Solicitation
GRCA 318719 North Rim & Springs Rehabilitation Pro
Department of the Interior · National Park Service
AI summary Beta
This summary may miss requirements: 39 of 51 attachments weren't read (B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part3.pdf, B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part4.pdf and 37 more). Check the attachments on SAM.gov.
The National Park Service (NPS) Denver Service Center wants a construction contractor for solicitation 140PP027R0005, the North Rim and Roaring Springs Rehabilitation Program at Grand Canyon National Park, Arizona. The work covers water, sewer and power systems. The response due date is January 8, 2027, 12:00 PM Mountain. The solicitation is full and open to all businesses, is marked more than $10 million, and is not yet funded.
Who can bid (4)
- Active registration in SAM.gov when the offer is submitted From B08_140PP027R0005.pdf
- A bid guarantee, such as an SF 24 bid bond, submitted with the offer From B08_140PP027R0005.pdf
- Large businesses must submit an acceptable small business subcontracting plan to be considered for award From B08_140PP027R0005.pdf
Show all 4Show fewer
- Named key personnel with relevant experience, plus an experienced borehole drilling subcontractor From B08_140PP027R0005.pdf
How to submit: One electronic copy, no hard copies; where to send it is not in the text read here. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
From the version posted Nov 9, 2026.
- Serious: Requirement is not yet funded. Award happens only if and when money becomes available, so a bid may never turn into a contract. From Sol_140PP027R0005.pdf
- Serious: Bid guarantee and bonds required. A bid bond (Standard Form 24: a surety's promise backing your offer) goes in with the offer, and the contract carries a performance and payment bonds clause. A project over $10 million needs strong bonding capacity. From B08_140PP027R0005.pdf
- Worth checking: 420-day water milestone with daily damages. Water must reach the North Rim tank farm within 420 calendar days after notice to proceed (NTP: the Government's order to start work), or liquidated damages (a set daily charge for late work) of $5,534.00 per day apply. From B08_140PP027R0005.pdf
Show all 10Show fewer
- Worth checking: Sole-source manufacturer letters required. Offers must include signed letters from six named manufacturers saying you may buy their products and giving delivery times; missing letters can weaken the technical approach score. From B08_140PP027R0005.pdf
- Worth checking: Borehole drilling and event-based line items. Six contract line item number (CLIN: one priced line of the order) entries for drilling events, such as hitting a void, need Contracting Officer approval before paid time starts. Drilling experience is scored. From B08_140PP027R0005.pdf
- Worth checking: Winter limits and remote access. Offers must address winter operations from December 15 to March 15, limited hauling on SR-67 and reduced inner canyon access. Schedules that skip these are rated higher risk. From B08_140PP027R0005.pdf
- Worth checking: Performance period dates differ. The SF 1442 shows March 1, 2027 to March 31, 2031, while the text gives 1,095 calendar days after NTP and the schedule assumes an NTP of June 14, 2027. Ask the contracting officer which governs. From Sol_140PP027R0005.pdf
- Worth checking: Pre-proposal site visit details not read. The solicitation points to Section L for a pre-proposal site visit; whether it is required, and when, was not in the text read here. From Sol_140PP027R0005.pdf
- Minor: Government supplies the control system programming. The Government separately hires the supervisory control and data acquisition (SCADA: the computer system that runs plant equipment) programmers, and you must coordinate with them and meet the cybersecurity specification. From B08_140PP027R0005.pdf
- Minor: Taxes are included in the price. All federal, state and local taxes must be priced in because the project is not tax exempt. From Sol_140PP027R0005.pdf
Read from the notice and 12 attachments. 39 of 51 not read. Show which files.
