Combined Synopsis/Solicitation
Garage Drywall Demolition at Udall Building
Department of the Interior
Small business set-aside · DC
AI summary Beta
The notice looks incomplete: The middle of each solicitation file (about pages 16 to 25: clauses) is attached but not read here; it may hold bonding, insurance or other clause details. Check the full files on SAM.gov. Check the attachments on SAM.gov.
The Department of the Interior (Interior Business Center) wants a contractor to demolish drywall ceiling bulkheads in two parking garages at the Stewart Lee Udall Building, 1849 C Street NW, Washington, DC (solicitation 140D0427Q0949). It is a total small business set-aside, priced as two firm-fixed-price jobs (one set price each), with work due 90 days from the notice to proceed. Amendment 0003 sets the response due date at December 11, 2026, 12:00 PM Eastern.
Who can bid (4)
- Total small business set-aside: only small businesses under NAICS 238910 (Site Preparation Contractors, size standard $19 million) can bid From Sol_140D0427Q0949_Amd_0003.pdf
- Bid guarantee (bid bond on SF 24) with the quote; the amount is left blank in the clause From Sol_140D0427Q0949_Amd_0003.pdf
- Company specializing in this work with at least 5 years of documented successful experience From Sol_140D0427Q0949_Amd_0003.pdf
Show all 4Show fewer
- Prime contractor must attend an on-site walk-through of the space From Sol_140D0427Q0949_Amd_0003.pdf
How to submit: Email to Contracting Officer Nicholas Lewicki (nicholas_lewicki@ibc.doi.gov) and contract specialist Haider Al Azzawi (halazzawi@ibc.doi.gov). What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (8)
From the version posted Nov 20, 2026.
- Serious: Small business set-aside. Only small businesses under NAICS 238910 (size standard $19 million) can bid. From Sol_140D0427Q0949_Amd_0003.pdf
- Serious: Bid bond required, amount blank. The evaluation checks an SF 24 bid bond, and a missing guarantee may get the bid rejected, but the clause leaves the percent and dollar amount blank; ask the contracting officer. From Sol_140D0427Q0949_Amd_0003.pdf
- Serious: Site walk-through: "must attend" vs "urged". The statement of work says the prime contractor must attend an on-site walk-through, while the site visit clause only urges bidders to inspect the site; ask whether skipping it rules you out. From Sol_140D0427Q0949_Amd_0003.pdf
Show all 8Show fewer
- Worth checking: The site visit was Nov 13, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From Sol_140D0427Q0949_Amd_0003.pdf
- Worth checking: Night and weekend work only. All garage work must happen outside 6 AM to 8 PM on weekdays, which raises labor costs, and after-hours access lists are due to Security at least 3 business days ahead. From Sol_140D0427Q0949_Amd_0003.pdf
- Worth checking: Escort costs for workers without badges. Short-term workers won't have DOI badges, so you may have to pay for a security guard escort; price it in. From Sol_140D0427Q0949_Amd_0003.pdf
- Minor: Completion time stated two ways. The statement of work gives 90 days from the notice to proceed, but Section F says three months after contract award; ask which clock applies. From Sol_140D0427Q0949_Amd_0003.pdf
- Minor: Date passed (May 18, 2026): Davis-Bacon wages apply. Workers must be paid at least the rates in wage determination DC20260002 Modification 3, dated May 18, 2026. From Sol_140D0427Q0949_Amd_0003.pdf
Read from the notice and 4 attachments. Show which files.
