Solicitation
GRCA 257282 - Replace Wastewater Plant at South Ri
Department of the Interior · National Park Service
AI summaryThe National Park Service (NPS), through its Denver Service Center, wants a contractor to build a new 0.65 million gallons per day membrane bio-reactor wastewater treatment plant (a plant that filters wastewater through membranes) at Grand Canyon South Rim Village, Arizona. The contract also covers an access road, a compost facility and 12 months of operations support. It is open to all firms (full and open competition) and is currently unfunded. The response due date is November 18, 2026, 1:00 PM Mountain (an amendment moved it to Nov 18, 2026, 1:00 AM MST · 3:00 AM Eastern), moved from November 2, 2026 by Amendment 0006. More in the summary
A newer version of this notice was posted Oct 27, 2026. It moves the due date from Nov 2, 2026 to Nov 18, 2026, which is the date shown on this page. See the latest version.
AI summary Beta
Summary of the version posted Oct 16, 2026. The notice was amended Oct 27, 2026. The due date moved from Nov 18, 2026 to Nov 18, 2026. Check what else changed on SAM.gov. This summary may miss requirements: 36 of 48 attachments weren't read (B09_Amendment_01_SF30_01.pdf, Sol_140P2026R0101.pdf and 34 more). Check the attachments on SAM.gov.
The National Park Service (NPS), through its Denver Service Center, wants a contractor to build a new 0.65 million gallons per day membrane bio-reactor wastewater treatment plant (a plant that filters wastewater through membranes) at Grand Canyon South Rim Village, Arizona. The contract also covers an access road, a compost facility and 12 months of operations support. It is open to all firms (full and open competition) and is currently unfunded. The response due date is November 18, 2026, 1:00 PM Mountain, moved from November 2, 2026 by Amendment 0006.
Who can bid (4)
- Open to all firms: the notice is full and open competition with no set-aside program. SAM.gov does not list a set-aside.
- Hold a current, active System for Award Management (SAM.gov) registration when the proposal is submitted.
- Submit a bid bond (Standard Form 24) or other suitable bid guarantee with the proposal.
Show all 4Show fewer
- Not have helped design or write the specifications for this project, as a prime or consultant. Such firms and teams that include them will not be considered.
How to submit: Email only, to Contracting Officer Tim Burger (timothy_burger@ios.doi.gov), Contract Specialist Kristin Tauber (Kristin_tauber@ios.doi.gov) and CS_DSC_Proposal_Submission@nps.gov. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (9)
- Serious: Bid bond with the proposal, then performance and payment bonds. A project over $10 million needs a surety (bonding company) that will issue a bid bond now and performance and payment bonds after award.
- Worth checking: Wastewater plant experience bar for you and your subcontractors. Factor 1 asks for comparable plant projects, a prime role self-performing at least 40% of cost, and separate narratives for the key process and civil subcontractors.
- Worth checking: Currently unfunded requirement. The Government expects funds but will award only if and when they become available, so an award may be delayed or may not happen.
Show all 9Show fewer
- Worth checking: Liquidated damages of $5,856.43 per calendar day. Finishing late costs this amount for each day of delay, on a remote site with winter weather, access limits and long-lead equipment.
- Worth checking: Key trade firms are locked in at proposal. You must name the firms for process, mechanical/plumbing, electrical and civil work, and changing them later needs the Contracting Officer's approval.
- Minor: Taxes must be in your price. Federal, state and local taxes must be included in the proposal because the project is not tax exempt.
- Minor: Notice to proceed date differs between documents. Section H assumes a notice to proceed by February 1, 2027, while Amendment 0002 changes the assumed date for the Factor 2 schedule to April 1, 2027. Ask the Contracting Officer which date governs completion.
- Minor: The site visit was Sep 16, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered.
- Minor: Email-only submission with size caps. A proposal sent any other way is not accepted, so large files must be split across several emails.
Read from the notice and 12 attachments. 36 of 48 not read. Show which files.
