Solicitation
Amendment 0006 to Provide Official RFI Responses, Update Solicitation Documents, Extend Proposal Due Date, & other Official Information
Department of Veterans Affairs
Response due Dec 1, 2026 · SDVOSB set-aside · Boise, ID
Market research, not a bid. Replying is free and tells Department of Veterans Affairs who could do this work. Send a short reply to the contracting contact; no price is needed. See the contact
A newer version of this notice was posted Nov 19, 2026. It moves the due date from Nov 25, 2026 to Dec 1, 2026, which is the date shown on this page. See the latest version.
AI summary Beta
Summary of the version posted Nov 10, 2026. The notice was amended Nov 19, 2026. The due date moved from Nov 25, 2026 to Dec 1, 2026. Check what else changed on SAM.gov. This summary may miss requirements: 2 of 9 attachments weren't read (Atch. 1_36C26027R0002 0006_RFI Log_531-25-102 Expand ER.xlsx, Atch. 5_36C26027R0002 0006_Drawings-rv1_531-25-102-Expand ED.pdf). Check the attachments on SAM.gov.
Only service-disabled veteran-owned small businesses (SDVOSBs) can bid on VA solicitation 36C26027R0002, Amendment 0006, to expand the Emergency Department at the Boise VA Medical Center in Idaho. The response due date is now November 25, 2026, 10:00 AM Mountain (12:00 PM Eastern). The work renovates 10,700 sf in Building 85 while the hospital stays open, with a total performance period of 443 calendar days from notice to proceed. This amendment replaces the drawings and specifications, revises the statement of work and adds a second round of questions.
Who can bid
- Service-disabled veteran-owned small business (SDVOSB) set-aside under FAR 19.14: only SDVOSBs can bid.
- Limits on subcontracting: for general construction, the firm will not pay more than 85% of the amount the government pays it to firms that are not certified SDVOSBs or veteran-owned small businesses (VOSBs). Cost of materials is excluded. From Atch. 8_36C26027R0002 0006_Clause Updates_531-25-102-Expand ED.pdf
- Past performance: completed projects in the past 6 years, with your firm as prime (one subcontractor project allowed). From 36C26027R0002 0006.pdf
How to submit: due November 25, 2026, 10:00 AM Mountain (12:00 PM Eastern). What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
- Serious: SDVOSB set-aside: only service-disabled veteran-owned small businesses can bid. SAM.gov lists the set-aside as SDVOSB (FAR 19.14). A business without that status cannot win this award.
- Serious: Work inside an active hospital emergency department. The department runs 24/7, so noisy work may be limited to off-hours and work is done in phases with strict infection control. This adds cost and schedule risk. From Atch. 2_36C26027R0002 0006_SOW-rv1_531-25-102-Expand ED.pdf
- Serious: Revised drawings and specifications replace the originals. Price only from the new documents. The old set is void, so any earlier pricing work must be checked against the new set. From 36C26027R0002 0006.pdf
Show all 10Show fewer
- Serious: Limit on subcontracting at 85% for general construction. At least 15% of what the government pays must go to your own SDVOSB or a similarly situated SDVOSB or VOSB, with materials left out. This limits how much you can sublet. From Atch. 8_36C26027R0002 0006_Clause Updates_531-25-102-Expand ED.pdf
- Worth checking: Response due date extended to November 25, 2026. Amendment 0006 moves the response due date to November 25, 2026, 10:00 AM Mountain. SAM.gov shows the same date and time. From 36C26027R0002 0006.pdf
- Worth checking: Past performance rules changed. Projects now count if completed in the last 6 years (it was 5). The narrative limit rose to 25 pages. Only one subcontractor project is allowed. From 36C26027R0002 0006.pdf
- Worth checking: Limited Notice to Proceed with no on-site work. Before construction starts, you get a Limited Notice to Proceed of up to 60 days for submittals and material orders. Costs there are before you can start site work. From Atch. 2_36C26027R0002 0006_SOW-rv1_531-25-102-Expand ED.pdf
- Worth checking: Noise and vibration limits. Loud or disruptive demolition next to occupied areas may be restricted, and work over the limits must be scheduled outside business hours at no added cost to the VA. From Atch. 2_36C26027R0002 0006_SOW-rv1_531-25-102-Expand ED.pdf
- Worth checking: Class IV infection control and pre-construction risk assessment. The infection control risk assessment (ICRA) and pre-construction risk assessment (PCRA) are mandatory execution constraints. Expect barriers, negative air and weekly inspections. From Atch. 2_36C26027R0002 0006_SOW-rv1_531-25-102-Expand ED.pdf
- Minor: Questions were due Nov 13, 2026. Check the amendments for the agency's answers. From 36C26027R0002 0006.pdf
Read from the notice and 7 attachments. 2 of 9 not read. Show which files.
