Combined Synopsis/Solicitation
Ross Springs Waterline Replacement
Department of Agriculture · Forest Service
Small business set-aside · UT
AI summary Beta
Only small businesses can bid: this is a total small business set-aside from the USDA Forest Service, Ashley National Forest (solicitation 1240LT27Q0022). The job is replacing a 4-inch water main with high-density polyethylene (HDPE) plastic pipe in Daggett County, Utah. The pipe length is unclear: 4450 linear feet in the notice, 4475 in the schedule. Quotes are due December 1, 2026, 3:00 PM Mountain, with a bid guarantee. A pre-bid meeting is set for November 18, 2026 (passed).
Who can bid
- Small business: this is a total small business set-aside under NAICS 237110 From C04b 1240LT27Q0022.pdf
- Bid guarantee (such as a bid bond) of 20 percent of the bid price or $3 million, whichever is less, with the quote From C04b 1240LT27Q0022.pdf
- Active SAM.gov registration From C04b 1240LT27Q0022.pdf
Things to watch (10)
From the version posted Nov 10, 2026.
- Serious: Small business set-aside. Only small businesses can send quotes; the size standard shown for this code is $45 (million) in average annual receipts. From C04b 1240LT27Q0022.pdf
- Serious: Bid guarantee due with the quote. Missing or wrong guarantee can get the quote rejected; it must be 20 percent of the bid price or $3 million, whichever is less. The offer form's guarantee box couldn't be read; check it on SAM.gov. From C04b 1240LT27Q0022.pdf
- Serious: Payment bond required after award. A payment bond for 100 percent of the contract price is due within 15 days of award, and the contract also includes the performance and payment bonds clause. Bond premiums are covered in the mobilization item. From C04b 1240LT27Q0022.pdf
Show all 10Show fewer
- Worth checking: Pipe length differs between documents. The notice and statement of work say 4450 linear feet of 4-inch pipe; the solicitation's schedule of items says 4475. Ask the contracting officer which governs. From C04b 1240LT27Q0022.pdf
- Worth checking: Experience requirement mentions HVAC work. The relevant experience section asks for projects showing HVAC (heating and cooling) experience, which doesn't match a waterline job. Ask the contracting officer what experience counts. From C04b 1240LT27Q0022.pdf
- Worth checking: The site visit was Nov 18, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From 1240LT27Q0022.pdf
- Worth checking: Construction wage rates apply. A Davis-Bacon wage determination for heavy construction in Daggett County, Utah (UT20260025) is attached. The Service Contract Labor Standards clause is also checked, so ask which wage rules govern. From C04b 1240LT27Q0022.pdf
- Worth checking: Buy American rules for construction materials. Only domestic construction materials may be used unless the Government approves an exception, which affects pipe and valve sourcing. From C04b 1240LT27Q0022.pdf
- Minor: Stream protection plan before work starts. The contractor must submit a stream protection plan and get written approval from the Contracting Officer's Representative before construction begins. From C04c SOW 1240LT27Q0022.docx
- Minor: No utilities at the site. Utilities are not available for construction, and the contractor must provide portable toilets and may not camp overnight on site. From C04c SOW 1240LT27Q0022.docx
Read from the notice and 6 attachments. Show which files.
