Fermi Forward Discovery Group (FFDG), the company that runs Fermilab for the Department of Energy, wants a construction subcontractor to fabricate and install a Low Conductivity Water (LCW) pump room piping system in the F-37 Building at Fermilab in Batavia, Illinois. It is an open competition (no set-aside) decided on lowest price among technically acceptable offers, and proposals are emailed to Fermilab by November 19, 2026. This is a subcontract under FFDG's prime DOE contract, so FFDG's own terms, bonds and Davis-Bacon wage rules apply.
Watch out for
- Large bid guarantee due with the proposal. You must post a bid bond or equivalent for 20 percent of your price (up to $3 million) by the deadline, which needs a surety relationship or cash tied up and can get a small firm rejected.
Failure to furnish a bid guarantee in the proper form and amount, by the time
- 100% payment and performance bonds. The winner must provide bonds for the full price (payment bond over $35,000, performance bond over $150,000), so you need strong bonding capacity.
If the subcontract exceeds $150,000.00, the successful offeror is required to furnish FFDG with a
- 10 years of comparable experience required. Younger firms must rely on key personnel (superintendent and project manager) with 10 years of experience, and FFDG alone decides what counts as comparable.
The offeror shall demonstrate at least ten (10) years of business
- Pre-proposal site visit and secured-site access. Attendance is optional, but skipping it bars later claims for conditions that a visit would have revealed. Access requests are due at least 7 days before the October 27 visit, and the site needs a REAL ID.
Failure to attend the pre-solicitation meeting will preclude the consideration of any
- Conflicting citizenship wording for site access. The SAM.gov notice says attendees must be U.S. citizens, while the RFP says 'preferably'; confirm with the procurement specialist before planning who attends.
attendees must be a U.S. Citizen and have
- Tight space and field fitting. Drawings are 2D layouts with reference dimensions, so a lot of field fitting is expected in a cramped pump room, and the drawings were not available to read.
A thorough understanding of the spacing constraints is critical to successful performance.
- You buy all equipment and instruments up front. The contractor supplies all equipment, piping, valves and instrumentation, which ties up cash before progress payments (the sample subcontract holds back 10 percent until final acceptance).
All equipment, components and instrumentation, including equipment described
- Davis-Bacon wages and weekly certified payroll. You and every lower-tier subcontractor must pay prevailing wages and file weekly certified payroll in LCPTracker, which adds paperwork and cost.
The subcontractor and its subcontractors are required to submit certified payrolls and labor compliance
- Incomplete proposals can be thrown out. Missing any required document (timeline, prior work examples, references, signed price form) can make the offer non-responsive.
specifically, failure to provide all documents required, may result in your submission being considered
- Exceptions to terms can disqualify you. Taking exceptions to the specifications or FFDG's terms and conditions risks disqualification, so the FFDG general terms (not provided here) need a careful read.
Please be advised that any exceptions to the specifications or to FFDG’s
- Strict welding, testing and Fermilab oversight. Work needs qualified stainless welders with argon purge, an air test and a hydrotest witnessed by Fermilab ES&H, and you must supply about 2,000 gallons of deionized water for the test.
Contractor shall make arrangements to provide this.
- Electrical work is part of the scope. Scope includes motor feeds, VFDs, conduit, cable tray and fire-stopping, so you need electrical capability or a qualified electrical sub; licensing requirements are not stated in the text provided.
responsible for coring and fire-stopping all required access holes.
- Inconsistent documents in the package. The notice lists NAICS 23822 while the RFP says 238220 'All Other Specialty Trade Contractors', and the sample subcontract is for a different project (PIP-II CPB HX and Pump) with older wage rates, so confirm details before relying on them.
Classification System (NAICS) code for this solicitation is 238220: All Other Specialty Trade
Read from the notice and 12 attachments. 13 not read in full.