- Atch. 3_36C26027R0002 0006_Specifications Vol. 1-rv1_531-25-102-Expand ED.pdf (read)
- Atch. 4_36C26027R0002 0006_Specifications Vol. 2-rv1_531-25-102-Expand ED.pdf (read)
- 36C26027R0002 0006.pdf (read)
- Atch. 2_36C26027R0002 0006_SOW-rv1_531-25-102-Expand ED.pdf (read)
- Atch. 6_36C26027R0002 0006_PCRA_531-25-102 Expand ER.pdf (read)
- Atch. 8_36C26027R0002 0006_Clause Updates_531-25-102-Expand ED.pdf (read)
- Atch. 7_36C26027R0002 0006_ICRA_531-25-102 Expand ER.pdf (read)
- Atch. 1_36C26027R0002 0006_RFI Log_531-25-102 Expand ER.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- Atch. 5_36C26027R0002 0006_Drawings-rv1_531-25-102-Expand ED.pdf: not read (it couldn't be opened): open it on SAM.gov
Full summary
What they want
- Renovate 10,700 sf on the first floor of Building 85 and expand the existing 5,700 sf emergency room to 8,900 sf
- Reconfigure and relocate 1,800 sf of adjacent space: the admitting office, corridors and ER waiting area
- Do demolition, new walls, flooring, ceilings, windows, millwork and finish work
- Do mechanical (heating and cooling), plumbing, medical gas, electrical, nurse call, security, fire alarm and sprinkler work, and possible asbestos or lead abatement
- Build in phases so the active Emergency Department keeps running 24/7
- Follow Class IV infection control rules: sealed barriers, negative air pressure, HEPA filtration (HEPA is a high-efficiency air filter), an anteroom
- Provide all labor, materials, equipment, testing and disposal of waste
- Submit contract submittals and material orders during a Limited Notice to Proceed (LNTP) of up to 60 calendar days; no on-site work is allowed during it
- Period of performance
- 443 calendar days from issuance of Notice to Proceed (NTP). A Limited Notice to Proceed of up to 60 calendar days runs inside that time. Construction NTP is anticipated for Spring 2027.
- Place of performance
- Boise VA Medical Center, 500 W. Fort Street, Boise, ID 83702
- Estimated value
- Not stated
- Offers due
- November 25, 2026, 10:00 AM Mountain (12:00 PM Eastern) (from the version posted Nov 10, 2026; amended since)
- Page limits
- Past performance narrative: no more than 25 pages in all, including table of contents and cover page. The Government will not evaluate pages past 25 or projects past 3.
What to include when you submit
- Send the past performance narrative described in Section 6 of the RFP: at most 3 projects, 25 pages in all.
- Projects must be completed within the past 6 years of the RFP issuance date (the amendment changed this from 5 years).
- Projects must be completed with your firm as prime contractor. You may submit one project where you were a subcontractor, with the type of work and the level of effort or percentage you performed.
- Pricing and construction cost must be based only on the revised drawings and specifications issued with this amendment.
- Acknowledge Amendment 0006 with your offer, by one of the methods on the SF 30 (the amendment form).
- Sign the limitations on subcontracting certificate (VA clause 852.219-75, which replaces Attachment 7 of the original RFP).
After award, you must have
- Personnel vetting and credentialing under the VA clause 852.204-72, which workers need for physical or logical access to VA facilities and systems.
Current contractor
No incumbent is named. The statement of work says this is the first and only phase of the construction project and no follow-on work is scheduled.
Not in the notice text
- The original RFP (Section 6 proposal instructions, evaluation factors, bonding, how to send the offer, the site visit) is not among the documents read. Only Amendment 0006 and attachments are. Check the original solicitation on SAM.gov.
- How to submit the offer, the evaluation factors and award method, bonding requirements (the amendment lists a VA bond premium adjustment clause) and the contract type are not in the documents read.
- The RFI log (spreadsheet) with the VA's official answers, the drawings (too large to read) and the middle of both specification volumes and the infection control plan were attached but not fully read.
- Whether there is a site visit and which wage rule applies (Davis-Bacon wage determination) is not stated in the documents read, and this is construction (NAICS 236220).
- The estimated value or price range of the project is not stated in the documents read.
- Specific work hours and noise and vibration thresholds are in the specifications, which were only partly read.
More to check before you reply
- Not certified through VetCert yet? Apply on VetCert (SBA), or start with the SDVOSB guide. More open service-disabled veteran-owned set-asides under NAICS 236220
Notice details
Notice type, codes, versions and files
- Posted
- Nov 10, 2026
- Notice type
- Solicitation
- Office
- 260-Network Contract Office 20 (36C260), Vancouver, WA
- Product/service code
- Y1DA · Construction of Hospitals and Infirmaries
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 236220)
- Versions
8 versions have been posted, newest first.
- Nov 19, 2026 · Amendment 0007Due Dec 1, 2026 (changed)
- Nov 10, 2026 · Amendment 0006 (this version)Due Nov 25, 2026 (changed)
- Nov 3, 2026 · Amendment 0005Due Nov 18, 2026 (changed)
- Oct 26, 2026 · Amendment 0004Due Nov 6, 2026 (changed)
- Oct 8, 2026 · Amendment 0003Due Oct 30, 2026
- Oct 2, 2026 · Amendment 0002Due Oct 30, 2026
- Sep 23, 2026 · Amendment 0001Due Oct 30, 2026
- Sep 22, 2026 · SolicitationDue Oct 30, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Open SDVOSB set-aside contracts
Terms on this notice: Solicitation, SDVOSB (service-disabled veteran-owned small business), Set-aside
Full notice text from SAM.gov
Similar open opportunities
- 666-27-102 Lightning Protection Update B71NService-disabled veteran-owned small business (SDVOSB) set-aside: only firms both visible and verified as SDVOSBs in the Small Business Administration (SBA) certification…
- Amendment 0002 Y1DZ--36C261-28-AP-0022 | 612-27-1-6009-0001 | Construct Modular Imaging Center in Stockton | 612A4-CSI-002Only service-disabled veteran-owned small businesses (SDVOSB) verified in the Small Business Administration's (SBA) VetCert database can quote.
- N4008427R1027 FY27 Special Project Usnh Amendment 0002