Solicitation
Cooling Tower, Roofing, and Structural Construction
Department of the Treasury · Bureau of Engraving and Printing
Small business set-aside · DC
A newer version of this notice was posted Nov 12, 2026. It moves the due date from Oct 9, 2026 to Dec 11, 2026, which is the date shown on this page. See the latest version.
AI summary Beta
Summary of another version of this notice: check what changed on SAM.gov. This summary may miss requirements: 25 of 37 attachments weren't read (2031ZA26R00027 0001.pdf, Attachment 8 - Site Visit Sign In Sheet.pdf and 23 more). Check the attachments on SAM.gov.
The Bureau of Engraving and Printing (Treasury) seeks a small business for solicitation 2031ZA26R00027, a design-build job to replace cooling towers, their steel platform and a power plant wing roof in Washington, DC. It is a total small business set-aside, firm-fixed-price (FFP: one set price, whatever the work ends up costing). The response due date is December 11, 2026, 12:00 PM Central. The tower count is unclear: the solicitation says two, and the statement of work says four.
Who can bid (5)
- Small business under NAICS 236220 (size standard $45.0 million) on the date the offer is submitted and on the date of award; total small business set-aside, so only small businesses can bid From 2031ZA26R00027 Revision 01 11052026.pdf
- Project Manager employed by the prime contractor, with an engineering, architecture or related degree and/or five years managing similar projects, plus five years in historical government buildings From 2031ZA26R00027 Revision 01 11052026.pdf
- Specialized technical staff with engineering degrees and Professional Engineering licenses in the relevant trades From 2031ZA26R00027 Revision 01 11052026.pdf
Show all 5Show fewer
- Prime must show design-build experience as the prime contractor managing construction subcontractors; only major subcontractors (at least 25% of total value) count toward experience From 2031ZA26R00027 Revision 01 11052026.pdf
- At least three recent past performance references (last 5 years) for similar-size work, returned by the references themselves From Attachment 1 - Past Performance Questionnaire.pdf
How to submit: Section L's full instructions weren't read. Questions go by email to the contracting officer, Laqulla Williams at Laqulla.Williams@bep.gov.. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (12)
From the version posted Nov 12, 2026.
- Serious: Total small business set-aside. Only small businesses can bid, and size is checked both when you send the offer and at award. From 2031ZA26R00027 Revision 01 11052026.pdf
- Serious: Bonds and offer guarantee appear to be required. The solicitation form appears to call for performance and payment bonds within 10 days of award and an offer guarantee, and the pricing table has a bond premium line. The form's checkboxes are hard to read; check the form on SAM.gov. From Attachment 4 - Pricing Table Revision 01 Amendment 0002.pdf
- Serious: Tower count differs between documents. The solicitation says two Evapco towers are replaced. The statement of work says four, and calls them both two-cell and eight-cell. Ask the contracting officer how many towers and cells are in scope before you price. From Attachment 3 - Statement of Work - Cooling Towers Revision 02 Amendment 0002.pdf
Show all 12Show fewer
- Serious: Licensed engineers and specific key personnel required. You need a project manager on your own payroll, a project superintendent with 5 years in historical government buildings, and Professional Engineering licenses. From 2031ZA26R00027 Revision 01 11052026.pdf
- Serious: The site visit was Sep 30, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From 2031ZA26R00027 0003.pdf
- Worth checking: Worker background checks before site access. Every worker on the job, including subcontractors, must be cleared by BEP before entering. Build clearance time into your schedule.
- Worth checking: Past performance questionnaire return date of October 9, 2026. The questionnaire gives October 9, 2026, 12:00 PM Central as the references' return date. The response due date later moved to December 11, 2026. Ask the contracting officer which date governs. From Attachment 1 - Past Performance Questionnaire.pdf
- Worth checking: Contractor must perform a share of the work itself. Monthly workforce reports certify that the small business prime and similarly situated subcontractors performed at least 15 percent of personnel cost on construction contracts. From Attachment 7 - Monthly Workforce Report.pdf
- Worth checking: Long design-build schedule with live building. Work can last up to 730 days and BEP stays fully operational throughout; work hours are 8:00 AM to 5:00 PM Eastern, Monday through Friday. From Attachment 3 - Statement of Work - Cooling Towers Revision 02 Amendment 0002.pdf
- Minor: Response due date moved twice. Amendment 0001 moved the response due date to November 9, 2026, and Amendment 0002 moved it to December 11, 2026. Use December 11, 2026. From 2031ZA26R00027 0002.pdf
- Minor: Lead-based paint responsibility. You must test for lead-based paint, write an abatement plan for BEP's safety office to approve, and dispose of the waste under EPA and DC rules. From Attachment 3 - Statement of Work - Cooling Towers Revision 02 Amendment 0002.pdf
- Minor: Drawings not guaranteed. Plans aren't available for the work areas. BEP may provide archive drawings for information only, so site survey risk falls on you. From Attachment 3 - Statement of Work - Cooling Towers Revision 02 Amendment 0002.pdf
Read from the notice and 12 attachments. 25 of 37 not read. Show which files.