- Sol_140PP027R0005.pdf (read)
- B08_140PP027R0005.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part2.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part5.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part6.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part7.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part8.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part10.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part11.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part12.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part15.pdf (read)
- B08_Attach_01_Specs_Rehabilitate_North_Rim_Vol_B_(Div_02-23)_20261012.pdf (read)
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part3.pdf: not read (it couldn't be opened): open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part4.pdf: not read (it couldn't be opened): open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part1.pdf: not read (it couldn't be opened): open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part9.pdf: not read (it couldn't be opened): open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part13.pdf: not read (it couldn't be opened): open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_05_20261012_Part14.pdf: not read (it couldn't be opened): open it on SAM.gov
- B08_Attach_01_Specs_Rehabilitate_North_Rim__Vol_A_(Div_01)_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_01_Specs_Rehabilitate_North_Rim_Vol_C_(Div_26-46)_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part2.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part3.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part4.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part1.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part5.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part6.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_04_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_03_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_02_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_01_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part7.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part8.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part9.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part11.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_00_20261012_Part10.pdf: not summarized: open it on SAM.gov
- B08_Attach_03_Wage_Determintation.pdf: not summarized: open it on SAM.gov
- B08_Attach_04_CLIN_Price_Sheet_-_Services.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- B08_Attach_05_Solit_PSP_Vol_II_SubKPlan_REQD.pdf: not summarized: open it on SAM.gov
- B08_Attach_06_Solit_PSP_Vol_II_GenRefs.pdf: not summarized: open it on SAM.gov
- B08_Attach_07_Solit_PSP_Vol_I_PastPerf_REQD.pdf: not summarized: open it on SAM.gov
- B08_Attach_08_Solit_PSP_Vol_II_BidBond.pdf: not summarized: open it on SAM.gov
- B08_Attach_09_GRCA_318719_GISR_20260331.pdf: not summarized: open it on SAM.gov
- B08_Attach_10_GRCA_318719_Innercanyon_GIR_20250811.pdf: not summarized: open it on SAM.gov
- B08_Attach_11_GRCA_318719_North_Rim_GIR_20250811.pdf: not summarized: open it on SAM.gov
- B08_Attach_12_Site_Visit_Attendee_List.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_08_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_06_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_09_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_10_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_11_20261012.pdf: not summarized: open it on SAM.gov
- B08_Attach_02_North_Rim_Final_CDs_Volume_12_20261012.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Rehabilitate the Roaring Springs Pumphouse and replace the water pipelines between it, the North Rim tank farm and Roaring Springs Cave (CLINs 0010 to 0050)
- Drill the borehole for the North Rim to Roaring Springs Pumphouse pipeline (CLIN 0020), with six event-based CLINs paid by the hour
- Build the North Rim Water Treatment Plant at the tank farm site (CLIN 0060)
- Reach water delivery to the North Rim tank farm within 420 calendar days after NTP
- Power work: more diesel fuel storage, a fourth standby generator, new transformers, junction boxes and shunt reactors, and overhead power from North Rim to the pumphouse (CLINs 0090 and 0100)
- Option 1: replace the North Rim sewer collection system (CLIN 0080)
- Option 2: replace underground power and fiber from the pumphouse to Manzanita (CLIN 0110)
- Option 3: replace the defunct solar power system at Cottonwood Campground (CLIN 0120)
- Contract type
- Firm-fixed-price (FFP): one set price, whatever the work ends up costing; base lump-sum lines plus three priced option lines
- Period of performance
- Start within 15 calendar days after NTP and finish within 1,095 calendar days after NTP; water to the North Rim tank farm within 420 calendar days after NTP. The form also shows a performance period of March 1, 2027 to March 31, 2031
- Place of performance
- Grand Canyon National Park, Arizona
- Estimated value
- Magnitude of construction: more than $10 million (a size range, not a price estimate)
