Solicitation
GRCA 257282 - Replace Wastewater Plant at South Ri
Department of the Interior · National Park Service
AI summary Beta
This summary may miss requirements: 49 of 61 attachments weren't read (Sol_140P2026R0101_Amd_0004.pdf, B09_Amendment_04_SF30_0004.pdf and 47 more). Check the attachments on SAM.gov.
Solicitation 140P2026R0101: the National Park Service (Denver Service Center) wants a contractor to build a new wastewater treatment plant at the South Rim Village, Grand Canyon National Park, Arizona, plus a compost facility, access road work and 12 months of operational support. It is open to all businesses (full and open competition), size over $10,000,000, with a bid guarantee required. The response due date is December 18, 2026, 3:00 PM Mountain, and Amendment 0009 says a later amendment will set a new date.
Who can bid (6)
- Bid guarantee (Standard Form 24 bid bond or other suitable guarantee) sent with the offer From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Current, active SAM.gov registration when the offer is submitted From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Firms that helped develop the design or specifications cannot be the prime or a subcontractor From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
Show all 6Show fewer
- Prime and key subcontractors show recent wastewater treatment plant experience, with the prime self-performing at least 40% of cost (excluding materials) to count as prime experience From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Project manager, construction superintendent and quality control manager with comparable experience; four key trade firms named and kept for the contract From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Past performance information for the offeror and key subcontractors From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
How to submit: Email only, to the contracting officer, the contract specialist and CS_DSC_Proposal_Submission@nps.gov; no other delivery method is accepted. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
From the version posted Nov 16, 2026.
- Serious: Bid guarantee required with the offer. A bid bond must be in the offer; a small business needs a surety (bond company) willing to back a project of more than $10,000,000. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Serious: Unfunded requirement. The project has no funding yet; the contract will be awarded only if and when funds become available, so the award date is open. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Serious: Large, specialized wastewater plant project. Magnitude is more than $10,000,000, and evaluators score recent wastewater plant work, startup and commissioning experience, and the prime's self-performance (at least 40% of cost); a firm without this record will score poorly. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
Show all 10Show fewer
- Worth checking: Questions were due Oct 29, 2026. Check the amendments for the agency's answers. From Sol_140P2026R0101_Amd_0008.pdf
- Worth checking: Liquidated damages of $5,856.43 per day. Finishing late costs the contractor this amount for each calendar day of delay. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Worth checking: Remote Grand Canyon site and 1,095-day schedule. Work must finish not later than 1,095 days after notice to proceed, in a remote, high-visitor area with winter weather and limited staging; the schedule is scored on realism. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Worth checking: Key personnel and key trade firms locked in. The four key trade firms and named key personnel are permanent unless the contracting officer approves a change, so teaming must be settled before submitting. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Worth checking: Design firms barred from bidding. Any firm that helped develop the design or specifications cannot be the prime or a subcontractor; the proposal will not be considered. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Minor: Email-only submission with strict file sizes. Proposals go by email in two volumes with attachments under 38 MB each; any other delivery method is rejected. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
- Minor: Prices must include all taxes. The project is not tax exempt, so federal, state and local taxes belong in the price. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf
Read from the notice and 12 attachments. 49 of 61 not read. Show which files.
