proceed date used for the Factor 2 schedule to April 1, 2027.
- Place of performance
- South Rim Village, Grand Canyon National Park, Arizona
- Estimated value
- Magnitude of construction: more than $10,000,000 (no more precise estimate given)
- How they'll choose
- Best value tradeoff (FAR Part 15) with no required discussions. Non-price factors 1 to 4 are in descending order of importance; all non-price factors combined are about equal to price.
- Offers due
- November 2, 2026, 2:00 PM Mountain Time (SAM response deadline; the SF 1442 also shows 11/02/2026 and 1400). The Amendment 5 form was unreadable, so any later change to the date is unknown. (from the version posted Sep 18, 2026; amended since)
- How to submit
- Email only, to Contracting Officer Tim Burger (timothy_burger@ios.doi.gov), Contract Specialist Kristin Tauber (Kristin_tauber@ios.doi.gov) and CS_DSC_Proposal_Submission@nps.gov
- Page limits
- Factor 1: 8-page prime narrative plus 5 pages per key subcontractor (the heading says 13 pages); Factor 2: 8 pages (schedule chart not counted); Factor 3: 5 pages
What they'll judge offers on
- Factor 1: Technical Experience
- Factor 2: Technical Approach (greatest emphasis on realism and feasibility of the execution and commissioning approach)
- Factor 3: Management Approach
- Factor 4: Key Personnel Experience
- Factor 5: Past Performance
- Factor 6: Small Business Participation (small businesses get maximum credit)
- Price (evaluated for fairness, reasonableness and unbalanced line items)
What to include when you submit
- Email subject line format: 140P2026R0101, GRCA 257282 REPLACE WWTP SOUTH RIM, email x of x
- Send Volume I (technical) and Volume II (business and price) as separate email attachments; each attachment no larger than 38 MB and each email no larger than 100 MB
- Volume I folders: Technical Experience, Technical Approach, Management Approach, Key Personnel Experience, Past Performance, Small Business Participation
- Volume II: SF 1442 (blocks 14-20c signed by an authorized official), amendment acknowledgments, Section B price schedule with a schedule of values for each line item, SF 24 bid bond (or other bid guarantee), Section K reps and certs, General References form, and a subcontracting plan if you are a large business
- Past performance: send the Past Performance Questionnaire to your references and include copies in Volume I; also disclose any less-than-satisfactory performance
- Include a Critical Path Gantt chart schedule and resumes for the Project Manager, Construction Superintendent and Quality Control Manager
- Questions must be emailed to the Contracting Officer and Contract Specialist at least 7 days before the due date
- Offerors must confirm that their proposals were received
- Acknowledge all amendments and address FAR 52.229-11
- Price in all federal, state and local taxes (project is not tax exempt) and complete Attachment 13 (price schedule)
Not in the notice text
- Whether the Amendment 5 SF 30 changed the offer due date or other terms (that form could not be read)
- Whether the September 16, 2026 site visit was mandatory
- Bond amounts and when performance and payment bonds are due after award (SF 1442 block 12 text was not readable)
- What the Section L passage about firms 'under these circumstances' not being considered for award refers to (it was in a part of the solicitation not provided)
- Answers to offeror questions in Amendments 3 and 5, and the 'What Evaluators Will Ask' document in Amendment 2
- Project specifications, drawings, wage determination, hazardous materials report and geotechnical report
- Price schedule details (Attachment 13 spreadsheet was not read)
- Relative importance of Factors 5 and 6 compared with Factors 1 to 4
- Funding status and award timing (the notice says it is unfunded)
- Whether Section J, K and early Section L (including site visit rules and bid guarantee details) have extra conditions not provided
Notice details
Notice type, codes, versions and files
- Posted
- Sep 18, 2026
- Notice type
- Solicitation
- Office
- DSC Contracting Services Division, Denver, CO
- Product/service code
- Y1ND · Construction of Sewage and Waste Facilities
- Business type
- Energy, fuel & utilities (FedReady's grouping, from NAICS 221320)
- Versions
12 versions have been posted, newest first.
- Nov 16, 2026 · Amendment 0009Due Dec 18, 2026
- Nov 10, 2026 · Amendment 0008Due Dec 18, 2026 (changed)
- Oct 28, 2026 · Amendment 0007Due Nov 18, 2026
- Oct 27, 2026 · Amendment 0006Due Nov 18, 2026
- Oct 16, 2026 · Amendment 0005Due Nov 18, 2026 (changed)
- Sep 18, 2026 · Amendment 0004 (this version)Due Nov 2, 2026
- Sep 3, 2026 · Amendment 0003Due Nov 2, 2026
- Sep 2, 2026 · Amendment 0002Due Nov 2, 2026
- Aug 11, 2026 · Amendment 0001Due Nov 2, 2026
- Aug 7, 2026 · SolicitationDue Nov 2, 2026
- Aug 1, 2026 · Special NoticeDate Nov 2, 2026
- Jul 31, 2026 · SolicitationDue Nov 2, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- Operations and Maintenance (O&M) Services for the SBIWTPThe International Boundary and Water Commission: US-Mexico (USIBWC) wants a contractor to operate and maintain the South Bay International Wastewater Treatment Plant (SBIWTP) in…
- Mike Monroney Aeronautical Center (MMAC) Industrial Waste Water Treatment Plant UpgradesSolicitation 6973GH-27-R-00005 is a total small business set-aside: only small businesses can bid.
- Rosebud Lift Station ConstructionThe Indian Health Service (IHS), Division of Engineering Services in Seattle, wants a contractor under solicitation 75H70127R00007 to remove and replace the sewage lift station…
- Wilson Lake Sewage Lagoon Project (Minooka and Lucas Parks), USACE Kansas CityThe U.S. Army Corps of Engineers, Kansas City District, plans a total small business set-aside invitation for bid (IFB: a sealed-bid solicitation) for sewer upgrades at Minooka…