- 2031ZA26R00027 0003.pdf (read)
- 2031ZA26R00027 0002.pdf (read)
- 2031ZA26R00027 Revision 01 11052026.pdf (read)
- 2031ZA26R00027.pdf (read)
- Attachment 4 - Pricing Table Revision 01 Amendment 0002.pdf (read)
- Attachment 3 - Statement of Work - Cooling Towers Revision 02 Amendment 0002.pdf (read)
- Attachment 3 - Statement of Work - Cooling Towers.pdf (read)
- Attachment 4 - Pricing Table.pdf (read)
- Attachment 5 - Quality Assurance Surveillance Plan (QASP).pdf (read)
- Attachment 6 - Initial Staffing Plan.pdf (read)
- Attachment 1 - Past Performance Questionnaire.pdf (read)
- Attachment 7 - Monthly Workforce Report.pdf (read)
- 2031ZA26R00027 0001.pdf: not summarized: open it on SAM.gov
- Attachment 8 - Site Visit Sign In Sheet.pdf: not summarized: open it on SAM.gov
- Attachment 10 - 75D-07.0-04 EMS Document EHS Contractor Requirements.pdf: not summarized: open it on SAM.gov
- Attachment 11 - 75D-04.0-11 Fall Protection Procedure.pdf: not summarized: open it on SAM.gov
- Attachment 12 75D-04.0-01 Emergency Action and Fire Prevention Plan.pdf: not summarized: open it on SAM.gov
- Attachment 14 Evapco performance data.pdf: not read (it couldn't be opened): open it on SAM.gov
- Attachment 15 M02-schematic-BEPVFD Model Chiller Planty Flow Schematic mechanical 2.pdf: not summarized: open it on SAM.gov
- Attachment 16 M03-vfd plan-BEPVFD.pdf: not summarized: open it on SAM.gov
- Attachment 17 M04-Cooling Tower piping plan-BEPVFD M-4.pdf: not summarized: open it on SAM.gov
- Attachment 18 Plate and Frame HX Information.pdf: not summarized: open it on SAM.gov
- Attachment 19 Structural Support for VFDs.pdf: not summarized: open it on SAM.gov
- Attachment 21 BEP-E1R613 Model Chiller Plant Electrical.pdf: not summarized: open it on SAM.gov
- Attachment 22 BEP-E2R0613 Layout1 Chiller Plant Electrical 2.pdf: not summarized: open it on SAM.gov
- Attachment 23 BEP-M1R613 w chiller Layout1.pdf: not summarized: open it on SAM.gov
- Attachment 24 Cooling Tower Information BEP Chilled Water Plant.pdf: not summarized: open it on SAM.gov
- Attachment 25 ax-dcm-06 Main Roof Top.pdf: not summarized: open it on SAM.gov
- Attachment 26 M-DCA-09-1001023-HV.pdf: not summarized: open it on SAM.gov
- Attachment 27 ax-dca-09 Annex Roof Top.pdf: not summarized: open it on SAM.gov
- Attachment 28 Chiller Plan Upgrade M-1_120508 Model (1).pdf: not summarized: open it on SAM.gov
- Attachment 29 Chiller Plan Upgrade M-1_recover.pdf: not summarized: open it on SAM.gov
- Attachment 30 Pictures.pdf: not read (it couldn't be opened): open it on SAM.gov
- Attachment 31 Pictures.pdf: not read (it couldn't be opened): open it on SAM.gov
- Attachment 32 Pictures.pdf: not read (it couldn't be opened): open it on SAM.gov
- Attachment 20 Tower_submittal.pdf: not summarized: open it on SAM.gov
- Attachment 2 - Davis-Bacon Wage Determination DC20260001 Modification 06.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Survey the site, then design and get approved drawings for the work (design-build)
- Demolish and dispose of the existing Evapco and BAC cooling towers, pumps, piping and the corroded steel platform
- Install new cooling towers sized for four chillers rated 1,375 tons each, plus a new structural steel platform
- Replace the leaking power plant wing roof between the platform demolition and the new platform
- Install electrical, mechanical, chemical feed, fire/smoke detection and SCADA (remote monitoring and control system) integration
- Recommend chiller upgrades and the best chiller type for the new towers
- Handle lead-based paint testing, abatement plan and waste removal if found
- Deliver as-built drawings, a SCADA commissioning report and a demolition and disposal report
- Contract type
- Firm-fixed-price, one lump sum line
- Period of performance
- No more than 730 calendar days from the Notice to Proceed; work begins within 3 calendar days after the notice to proceed
- Place of performance
- BEP DCF, 14th & C Streets, S.W., Washington, D.C.