- 378854_MR.pdf
- EXHIBIT_4_ED0042585_PIP-II_F37_Bldg_Low_Conductivity_Water_Specification.pdf
- EXHIBIT_3_ED0042584_PIP-II_Low_Conductivity_Water_LCW_System_Instrumentation_Specification.pdf
- EXHIBIT_5_F37_LCW_Electrical_Statement_of_Work_and_prints_rev_A.pdf
- EXHIBIT_24_Sample Subcontract.pdf
- EXHIBIT_23_Performance Bond.pdf
- EXHIBIT_21_Bid_Bond.pdf
- EXHIBIT_20_SF1413-23a.pdf
- EXHIBIT_19_General_Decision_Number_IL20260008_05_18_2026.pdf
- EXHIBIT_18_Injury_Illness_Questionaire.pdf
- EXHIBIT_17_FL-55.pdf
- EXHIBIT_16__2025_Construction_Insurance_Requirements.pdf
- EXHIBIT_15_SARC.pdf: over the file limit for one brief
- EXHIBIT_14_Proposal Certifications.pdf: over the file limit for one brief
- EXHIBIT_13_CESHC.pdf: over the file limit for one brief
- EXHIBIT_12_014100 Quality Requirements.pdf: over the file limit for one brief
- EXHIBIT_10_013100 ESH Requirements.pdf: over the file limit for one brief
- EXHIBIT_9_010010 General Requirements.pdf: over the file limit for one brief
- EXHIBIT_8_FESHM 5034 Pressure Testing.pdf: over the file limit for one brief
- EXHIBIT_7_ADDENDUM TO FESHM.pdf: over the file limit for one brief
- EXHIBIT_6_5031_1 Piping Systems March 2025.pdf: over the file limit for one brief
- EXHIBIT_2_FFDG_General_Terms_and_Conditions.pdf: over the file limit for one brief
- EXHIBIT_25_Drawings.zip: .zip files aren't read yet
- EXHIBIT_22_Payment Bond.pdf: over the file limit for one brief
- EXHIBIT_11_013300 Submittals.pdf: over the file limit for one brief
Full brief
What they want
- Install the LCW pump room equipment: two 50 hp centrifugal pumps (one running, one standby), a shell-and-tube heat exchanger and a 250 gallon expansion tank
- Install process equipment: deionization skid, particulate filters and dissolved-oxygen removal skid
- Supply and weld stainless steel (304/304L) LCW piping, plus valves, flanges, fittings and hardware
- Buy and install instruments (pressure gages, flow transmitters, pressure transmitters, strainers, etc.)
- Build pipe supports and the foundation bases for the pumps
- Do the electrical installation (not control wiring): disconnects, conduit, cable tray, two VFDs, cable pulls, coring and fire-stopping
- Test the system: 12 PSIG air test, then a hydrostatic test using about 2,000 gallons of clean deionized water you must arrange, then witness pump start-up
- Provide welder qualification records, a project-specific QC plan, material test reports, redlined drawings and test reports
- Contract type
- Firm-fixed-price construction subcontract (lump sum price)
- Period of performance
- Not stated for this project. The attached sample subcontract (written for a different Fermilab project, PIP-II CPB HX and Pump) says work is completed within 180 calendar days of notice to proceed. The RFP asks for a project timeline with your proposal.
- Place of performance
- Fermi National Accelerator Laboratory (Fermilab), Batavia, Illinois (DuPage County), F-37 Building mechanical room
- How they'll choose
- Lowest price technically acceptable: award goes to the lowest-priced proposal that meets the acceptability standards for the non-price factors, including past performance. FFDG alone decides what is acceptable.
- Offers due
- November 19, 2026, 2:00 PM Central Time (questions due in writing by November 5, 2026, 4:00 PM Central)
- How to submit
- Email to the Procurement Specialist, Michele Reynolds, micheler@fnal.gov
What they'll judge offers on
- Experience: at least 10 years of business experience on comparable projects (or key personnel with 10 years if the firm is newer)
- Current/past projects of similar size, scope and complexity
- Compliance with safety codes and standards and the ability to meet the specifications and drawings
- Ability to meet the scheduling timeline (a project timeline is required)
What to include when you submit
- Submit two separate parts: Part I Technical Proposal and Part II Business/Cost/Price. Do not bind them together, and the technical part must not mention cost.
- Part I: years in business, key personnel (superintendent and project manager) with resumes and dates of experience, current/past projects, safety compliance, and a project timeline.
- Part II: signed Price Proposal Form (Exhibit 1), bid guarantee or bid bond, Subcontractor Annual Representations & Certifications (SARC), and Proposal Certifications form PUR-466. Keep these as separate documents.
- Include prior work examples and references; missing documents can make the proposal non-responsive.
- A draft small business subcontracting plan (FL-55) is required if you are not a small business and the subcontract exceeds $750,000.
- Put any exceptions to the terms or specifications on a separate sheet on company letterhead.
- Acknowledge any amendments (email, signed amendment, or in the proposal) or risk disqualification.
- Clearly mark proprietary information.
- The offer must stay open for 90 calendar days after the opening date.
- Exhibit 18 (Injury and Illness Data Questionnaire) is included in the package; the RFP does not clearly say it must be returned with the proposal.
You must have
- Open to all businesses: unrestricted, no set-aside
This acquisition is unrestricted and contains no set-aside provisions.