- B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf (read)
- Sol_140P2026R0101_Amd_0006.pdf (read)
- B09_Amendment_06_SF_30_0006.pdf (read)
- Sol_140P2026R0101_Amd_0005.pdf (read)
- B09_Amendment_05_SF_30_0005.pdf (read)
- Sol_140P2026R0101_Amd_0004.pdf (read)
- B09_Amendment_04_SF30_0004.pdf (read)
- Sol_140P2026R0101_Amd_0003.pdf (read)
- B09_Amendment_03_SF30_0003.pdf (read)
- Sol_140P2026R0101_Amd_0002.pdf (read)
- B09_Amendment_02_SF30_0002.pdf (read)
- Sol_140P2026R0101_Amd_01.pdf (read)
- B09_Amendment_01_SF30_01.pdf: not summarized: open it on SAM.gov
- Sol_140P2026R0101.pdf: not summarized: open it on SAM.gov
- B09_Amendment_01_GRCA257282_CD_Specifications_June2025_01.pdf: not summarized: open it on SAM.gov
- B09_Amendment_01_RCA257282_Access_Road_100P_Final_CD_Specifications_01.pdf: not summarized: open it on SAM.gov
- B09_Amendment_06_GRCA_25782_Site_Visit_Sign_in_Sheet_0006.jpeg: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B09_Amendment_06_B08_Att_13_Solit_PSP_Vol_II_SubKPlan_0006.docx: not summarized: open it on SAM.gov
- B09_Amendment_06_GRCA257282_FinalCD_Addendum_06_0006.pdf: not summarized: open it on SAM.gov
- B09_Amendment_06_Answers_to_Questions_0006.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_Answers_to_Questions_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_02_SCADA_wSeal_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_04_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA257282_FinalCD_Addendum_05_0005.pdf: not summarized: open it on SAM.gov
- B09_Amendment_05_GRCA_Final_Individual_Specs_0005.zip: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B09_Amendment_03_Answers_to_Questions_0003.pdf: not summarized: open it on SAM.gov
- B09_Amendment_03_GRCA257282_FinalCD_Addendum_03_Compiled_wSeal_0003.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_What_Evaluators_Will_Ask_for_Each_Factor_2_0002.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_GRCA_257282_SR_WWTP_PreBid_Mtg_presentation_(8-11-26)_FINAL_0002.pdf: not summarized: open it on SAM.gov
- B09_Amendment_02_GRCA_257282_Precon_SignIn_0002.pdf: not summarized: open it on SAM.gov
- B08_Att_03_GRCA257282_100P_FinalCD_Addendum_1.pdf: not summarized: open it on SAM.gov
- B08_Att_04_GRCA257282_Geotechnical_Recommendation_TM_May2025.pdf: not summarized: open it on SAM.gov
- B08_Att_09_Solit_PSP_Vol_I_PastPerf_REQD.pdf: not summarized: open it on SAM.gov
- B08_Att_10_Solit_PSP_Vol_II_BidBond.pdf: not summarized: open it on SAM.gov
- B08_Att_13_Solit_PSP_Vol_II_SubKPlan_REQD_RELEASED_v2_Mar25.pdf: not summarized: open it on SAM.gov
- B08_Att_08_Solit_PSP_Vol_I_Exp_REQD.pdf: not summarized: open it on SAM.gov
- B08_Att_11_Solit_PSP_Vol_II_Equals.pdf: not summarized: open it on SAM.gov
- B08_Att_12_Solit_PSP_Vol_II_GenRefs.pdf: not summarized: open it on SAM.gov
- B08_Att_07_GRCA_257282_Price_Schedule.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B09_Amendment_01_GRCA257282_Access_Road_100P_Final_CD_DRAWINGS_01.pdf: not summarized: open it on SAM.gov
- B08_Att_06_Wage_Determination_(1).pdf: not summarized: open it on SAM.gov
- B08_Att_01c_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part3.pdf: not summarized: open it on SAM.gov
- B08_Att_01a_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part1.pdf: not summarized: open it on SAM.gov
- B08_Att_01b_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part2.pdf: not summarized: open it on SAM.gov
- B08_Att_01d_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part4.pdf: not summarized: open it on SAM.gov
- B08_Att_01e_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part5_1.pdf: not summarized: open it on SAM.gov
- B08_Att_01e_GRCA257282_CD_Drawings_and_Details_Combined_June2025_Part5.pdf: not summarized: open it on SAM.gov
- B08_Att_05_Hazardous_Materials_Investigation_Report_South_Rim_WWTP.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Build a new 0.65 million gallons per day membrane bio-reactor wastewater treatment plant at the existing plant site, with administrative and support buildings, utilities, site power, electrical and controls
- Demolish and remove the existing plant after the Government accepts the new one; the old plant keeps running under NPS staff until then
- Site work: grading, paving, fencing, relocation of existing storage, and access road improvements and extension
- Build a compost facility (contract line item number, CLIN, 0020: one priced line of the order)
- Provide a 12-month operational support period (CLIN 0030)
- Start up and commission the treatment processes, including operator training and testing
- Option A: radon gas testing. Option B: active radon mitigation system. The Government may exercise these within 60 days after award
- Finish all work ready for use not later than 1,095 days after the notice to proceed (the order to start work)
- Contract type
- Firm-fixed-price (FFP): one set price, whatever the work ends up costing. Four base lump-sum line items plus two separately priced options.