- Estimated value
- Government's estimated price range: between $1,000,000 and $5,000,000
- How they'll choose
- Best value trade-off with a single award; non-price factors together are significantly more important than price
- Offers due
- December 11, 2026, 12:00 PM Central
- How to submit
- Section L's full instructions weren't read. Questions go by email to the contracting officer, Laqulla Williams at Laqulla.Williams@bep.gov.
- Page limits
- Business/Price volume: no page limit, double-spaced, 12-point Times New Roman. Page limits for the technical volume weren't read.
What they'll judge offers on
- Corporate Experience (design-build, renovations, complex mechanical, electrical and plumbing systems; weighted heavier, equal to Past Performance)
- Past Performance (technical quality, schedule, management; weighted heavier, equal to Corporate Experience)
- Technical Approach (strategy for the SOW, subcontractor use, project management, staffing and continuity, contingency plan)
- Key Personnel (project manager, specialized technical staff, project superintendent)
- Project Plan (project management and planning, oversight and monitoring)
- Price (price analysis of the overhead and profit rates in the pricing table)
What to include when you submit
- Send a Business/Price volume (Volume II) with signed acknowledgement of each amendment.
- Complete the pricing table's overhead (including general and administrative) and profit percentages in section B.1 and include them in Volume II.
- Give an itemized breakdown of all divisions and subdivisions of cost for the one lump-sum line.
- Include a copy of the signed Contractor Teaming Arrangement if quoting as a team.
- Include the name and contact information of the proposed Project Manager.
- Offers giving the Government less than 150 calendar days to accept after the response due date are rejected.
- Send the Past Performance Questionnaire to at least three assessors (references) for recent work from the last 5 years; the assessors, not you, email it back to the contracting officer.
- Complete the Initial Staffing Plan (Attachment 6) for the base and each option period.
After award, you must have
- BEP background suitability investigation for contractor and subcontractor workers before they enter the site; security packets go to the contracting officer's representative (COR) within ten working days From 2031ZA26R00027 Revision 01 11052026.pdf:
…shall be subjected to suitability investigations, conducted by the…
Current contractor
No incumbent is named. The documents give no sources sought or award-count details.
Not in the notice text
- Parts of the solicitation and statement of work were cut short when read, and many drawings, the safety forms, and the Davis-Bacon wage determination (DC20260001 Modification 06) are attached on SAM.gov but not read. Check them there.
- Section L (instructions), including the question deadline in L.6, the technical volume page limits and how to send offers, wasn't fully read. Amendment 0003 says questions are due by the date set in Amendment 0002.
- Whether the site visit was a required step isn't clear from the text read; Section L.4 (52.236-27 Site Visit) wasn't read.
- Whether performance and payment bonds and an offer guarantee are required; the form's checkboxes couldn't be read clearly.
- How many towers and cells are being replaced: two in the solicitation, four in the statement of work.
- Which Davis-Bacon wage rule applies: the wage determination is attached but not read, though the solicitation lists it as Attachment 2.
Notice details
Notice type, codes, versions and files
- Posted
- Sep 16, 2026
- Notice type
- Solicitation
- Office
- Office of the Chief Procurement Officer, Washington, DC
- Product/service code
- Z2EC · Repair or Alteration of Production Buildings
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 236220)
- Versions
4 versions have been posted, newest first.
- Nov 12, 2026 · Amendment 0003Due Dec 11, 2026
- Nov 5, 2026 · Amendment 0002Due Dec 11, 2026 (changed)
- Oct 8, 2026 · Amendment 0001Due Nov 9, 2026 (changed)
- Sep 16, 2026 · Solicitation (this version)Due Oct 9, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Set-aside contracts explained
Terms on this notice: Solicitation, Set-aside