- At least 10 years of business experience as a contractor on projects comparable in size, scope and complexity (or key personnel with 10 years of experience)
The offeror shall demonstrate at least ten (10) years of business
- Bid guarantee of at least 20 percent of the bid price (capped at $3 million) with the proposal, such as a bid bond, certified check or irrevocable letter of credit
The offeror shall provide a bid guarantee in the amount of not less than 20 percent
- Payment bond for 100 percent of the price if the subcontract exceeds $35,000, due within 10 calendar days after the subcontract takes effect
If the subcontract exceeds $35,000.00, the successful offeror is required to furnish FFDG with a
- Performance bond for 100 percent of the price if the subcontract exceeds $150,000
If the subcontract exceeds $150,000.00, the successful offeror is required to furnish FFDG with a
- Insurance before site work: commercial general liability ($1M per occurrence, $2M aggregate), auto ($1M), excess liability, workers' compensation, and pollution liability ($1M), with FFDG, the University of Chicago, URA and the U.S. Government as additional insureds. Completed-operations coverage must be kept for at least 10 years.
(To be maintained for at least 10 years after final
- Qualified welders and welding procedures (WPS, PQR, WPQ) under ASME rules; each welder must also weld a test joint observed by a Fermilab-designated inspector
All welders must be qualified using an appropriate Welding Procedure
- Davis-Bacon wage rates and weekly certified payrolls entered in LCPTracker, also required of lower-tier subcontractors
The Subcontract is subject to the wage and labor standards under the Davis-Bacon Act and the related
- Buy American (FAR 52.225-9) rules for construction materials apply
NOTICE OF BUY AMERICAN REQUIREMENT – CONSTRUCTION MATERIALS
- A project-specific QC plan, plus evidence of a corporate quality assurance program during bidding
The SUBCONTRACTOR SHALL provide a project specific QC plan, this is an addition
- Small business subcontracting plan if you are not a small business and the subcontract exceeds $750,000
A small business subcontracting plan will be required if the awardee does not meet the definition of
Not in the notice text
- Estimated contract value or budget
- Period of performance and schedule for this project (only a sample subcontract for a different project says 180 calendar days from notice to proceed)
- The 25 construction drawing sheets (provided as a zip file that was not read)
- FFDG General Terms and Conditions, the General Requirements, ESH Requirements, Submittals and Quality Requirements sections, the FESHM piping and pressure testing manuals, SARC, Proposal Certifications (PUR-466) and the Payment Bond form (all not provided to this brief)
- Most of the Davis-Bacon wage determination IL20260008 (the text was unreadable), so wage rates are unknown
- Part of the F-37 piping specification (materials and supports sections) was cut out of the text provided
- Any state or local licensing requirements for the plumbing, welding or electrical work
- Relative weight of the evaluation factors and the minimum standard for acceptability
- Whether the Injury and Illness Data Questionnaire (Exhibit 18) must be returned with the proposal
- Whether SAM.gov registration is required to bid on this FFDG subcontract
FedReady checks notices like this against your business profile, tracks deadlines, and alerts you to new matches. Creating an account is free.
Key facts
- Response due
- Nov 19, 2026, 8:00 PM UTC
- Posted
- Oct 8, 2026
- Notice type
- Solicitation
- Solicitation
- 378854_MR
- Agency
- Department of Energy
- Office
- Fermilab - DOE Contractor
- Set-aside
- No Set aside used
- NAICS
- 23822
- Product/service code
- K056
- Business type
- Construction & renovation
- Place of performance
- Batavia, IL, 60510
- Contracting contact
- Michele Reynoldsmicheler@fnal.gov6308402448
Before you respond
Full notice text from SAM.gov
Similar open opportunities
- 671-24-004 NRM Replace 2nd Floor RoofThe VA's Network Contract Office 17 is seeking sealed bids (an Invitation for Bid) to replace the 2nd floor roof at the South Texas Veterans Healthcare System in San Antonio, TX.…
- Construction of Ogden Elevator Cab Interiors Jesse Brown Medical CenterThe VA's Great Lakes Acquisition Center is seeking a Service-Disabled Veteran-Owned Small Business (SDVOSB) to upgrade the interiors of four elevator cabs in the Ogden Pavilion…
- CON | Z2DA | REPLACE CHILLER 1 B104 | 580-24-111 | PRESOLICITATIONThe VA medical center in Houston, TX plans to replace a failed 1,000-ton chiller (plus transformer, piping, valves and controls) in Building 104.
- 36C25726Q0431 504-26-006 RE FINISH B4 N AND F ADMThe VA (Network Contracting Office 17, Temple TX) wants a contractor to replace about 1,200 sq ft of flooring (luxury vinyl tile plus rubber cove base) in the Food and Nutrition…
- Trade and Cargo AcademyThe Army Corps of Engineers Charleston District wants a contractor to build a Trade and Cargo Academy and a Cargo Security and Seized Property Training Facility at the Federal…