- How they'll choose
- Best value tradeoff: the Contracting Officer picks the proposal with the best value, and may pay more for a stronger one. Price is a factor; all non-price factors combined are about equal to price
- Offers due
- January 8, 2027, 12:00 PM Mountain
- How to submit
- One electronic copy, no hard copies; where to send it is not in the text read here
- Page limits
- Technical approach (Factor 2): 15 pages, not counting the schedule or manufacturer letters; Management approach (Factor 4): 5 pages; Key personnel resumes: 1 page each, outside the page limit
What they'll judge offers on
- Factor 1, Technical Experience: relevance of past projects, quality of performance, key personnel (project manager, construction superintendent, quality control manager) and the borehole drilling subcontractor
- Factor 2, Technical Approach: 420-day water milestone, SCADA and cybersecurity coordination, event-based CLINs, startup and commissioning, risks, winter operations, schedule
- Factor 3, Past Performance: relevance and quality, using questionnaires, Contractor Performance Assessment Reporting System (CPARS) reports and other sources
- Factor 4, Management Approach: capacity, roles and responsibilities, safety
- Factor 5, Small Business Participation: small business offerors get the maximum credit
- Price: checked for fairness and reasonableness and for unbalanced line items
What to include when you submit
- Volume I (non-price) covers Factors 1 to 5; Volume II is the business and price proposal
- Volume II folders: Standard Form 1442 (SF 1442), the solicitation and offer form (blocks 14 through 20C, signed by someone who can bind the company), amendments, Section B price schedule, bid bond, Section K representations, general references
- Price every base and option line, and add a separate schedule of values for each line showing major work components
- Send a bid bond on Standard Form 24 (SF 24) or another suitable bid guarantee
- Send 1-page resumes for key personnel: project manager, construction superintendent, quality control manager and site safety manager
- Send a past performance questionnaire (PPQ) to references for each Factor 1 project of your firm and key subcontractors, and include a copy of each in Volume I; CPARS reports may replace them
- Include a narrative on any less-than-satisfactory past performance, with causes and fixes
- Submit a critical path Gantt chart schedule assuming notice to proceed on June 14, 2027, with a schedule narrative covering winter operations, haul limits and recovery measures
- Send signed letters from each sole-source manufacturer: Flex Steel pipe, Flowserve pumps, Veolia/Suez ultrafiltration (UF) membranes, Caterpillar generator, Automation Direct DoMore programmable logic controllers (PLCs) and Hach instruments
- Send an organization chart and the safety programs of the prime and the borehole drilling subcontractor
- Complete the General References form, which the Government uses to check responsibility
- Large businesses must include a small business subcontracting plan; small businesses need not
After award, you must have
- Performance and payment bonds clause is part of the contract; amounts and due date were not in the text read From B08_140PP027R0005.pdf:
52.228-15 PERFORMANCE AND PAYMENT BONDS-CONSTRUCTION (JUN 2020) (DEVIATION MAY…
Not in the notice text
- Much of Section H and Section L (the site visit details, question deadline and where to send proposals) was not read here, and the drawings, specifications and forms are attached but not read; check the solicitation and its attachments on SAM.gov
- Whether a pre-proposal site visit is required, and its date
- Which wage rule applies: a wage determination file (B08_Attach_03_Wage_Determintation.pdf) is attached but not read, so confirm whether Davis-Bacon wages apply
- Bid bond and performance bond amounts and the Standard Form 1442 bond boxes
- The price sheet spreadsheet (B08_Attach_04_CLIN_Price_Sheet_-_Services.xlsx) is attached but not read
- The place of performance field on SAM.gov is blank; the solicitation names Grand Canyon National Park, Arizona
Notice details
Notice type, codes, versions and files
- Posted
- Nov 9, 2026
- Notice type
- Solicitation
- Office
- National Park Service Contracting Activity, Denver, CO
- Product/service code
- Y1NE · Construction of Water Supply Facilities
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 237110)
- Versions
3 versions have been posted, newest first.
- Nov 9, 2026 · Solicitation (this version)Due Jan 8, 2027 (changed)
- Oct 22, 2026 · PresolicitationDate Nov 6, 2026 (changed)
- Oct 6, 2026 · Special NoticeDate Oct 13, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- 550-26-121 FY27 NRM Emergent Repairs North Water Tower 71 & South Water Tower 94 CONThe Department of Veterans Affairs (VA) wants emergent repairs to the North Water Tower 71 and South Water Tower 94 in Danville, Illinois.
- Ross Springs Waterline ReplacementOnly small businesses can bid: this is a total small business set-aside from the USDA Forest Service, Ashley National Forest (solicitation 1240LT27Q0022).