- Period of performance
- Stated as 02/01/2027 to 02/01/2030. Work must be complete not later than 1,095 days after notice to proceed, plus separately priced options.
- Place of performance
- Grand Canyon National Park, South Rim Village, Arizona
- Estimated value
- Magnitude of construction stated as more than $10,000,000.00
- How they'll choose
- Best value tradeoff (Best Value Continuum, FAR Part 15.1). The Government may pay more than the lowest price and intends to award without discussions. Non-price factors combined are approximately equally important to price.
- Offers due
- November 18, 2026, 1:00 PM Mountain (from the version posted Oct 16, 2026; amended since)
- How to submit
- Email only, to Contracting Officer Tim Burger (timothy_burger@ios.doi.gov), Contract Specialist Kristin Tauber (Kristin_tauber@ios.doi.gov) and CS_DSC_Proposal_Submission@nps.gov
- Page limits
- Factor 1: 8 pages for the prime contractor narrative (the section header says 13 pages in all) and 5 pages for each key subcontractor narrative. Factor 2: 8 pages (the schedule chart is not counted). Factor 3: 5 pages.
What they'll judge offers on
- Factor 1, Technical Experience: relevance of the prime contractor's and key subcontractors' wastewater plant projects, subcontractor experience, schedule and budget record
- Factor 2, Technical Approach: civil work and plant installation, commissioning, means and methods, schedule, risks, natural, cultural and historic resources
- Factor 3, Management Approach: capacity, roles and responsibilities, safety, quality management, communication and reporting
- Factor 4, Key Personnel Experience: project manager, construction superintendent, quality control manager, and key trades
- Factor 5, Past Performance
- Factor 6, Small Business Participation: small businesses get the maximum credit and need not submit documentation
- Price: evaluated for fairness and reasonableness, with options added to the base price
What to include when you submit
- Send two volumes, Volume I (technical) and Volume II (business and price), each as separate email attachments. Subject line: 140P2026R0101, GRCA 257282 REPLACE WWTP SOUTH RIM, email x of x.
- Keep each attachment under 38 MB and each email under 100 MB. Confirm the Government received your proposal.
- Send questions only by email to the Contracting Officer and Contract Specialist, a minimum of 7 days before the response due date and time.
- Factor 1: the prime contractor narrative may include up to five relevant projects completed within the last eight years. Prime experience means managing multiple subcontractors while self-performing at least 40% of the contract cost, excluding materials.
- Factor 1: for each subcontractor doing most of the treatment process work and civil/site work, send a five-page narrative with up to three projects completed in the last five years.
- Factor 2: include a project-specific critical path schedule (Gantt chart) that shows completion within the required period, assuming a notice to proceed of April 1, 2027 (Amendment 0002).
- Factor 4: send resumes for the Project Manager, Construction Superintendent and Quality Control Manager, and describe your experience with the four key trades (process services, mechanical/plumbing, electrical, civil) and whether you have worked with the proposed firms.
- Factor 5: send a Past Performance Questionnaire (PPQ) to references for you and each key subcontractor, include copies in Volume I, and add a narrative disclosing any less-than-satisfactory performance. A Contractor Performance Assessment Reporting System (CPARS: the government past performance database) report may replace a PPQ.
- Volume II: Standard Form 1442 (blocks 14 through 20c) signed by someone who can bind the company, plus acknowledgment of all amendments.
- Volume II: the Section B price schedule (Attachment 13) with a separate schedule of values (SOV: price broken into major work parts) for each line item, including the options.