- C04c SOW 1240LT27Q0022.docx (read)
- 1240LT27Q0022.pdf (read)
- C04a SF-1442 1240LT27Q0022.pdf (read)
- C04b 1240LT27Q0022.pdf (read)
- C04d Plans 1240LT27Q0022.pdf (read)
- C04e WD Daggett County Utah 1240LT27Q0022.pdf (read)
Full summary
What they want
- Install HDPE water main, 4-inch: 4450 linear feet in the notice and statement of work, 4475 LF in the schedule of items
- Cover another 1150 linear feet of existing pipeline with imported fill from a Government source
- Install 2 combination air-vacuum valves with utility boxes
- Install valves, daylight drains and pumpout drains, and connect to existing lateral mains and services
- Leave the old 4-inch asbestos cement pipe abandoned in place
- Protect streams, limit public access and keep the Red Canyon Visitor Center area separated from the work
- Finish within 90 calendar days after notice to proceed; start date is Spring 2027
- Contract type
- Firm-fixed-price (FFP): one set price for the work, whatever it ends up costing. One award; pricing is required for all items
- Period of performance
- 90 calendar days after notice to proceed; start date Spring 2027
- Place of performance
- Flaming Gorge Ranger District of the Ashley National Forest, Daggett County, Utah, Section 52, T 2 N, R 21 E, about 25 miles southwest of Manila, Utah
- Estimated value
- Not stated
- How they'll choose
- Lowest price technically acceptable (LPTA): quotes are first rated Acceptable or Unacceptable on technical capacity, then the lowest evaluated price among acceptable quotes wins; no trade-offs
- Offers due
- December 1, 2026, 3:00 PM Mountain
What they'll judge offers on
- Technical Capacity (Acceptable or Unacceptable): (a) relevant experience on at least two projects completed in the past five years, (b) ability to meet the schedule (staffing, equipment, subcontractors, lead times, constraints), (c) exceptions or limitations to the statement of work
- Price: every line item priced on the Schedule of Items; evaluated for fairness and reasonableness
- Past Performance: rated Acceptable, Neutral or Unacceptable using references and records such as the Contractor Performance Assessment Reporting System (CPARS)
What to include when you submit
- Price every line item on the Schedule of Items (page 2 of the request for quote); missing line items may exclude the quote
- Send information on at least two similar projects completed within the past five years: name and location, owner, work performed, approximate contract value, completion date and a customer contact
- Describe how the work will meet the 90-day schedule: staffing and key personnel, major equipment or subcontractors, lead times for materials and any known scheduling constraints
- List any requirement in the statement of work you cannot accomplish, or state that you can perform all of it
- Provide a bid guarantee with the quote: 20 percent of the bid price or $3 million, whichever is less
- Acknowledge amendments and hold prices firm for 60 calendar days after the due date
After award, you must have
- Payment bond for 100 percent of the contract price, due within 15 days of award; performance and payment bonds clause is also included From C04b 1240LT27Q0022.pdf:
(c) The submission of the payment protection is required within 15 days of contract award.
- Insurance for work on a Government site, including general liability of at least $500,000 per occurrence From C04b 1240LT27Q0022.pdf:
…written on a comprehensive form of policy of at least $500,000 per occurrence.
Not in the notice text
- How to submit the quote (email address or portal) isn't stated in the text read; the solicitation form lists Derrick Dodson (derrick.dodson@usda.gov) as the information contact, so check SAM.gov
- Where the November 18, 2026 pre-bid meeting is held and whether it is required isn't stated; the amendment names Cathleen Christensen, 435-650-2336, as the contact
- The deadline for questions isn't stated
- Whether the bid guarantee box on the solicitation form is checked couldn't be read; the bid guarantee clause is marked as included
- Part of the statement of work file's technical specifications (middle sections) was left out of the text read here; check the full file on SAM.gov
Notice details
Notice type, codes, versions and files
- Posted
- Nov 10, 2026
- Notice type
- Combined Synopsis/Solicitation
- Office
- Ashley National Forest, Vernal, UT
- Product/service code
- Z2NE · Repair or Alteration of Water Supply Facilities
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 237110)
- Versions
6 versions have been posted, newest first.
- Nov 10, 2026 · Amendment 0005 (this version)Due Dec 1, 2026
- Nov 10, 2026 · Amendment 0004Due Dec 1, 2026 (changed)
- Nov 3, 2026 · Amendment 0003Due Nov 21, 2026
- Oct 26, 2026 · Amendment 0002Due Nov 21, 2026
- Oct 23, 2026 · Amendment 0001Due Nov 21, 2026 (changed)
- Oct 22, 2026 · Combined Synopsis/SolicitationDue Nov 21, 2027
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Set-aside contracts explained
Terms on this notice: Solicitation, Set-aside
Full notice text from SAM.gov
This project includes the replacement of 4” asbestos cement pipe (abandoned in place) with 4” HDPE water main and associated valves and connections to laterals. The work includes; Installation of 4450 linear feet of 4” HDPE pipeline, most of which will be shallow bury or laid on cleared ground and covered with imported fill from a government source. Cover an additional 1150 linear feet of existing pipeline with imported fill from a government source. Installation of 2 combination air-vacuum valves with utility boxes. Installing associated valves, daylight drains, and pumpout drains; and connecting to existing lateral mains and services.
Similar open opportunities