Solicitation
Request for Proposal (RFP) - Resilient Missile Warning Tracking (RMWT) Low Earth Orbit (LEO) Ground Entry Points (GEPs)
Department of Defense · Department of the Air Force
A newer version of this notice was posted Nov 19, 2026. It moves the due date from Nov 2, 2026 to Dec 18, 2026, which is the date shown on this page. See the latest version.
AI summary Beta
Summary of the version posted Sep 29, 2026. The notice was amended Nov 19, 2026. The due date moved from Nov 2, 2026 to Dec 18, 2026. Check what else changed on SAM.gov. This summary may miss requirements: 4 of 15 attachments weren't read (Attachment 7.c. RMWT LEO GEPs Unpriced BOE Template IDIQ Base.xlsx, Attachment 7.c.1 RMWT LEO GEPs Unpriced BOE Template TO 01.xlsx and 2 more). Check the attachments on SAM.gov.
The Space Development Agency (SDA) wants one prime contractor to design, build, install, test and maintain Ground Entry Points (GEPs), the ground stations that connect to its Low Earth Orbit missile warning and tracking satellites, at multiple sites around the world. It is a very large, open-competition IDIQ contract (up to $369 million) with a first task order awarded at the same time. Ordering runs from March 2027 to September 2031, with an option period to September 2035. Much of the technical detail is in controlled (CUI) or classified documents that are only released on request.
Who can bid (7)
- Open competition with no set-aside; company size standard is 1,000 employees under NAICS 541715. Small businesses must show at least 50% self-performance for services; large businesses must meet a 5% small business participation minimum. From Attachment 5.a - RMWT LEO GEPs Model IDIQ Contract - FA240126R0003.pdf
- To access the Bidders' Library (which holds CUI technical documents): U.S. citizens at a cleared defense contractor with an active Joint Certification Program (JCP) certification, a CAGE code and an active SAM.gov registration From RMWT LEO GEPs Cover Letter_RFP_18Sep26_signed.pdf
- Active SAM.gov registration and a CAGE code From RMWT LEO GEPs Cover Letter_RFP_18Sep26_signed.pdf
Show all 7Show fewer
- Organizational conflict of interest limits: you cannot bid or perform on other Tranche 3 contracts without an OCI plan, and an SDA SETA contractor cannot also be the GEPs contractor From Attachment 7 - RMWT LEO GEPs Section L Proposal Instructions.pdf
- Facility security and foreign ownership disclosure (FSO and ISSM contacts, cleared personnel list, FOCI mitigation if foreign owned) in the security volume; a facility clearance is needed to submit classified material From Attachment 7.e. RMWT LEO GEPs Personnel & Facilities Template.docx
- Cybersecurity Maturity Model Certification (CMMC) status in SPRS at the required level for any system handling federal contract information or CUI (the level is left blank in the template) From Attachment 5.a - RMWT LEO GEPs Model IDIQ Contract - FA240126R0003.pdf
- Accounting system that meets DFARS 252.242-7006, or the pre-award accounting system forms completed before proposal submission
How to submit: Electronic proposals through DoD SAFE (https://safe.apps.mil), after requesting a SAFE Drop-off by email to ussf.pentagon.sda.mbx.fa240126r-006@mail.mil. Volume VII (cover letter and SF 33 offer) is to be emailed to the same address., due 02 November 2026 at 16:00 (4:00 PM) Eastern Time. Questions were due 2 October 2026 at 16:00 ET. SAFE drop-off requests and notice of any classified submission are due 23 October 2026.. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
- Serious: Very large, complex program. Up to $369 million over many years, worldwide construction and equipment work, and a past performance bar tied to multiple space vehicle vendors; a small firm would most likely need to team with an established prime or be a subcontractor. From Attachment 6. - RMWT LEO GEPs IDIQ Ordering Procedures.pdf
- Serious: Controlled and classified documents, restricted access. The statements of work, technical requirements and DD254 are CUI, and the Bidders' Library is limited to cleared U.S. citizens at JCP-certified contractors, so you may not be able to read the full requirements without that access. From RMWT LEO GEPs Cover Letter_RFP_18Sep26_signed.pdf
- Serious: OCI blocks other Tranche 3 work. Winning or even bidding on this contract can bar you from other Tranche 3 satellite and ground contracts, and you must guarantee you will avoid conflicts for the life of the contract. From Attachment 7 - RMWT LEO GEPs Section L Proposal Instructions.pdf
Show all 10Show fewer
- Worth checking: Questions were due Oct 2, 2026. Check the amendments for the agency's answers.