- Volume II: a Standard Form 24 bid bond or other suitable bid guarantee, the Section K representations and certifications, and the General References form.
- Large businesses must also submit a small business subcontracting plan; small businesses do not.
After award, you must have
- Give performance and payment bonds after award, within the time stated in the offer. From B08_GRCA_257282_140P2026R0101_SF1442_and_Clauses_7-30-26.pdf:
…failure of the Contractor to execute the contract and give the required performance and payment bonds within the…
Not in the notice text
- Text is incomplete: the middle of the main solicitation (including Section K and the Section L site visit instruction) was left out. The answers to questions, addenda, drawings, specifications, price schedule, bid bond and past performance forms are attached but not read.
- Whether the September 16, 2026 site visit was required is not in the text read. Its instruction is in Section L, which was only partly read.
- The wage rule for this construction work is not stated in the text read; a wage determination file (B08_Att_06_Wage_Determination_(1).pdf) is attached but not read.
- The bid guarantee amount and the Government's answers to bidder questions are in files that were not read.
- The order of importance of Factors 5 and 6, and the original SF 1442 hour for receiving proposals, could not be read clearly. Amendment 0006 gives only the new date, November 18, 2026.
- What the Government will ask for under Factor 2 is in 'What Evaluators Will Ask for Each Factor 2', which was attached but not read.
Eligibility and how to respond
- No set-aside: any business, large or small, can bid unless the notice says otherwise.
- How to submit, from the AI summary: Email only, to Contracting Officer Tim Burger (timothy_burger@ios.doi.gov), Contract Specialist Kristin Tauber (Kristin_tauber@ios.doi.gov) and CS_DSC_Proposal_Submission@nps.gov. Check it in the notice before you send anything.
- Construction contracts over $2,000 pay at least the local Davis-Bacon wage rates, from the wage determination in the solicitation. Price your labor from it: How to price a government contract, and how Davis-Bacon differs from the Service Contract Act.
Notice details
- Posted
- Aug 7, 2026
- Notice type
- Solicitation
- Office
- DSC Contracting Services Division, Denver, CO
- Product/service code
- Y1ND · Construction of Sewage and Waste Facilities
- Business type
- Energy, fuel & utilities (FedReady's grouping, from NAICS 221320)
- Versions
9 versions have been posted, newest first.
- Oct 27, 2026 · Amendment 0006Due Nov 18, 2026
- Oct 16, 2026 · Amendment 0005Due Nov 18, 2026 (changed)
- Sep 18, 2026 · Amendment 0004Due Nov 2, 2026
- Sep 3, 2026 · Amendment 0003Due Nov 2, 2026
- Sep 2, 2026 · Amendment 0002Due Nov 2, 2026
- Aug 11, 2026 · Amendment 0001Due Nov 2, 2026
- Aug 7, 2026 · Solicitation (this version)Due Nov 2, 2026
- Aug 1, 2026 · Special NoticeDate Nov 2, 2026
- Jul 31, 2026 · SolicitationDue Nov 2, 2026
- Related notices
Other notices that name this solicitation, or that this one names.
- GRCA 257282 - Replace South Rim Wastewater Treatment Plant, Grand Canyon, AZ · 140P2025R0093Posted earlier Jul 20, 2026 · Due Nov 2, 2026
- Attachments
Past awards and competition
Who has won work like this before, the likely incumbent, and what similar contracts paid, from USAspending.gov.
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- Operations and Maintenance (O&M) Services for the SBIWTPThe International Boundary and Water Commission: US-Mexico wants a contractor to run and maintain the South Bay International Wastewater Treatment Plant (SBIWTP) in San Ysidro,…
- Mike Monroney Aeronautical Center (MMAC) Industrial Waste Water Treatment Plant UpgradesThe Federal Aviation Administration (FAA) Mike Monroney Aeronautical Center is buying an industrial wastewater treatment plant (IWTP) upgrade in Oklahoma City under solicitation…
- Rosebud Lift Station Construction
- Design-Build Repair Storm Sewer Lines at U.S. Coast Guard Base San Juan, Puerto Rico Project Number: PN 15852459The U.S. Coast Guard plans an invitation for bid (IFB, a sealed price bid) set aside for service-disabled veteran-owned small businesses (SDVOSB) to repair storm sewer lines at…