- Sol_140D0427Q0949_Amd_0003.pdf (read)
- Sol_140D0427Q0949_Amd_0002.pdf (read)
- Sol_140D0427Q0949_Amd_0001.pdf (read)
- Sol_140D0427Q0949.pdf (read)
Full summary
What they want
- A/B garage (CLIN 0001, a contract line item number: one priced line): support about 20 junction boxes and 100 linear feet of conduit from the ceiling, then demolish about 1500 linear feet of drywall bulkheads and metal studs
- C/D/G garage (CLIN 0002): support about 80 junction boxes and 400 linear feet of conduit, then demolish about 6000 linear feet of bulkheads
- Patch and paint ceiling holes where fasteners come out
- Scrape and repaint peeling piping (about 250 linear feet in A/B, 1000 in C/D/G; fire sprinkler piping not included)
- Patch damaged fiberglass pipe insulation (about 50 linear feet in A/B, 200 in C/D/G)
- Remove all debris daily; HEPA-vacuum and wet-scrub the floor (at the end of the job in A/B, at the end of each workday in C/D/G)
- Work only outside business hours (6 AM to 8 PM, Monday to Friday), with a prime contractor supervisor on site whenever work happens
- Write and follow a Quality Control Plan, a Management Plan and a site Health and Safety Plan (HASP) naming an OSHA competent person
- Contract type
- Firm-fixed-price (one set price, whatever the work ends up costing): two lump-sum line items, 1 job each
- Period of performance
- 90 days from the notice to proceed (the statement of work); Section F says all work, including cleanup, is completed three months after contract award
- Place of performance
- Stewart Lee Udall Building (Department of the Interior headquarters), 1849 C Street NW, Washington, DC 20240
- Remote work
- No. From Sol_140D0427Q0949_Amd_0003.pdf:
Work shall be performed onsite at the Stewart Lee Udall Building (“the Udall Building,” “the building”):
- Estimated value
- Not stated
- How they'll choose
- Lowest price technically acceptable (LPTA): the lowest-priced quote that meets the technical requirements wins; award is planned without discussions
- Offers due
- December 11, 2026, 12:00 PM Eastern
- How to submit
- Email to Contracting Officer Nicholas Lewicki (nicholas_lewicki@ibc.doi.gov) and contract specialist Haider Al Azzawi (halazzawi@ibc.doi.gov)
- Page limits
- Technical response: 5 pages (the draft Quality Control Plan and draft Contractor Management Plan don't count); pages past the limit won't be read
What they'll judge offers on
- Technical: understanding of, approach to and ability to meet the requirements, including five years of experience
- Price: must be fair and reasonable
- Other documents: Standard Form 1442 complete, amendments acknowledged, SF 24 bid bond complete and acceptable, Section K representations checked in SAM.gov
What to include when you submit
- Submit the quote on Standard Form 1442 (SF 1442: the construction offer form you sign and return), and state that the quote is valid through the acceptance period it gives
- Technical response, up to 5 pages: your approach to the statement of work, proof of five years of experience, and a tentative project schedule
- Include a draft Quality Control Plan (QCP) and a draft Contractor Management Plan (CMP) covering staffing, work management, quality control, communication and facility issues
- Price: give the price as a total cost, with a price for each line item (A/B garage and C/D/G garage)
- Include an SF 24 bid bond (a surety's promise that you'll sign the contract if you win)
- Acknowledge Amendments 0001, 0002 and 0003 on the SF 1442 or by separate letter or email
- Make sure your SAM.gov representations and certifications are current; they are checked there
After award, you must have
- A prime contractor employee who speaks and writes English must supervise on site whenever work is done, including when subcontractors work From Sol_140D0427Q0949_Amd_0003.pdf:
At least one Prime Contractor employee must be onsite in a supervisory capacity any time work…
- Workers need REAL ID-compliant photo ID; those without a DOI PIV badge must be escorted, at the contractor's expense if a guard is used From Sol_140D0427Q0949_Amd_0003.pdf:
Contractor personnel without a PIV credential must be escorted by a DOI…
Not in the notice text
- The middle of each solicitation file (about pages 16 to 25: clauses) is attached but not read here; it may hold bonding, insurance or other clause details. Check the full files on SAM.gov.
- The bid guarantee's percent or dollar amount is blank in the clause.
- Whether performance and payment bonds are required, and within how many days, couldn't be read from the SF 1442's checkboxes; check the form on SAM.gov.
- Amendment 0001 said questions and answers would be posted in a later amendment; Amendments 0002 and 0003 don't include them.
- No Government estimate or price range is given.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 20, 2026
- Notice type
- Combined Synopsis/Solicitation
- Office
- Ibc Acq SVCS Directorate (00004), Herndon, VA
- Product/service code
- Z2AA · Repair or Alteration of Office Buildings
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 238910)
- Versions
4 versions have been posted, newest first.
- Nov 20, 2026 · Amendment 0003 (this version)Due Dec 11, 2026 (changed)
- Nov 17, 2026 · Amendment 0002Due Dec 2, 2026
- Nov 13, 2026 · Amendment 0001Due Dec 2, 2026 (changed)
- Nov 4, 2026 · Combined Synopsis/SolicitationDue Nov 19, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Set-aside contracts explained
Terms on this notice: Solicitation, Set-aside
Full notice text from SAM.gov
Similar open opportunities
- Demolition of an existing building, Site Improvements and construction of a Modular Office Building at the US Merchant Marine Academy Campus, Kings Point, NYThe U.S. Army Corps of Engineers New York District is seeking sealed bids (an invitation for bid, IFB) to demolish an existing building and build a new modular office of about…
- Project Number 657-507, Correct Seismic Deficiencies for Building 14, Marion VAMC, Illinois Construction of New Boiler Plant and Demolition of ExistingSolicitation 36C10F26R0085: only Veterans Affairs-verified service-disabled veteran-owned small businesses listed in VA's Vendor Information Pages (VIP) database can bid.