- Worth checking: Heavy proposal with strict formatting rules. Seven volumes with page limits, DoD SAFE encryption steps and a drop-off request due 23 October; a late or nonconforming file can knock out the whole proposal. From Attachment 7 - RMWT LEO GEPs Section L Proposal Instructions.pdf
- Worth checking: Funds not yet available. The Government is not obligated until money is appropriated and may award no contract at all, so bid costs could be spent for no award. From RMWT LEO GEPs Cover Letter_RFP_18Sep26_signed.pdf
- Worth checking: Past performance must be large and similar. Relevance is judged against supporting at least 6 space vehicle vendors and many globally dispersed sites, which a small or new firm may lack unless a teammate has it. From Attachment 8 - RMWT LEO GEPs Section M Eval Factors.pdf
- Worth checking: Hidden quantities for materials pricing. Your material unit prices will be multiplied by Government quantities you cannot see, which makes pricing materials risky. From Attachment 8 - RMWT LEO GEPs Section M Eval Factors.pdf
- Minor: Fewer subcontract tiers rated higher. Teaming structures with many tiers score lower, which affects how a small business can fit into a team. From Attachment 8 - RMWT LEO GEPs Section M Eval Factors.pdf
- Minor: Documents disagree on factor order. Section M lists Price as the last factor and calls the factors descending in importance, but the importance paragraph puts Price fourth and Small Business Participation last; also, Volume VII is emailed while other volumes go through DoD SAFE. From Attachment 8 - RMWT LEO GEPs Section M Eval Factors.pdf
Read from the notice and 11 attachments. 4 of 15 not read. Show which files.
- RMWT LEO GEPs Cover Letter_RFP_18Sep26_signed.pdf (read)
- Attachment 7 - RMWT LEO GEPs Section L Proposal Instructions.pdf (read)
- Attachment 8 - RMWT LEO GEPs Section M Eval Factors.pdf (read)
- Attachment 5.a - RMWT LEO GEPs Model IDIQ Contract - FA240126R0003.pdf (read)
- Attachment 5.b - RMWT LEO GEPs Model Task Order 01 - FA2401XXF000X.pdf (read)
- Attachment 6. - RMWT LEO GEPs IDIQ Ordering Procedures.pdf (read)
- Attachment 7.b. RMWT LEO GEPs Small Business Participation.docx (read)
- Attachment 7.e. RMWT LEO GEPs Personnel & Facilities Template.docx (read)
- Attachment 4.a - RMWT LEO GEPs IDIQ DD Form 1423, Contract Data Requirements List (CDRLs).pdf (read)
- Attachment 4.b - RMWT LEO GEPs Task Order 01 DD Form 1423, Contract Data Requirements List (CDRLs).pdf (read)
- Attachment 7.a.RMWT LEO GEPs Past Performance Questionnaire (PPQ).docx (read)
- Attachment 7.c. RMWT LEO GEPs Unpriced BOE Template IDIQ Base.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- Attachment 7.c.1 RMWT LEO GEPs Unpriced BOE Template TO 01.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- Attachment 7.d RMWT LEO GEPs Price Template.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- Attachment 9 - RMWT LEO GEPs DD2794 CSDR Plan.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
Full summary
What they want
- GEP site civil engineering: detailed design through completed construction
- Procure, install, integrate, test and verify communications shelters, antennas and antenna electronics, optical terminals and electronics, and site networking equipment and software
- Site surveys, security measures installation and trade studies or technical assessments at each GEP location
- Test hardware, training and onsite test support
- Maintenance of GEP sites and terminals
- Program management and systems engineering, including configuration management, integration and test
- Task Order 1: develop 7 Ground Support Equipment (GSE) units, buy 10 dual-band S/Ka antennas, run a technical investigation, and expand 1 CONUS RF GEP integration and test
- Deliver required data and reports (CDRLs)
- Contract type
- IDIQ (indefinite delivery, indefinite quantity), hybrid: firm-fixed-price lines for labor, civil engineering and materials; cost-no-fee lines (not-to-exceed) for travel and other direct costs. Task Order 1 is to be awarded with the IDIQ.