- B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf (read)
- Sol_140P2026R0101_Amd_0010.pdf (read)
- B09_Amendment_10_SF_30_0010.pdf (read)
- Sol_140P2026R0101_Amd_0009.pdf (read)
- B09_Amendment_09_SF_30_0009.pdf (read)
- Sol_140P2026R0101_Amd_0008.pdf (read)
- Sol_140P2026R0101_Amd_0007.pdf (read)
- B09_Amendment_07_SF_30_0007.pdf (read)
- Sol_140P2026R0101_Amd_0006.pdf (read)
- B09_Amendment_06_SF_30_0006.pdf (read)
- Sol_140P2026R0101_Amd_0005.pdf (read)
- B09_Amendment_05_SF_30_0005.pdf (read)
- Sol_140P2026R0101_Amd_0004.pdf: not summarized: open it on SAM.gov
- B09_Amendment_04_SF30_0004.pdf: not summarized: open it on SAM.gov
- Sol_140P2026R0101_Amd_0003.pdf: not summarized: open it on SAM.gov
- B09_Amendment_03_SF30_0003.pdf: not summarized: open it on SAM.gov
- Sol_140P2026R0101_Amd_0002.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_SF30_0002.pdf: not summarized: open it on SAM.gov
- Sol_140P2026R0101_Amd_01.pdf: not summarized: open it on SAM.gov
- B09_Amendment_01_SF30_01.pdf: not summarized: open it on SAM.gov
- Sol_140P2026R0101.pdf: not summarized: open it on SAM.gov
- B09_Amendment_01_GRCA257282_CD_Specifications_June2025_01.pdf: not summarized: open it on SAM.gov
- B09_Amendment_01_RCA257282_Access_Road_100P_Final_CD_Specifications_01.pdf: not summarized: open it on SAM.gov
- B09_Amendment_10_GRCA257282_FinalCD_Addendum_08_wSeal_0010.pdf: not summarized: open it on SAM.gov
- B09_Amendment_10_INV_100751_LTF_94239_Grand_Canyon_South_Rim_WWTP_Final_Permit_0010.pdf: not summarized: open it on SAM.gov
- B09_Amendment_10_SR_NPDES_AZ0022152_GCSR_Permit_SIGNED_ISSUED_122222_0010.pdf: not summarized: open it on SAM.gov
- B09_Amendment_09_Answers_to_Questions_0009.pdf: not summarized: open it on SAM.gov
- B09_Amendment_07_Answers_to_Questions_0007.pdf: not summarized: open it on SAM.gov
- B09_Amendment_07_GRCA257282_FinalCD_Addendum_07_0007.pdf: not summarized: open it on SAM.gov
- B09_Amendment_06_GRCA_25782_Site_Visit_Sign_in_Sheet_0006.jpeg: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B09_Amendment_06_B08_Att_13_Solit_PSP_Vol_II_SubKPlan_0006.docx: not summarized: open it on SAM.gov
- B09_Amendment_06_GRCA257282_FinalCD_Addendum_06_0006.pdf: not summarized: open it on SAM.gov
- B09_Amendment_06_Answers_to_Questions_0006.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_Answers_to_Questions_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_02_SCADA_wSeal_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_04_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_05_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA_Final_Individual_Specs_0005.zip: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B09_Amendment_03_Answers_to_Questions_0003.pdf: not summarized: open it on SAM.gov
- B09_Amendment_03_GRCA257282_FinalCD_Addendum_03_Compiled_wSeal_0003.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_What_Evaluators_Will_Ask_for_Each_Factor_2_0002.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_GRCA_257282_SR_WWTP_PreBid_Mtg_presentation_(8-11-26)_FINAL_0002.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_GRCA_257282_Precon_SignIn_0002.pdf: not summarized: open it on SAM.gov
- B08_Att_03_GRCA257282_100P_FinalCD_Addendum_1.pdf: not summarized: open it on SAM.gov
- B08_Att_04_GRCA257282_Geotechnical_Recommendation_TM_May2025.pdf: not summarized: open it on SAM.gov
- B08_Att_09_Solit_PSP_Vol_I_PastPerf_REQD.pdf: not summarized: open it on SAM.gov
- B08_Att_10_Solit_PSP_Vol_II_BidBond.pdf: not summarized: open it on SAM.gov
- B08_Att_13_Solit_PSP_Vol_II_SubKPlan_REQD_RELEASED_v2_Mar25.pdf: not summarized: open it on SAM.gov
- B08_Att_08_Solit_PSP_Vol_I_Exp_REQD.pdf: not summarized: open it on SAM.gov
- B08_Att_11_Solit_PSP_Vol_II_Equals.pdf: not summarized: open it on SAM.gov
- B08_Att_12_Solit_PSP_Vol_II_GenRefs.pdf: not summarized: open it on SAM.gov
- B08_Att_07_GRCA_257282_Price_Schedule.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B09_Amendment_01_GRCA257282_Access_Road_100P_Final_CD_DRAWINGS_01.pdf: not summarized: open it on SAM.gov
- B08_Att_06_Wage_Determination_(1).pdf: not summarized: open it on SAM.gov
- B08_Att_01c_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part3.pdf: not summarized: open it on SAM.gov
- B08_Att_01a_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part1.pdf: not summarized: open it on SAM.gov
- B08_Att_01b_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part2.pdf: not summarized: open it on SAM.gov
- B08_Att_01d_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part4.pdf: not summarized: open it on SAM.gov
- B08_Att_01e_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part5_1.pdf: not summarized: open it on SAM.gov
- B08_Att_01e_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part5.pdf: not summarized: open it on SAM.gov
- B08_Att_05_Hazardous_Materials_Investigation_Report_South_Rim_WWTP.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Build a new 0.65 MGD (million gallons a day) membrane bio-reactor wastewater treatment plant at the existing plant site (CLIN 0010)
- Demolish and remove the existing plant; keep the old plant running until the Government accepts the new one
- Build the compost facility (CLIN 0020) and improve and extend the access road (CLIN 0040)
- Provide 12 months of operational support for the new plant (CLIN 0030)
- Start up and commission the treatment processes, including operator training and testing
- Option A: radon gas testing (CLIN 0050); Option B: active radon mitigation system (CLIN 0060); the contracting officer may exercise options within 60 days after award
- Complete all work within 1,095 days after notice to proceed, which is assumed to be February 1, 2027
- Contract type
- Firm-fixed-price (FFP): one set price, whatever the work ends up costing. Four base line items plus two priced options.
- Period of performance
- February 1, 2027 to February 1, 2030 (as shown on the solicitation form and amendments); complete the work not later than 1,095 days after notice to proceed, assuming notice to proceed by February 1, 2027. Options: radon testing and active radon mitigation system.
- Place of performance
- Grand Canyon National Park, South Rim Village, Arizona
- Estimated value
- Magnitude of construction: more than $10,000,000.00 (a size range the solicitation gives, not a Government estimate)
- How they'll choose
- Best value tradeoff: the Government may pay more than the lowest price when a higher-priced proposal's benefits justify it. Awarded without discussions if possible.
- Offers due
- December 18, 2026, 3:00 PM Mountain
- How to submit
- Email only, to the contracting officer, the contract specialist and CS_DSC_Proposal_Submission@nps.gov; no other delivery method is accepted
- Page limits
- Factor 1 prime experience narrative: 8 pages, plus a 5-page narrative for each key subcontractor (heading says 13 page limit); Factor 2 technical approach: 8 pages (the schedule chart does not count); Factor 3 management approach: 5 pages
What they'll judge offers on
- Factor 1, Technical Experience: relevance of the prime's and key subcontractors' past wastewater plant projects, subcontractor experience, overall capability and performance risk
- Factor 2, Technical Approach: construction and commissioning plan, means and methods, schedule (critical path chart and narrative), risks, protection of natural, cultural and historic resources
- Factor 3, Management Approach: capacity, roles and responsibilities, safety, quality management, communication and reporting
- Factor 4, Key Personnel Experience: project manager, construction superintendent, quality control manager, and the four key trades
- Factor 5, Past Performance: surveys, CPARS (Contractor Performance Assessment Reporting System) reports and other sources
- Factor 6, Small Business Participation: small business prime offers get the maximum credit
- Price: evaluated for fairness, reasonableness and unbalanced line items; options are added to the base price
What to include when you submit
- Send two separate volumes, each as separate email attachments: Volume I (technical) and Volume II (business and price)
- Email subject line: 140P2026R0101, GRCA 257282 REPLACE WWTP SOUTH RIM, email x of x
- Each attachment no larger than 38 MB and each email no larger than 100 MB; verify the Government received the proposal
- Volume I: folders for Factors 1 to 6; one electronic copy only
- Factor 1: up to five similar projects completed within the last eight years for the prime; up to three projects completed in the last five years for each key subcontractor doing most of the treatment process and civil/site work
- Prime contractor experience means work done as a general contractor managing multiple subcontractors while self-performing at least 40% of the contract cost, excluding materials
- Factor 2: include a project schedule (critical path Gantt chart) that shows completion in the required period, assuming notice to proceed on February 1, 2027
- Factor 4: résumés for the project manager, construction superintendent and quality control manager; name the firms for the four key trades (process, mechanical/plumbing, electrical, civil)
- Factor 5: send the Past Performance Questionnaire to each client reference, include a copy of each in Volume I, and add a narrative on any less-than-satisfactory past performance
- Volume II: signed Standard Form 1442 (blocks 14 through 20C), acknowledgment of all amendments, Section B price schedule with a schedule of values for each line item, Standard Form 24 bid bond (or other suitable bid guarantee), Section K representations and certifications, and the General References form
- Large businesses must also send a small business subcontracting plan; small businesses do not
After award, you must have
- Performance and payment bonds after award (the solicitation form's bond fields could not be read) From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf:
…give the required performance and payment bonds within the…
Not in the notice text
- Much of the solicitation is attached but not read: the middle of the main solicitation file (including the bond fields, the pre-proposal site visit details and clauses), the original solicitation and Amendments 0001 to 0004, the question and answer files, specifications, drawings, the wage determination, the price schedule spreadsheet and the past performance and bid bond forms
- Whether the pre-proposal site visit is required, and its date; the solicitation points to Section L, and sign-in sheets are attached to Amendments 0002 and 0006 but were not read
- Which wage rule applies (a Davis-Bacon wage determination is attached but not read)
- The new response due date and question deadline; Amendment 0009 says they will be set in a later amendment
- Whether performance and payment bonds are required and their amounts (the solicitation form's fields could not be read; check the form on SAM.gov)
- Liability insurance amounts under clause 1452.228-70 (clause listed, text not read)
- The set-aside: SAM.gov does not state one, and the solicitation says unrestricted full and open competition
Notice details
Notice type, codes, versions and files
- Posted
- Nov 16, 2026
- Notice type
- Solicitation
- Office
- DSC Contracting Services Division, Denver, CO
- Product/service code
- Y1ND · Construction of Sewage and Waste Facilities
- Business type
- Energy, fuel & utilities (FedReady's grouping, from NAICS 221320)
- Versions
12 versions have been posted, newest first.
- Nov 16, 2026 · Amendment 0009 (this version)Due Dec 18, 2026
- Nov 10, 2026 · Amendment 0008Due Dec 18, 2026 (changed)
- Oct 28, 2026 · Amendment 0007Due Nov 18, 2026
- Oct 27, 2026 · Amendment 0006Due Nov 18, 2026
- Oct 16, 2026 · Amendment 0005Due Nov 18, 2026 (changed)
- Sep 18, 2026 · Amendment 0004Due Nov 2, 2026
- Sep 3, 2026 · Amendment 0003Due Nov 2, 2026
- Sep 2, 2026 · Amendment 0002Due Nov 2, 2026
- Aug 11, 2026 · Amendment 0001Due Nov 2, 2026
- Aug 7, 2026 · SolicitationDue Nov 2, 2026
- Aug 1, 2026 · Special NoticeDate Nov 2, 2026
- Jul 31, 2026 · SolicitationDue Nov 2, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- Operations and Maintenance (O&M) Services for the SBIWTPThe International Boundary and Water Commission: US-Mexico (USIBWC) wants a contractor to operate and maintain the South Bay International Wastewater Treatment Plant (SBIWTP) in…
- Mike Monroney Aeronautical Center (MMAC) Industrial Waste Water Treatment Plant UpgradesSolicitation 6973GH-27-R-00005 is a total small business set-aside: only small businesses can bid.
- Rosebud Lift Station ConstructionThe Indian Health Service (IHS), Division of Engineering Services in Seattle, wants a contractor under solicitation 75H70127R00007 to remove and replace the sewage lift station…
- Wilson Lake Sewage Lagoon Project (Minooka and Lucas Parks), USACE Kansas CityThe U.S. Army Corps of Engineers, Kansas City District, plans a total small business set-aside invitation for bid (IFB: a sealed-bid solicitation) for sewer upgrades at Minooka…