- Period of performance
- IDIQ ordering period 31 March 2027 to 30 September 2031, plus an option period 1 October 2031 to 30 September 2035. Task Order 1 is 12 months (31 March 2027 to 30 March 2028) plus four 12-month options. Award announcement expected 2Q FY27.
- Place of performance
- Notice lists Washington, DC. The work is at multiple, globally dispersed GEP sites on U.S. military and foreign sovereign facilities (nominal plan: 5-8 new and 1-4 updated sites).
- Estimated value
- IDIQ ceiling of $369,000,000 across all delivery/task orders
- How they'll choose
- Best value tradeoff (FAR Part 15 source selection). Technical, Management and Past Performance combined are more important than Price. Award may go to a higher-rated, higher-priced offeror. One contract will be awarded, and the Government may award none.
- Offers due
- 02 November 2026 at 16:00 (4:00 PM) Eastern Time. Questions were due 2 October 2026 at 16:00 ET. SAFE drop-off requests and notice of any classified submission are due 23 October 2026. (from the version posted Sep 29, 2026; amended since)
- How to submit
- Electronic proposals through DoD SAFE (https://safe.apps.mil), after requesting a SAFE Drop-off by email to ussf.pentagon.sda.mbx.fa240126r-006@mail.mil. Volume VII (cover letter and SF 33 offer) is to be emailed to the same address.
- Page limits
- Vol I Technical: 35 pages (rights assertions and unpriced BOE excluded). Vol II Management: 30 pages (IMS and CWBS unlimited; staffing plan up to 10 pages). Vol III Past Performance: 12 pages (up to 4 citations, 3 pages each). Vol IV Price: unlimited. Vol V OCI: unlimited. Vol VI Small Business Participation: 5 pages. Vol VII Model Contract: unlimited.
What they'll judge offers on
- Factor 1: Technical (Understanding of Requirements; Feasibility and Completeness of Approach; Scalability)
- Factor 2: Management (Project Management; Schedule Management; Subcontractor/Teammate and Foreign Subcontractor Management; Security and CUI/Classified Data Handling)
- Factor 3: Past Performance
- Price (Factor 5): Total Evaluated Price, reasonableness, unbalanced pricing, completeness
- Factor 4: Small Business Participation (least important)
What to include when you submit
- Submit seven volumes, each as its own searchable PDF; .zip files are not accepted
- Label each file with the RFP number, prime name, proposal title and volume number
- In DoD SAFE, check 'Encrypt every file' and the pick-up email box, and send the password in a separate email with the required subject line
- Request a SAFE Drop-off by email by 23 October 2026 even if you already use DoD SAFE; the response comes by 27 October 2026
- Times New Roman 12 pt text (10 pt in tables), 1-inch margins, single spacing, line numbers in the left margin
- Mark CUI per DoDI 5200.48; email the unclassified mailbox by 23 October 2026 if you need to submit anything classified
- Cover letter signed by an authorized official: proposal firm at least 180 days, accounting system statement, any exceptions to terms with rationale, assumptions, subcontractor list
- Complete the SF 33 offer, Section B summary (Attachment 7e) and Section K representations and certifications
- Large businesses: Small Business Participation Commitment Document (5% minimum); small businesses: SBPCD showing at least 50% self-performance for services
- Include an OCI assessment (and an OCI plan if a conflict exists or you plan to bid other Tranche 3 work)
- Complete the past performance questionnaires (Attachment 7a) and the Personnel and Facilities template (Attachment 7e)
- Only one proposal per offeror; alternate proposals are not accepted
Not in the notice text
- The IDIQ and Task Order 1 statements of work and the Technical Requirements Document are CUI and were not read (it may be an attached file the AI skipped; check SAM.gov)
- The CDRL forms (Attachments 4.a and 4.b) did not load and could not be read
- The price template, unpriced basis of estimate templates and CSDR plan spreadsheets (Attachments 7.c, 7.c.1, 7.d and 9) were not read
- About 24,600 characters in the middle of the Section L proposal instructions were not read (it may be an attached file the AI skipped; check SAM.gov) (including most Volume I and II details and the start of the Price volume instructions)
- About 107,500 characters in the middle of the model IDIQ contract were not read (it may be an attached file the AI skipped; check SAM.gov) (special requirements, clauses and representations)
- The required CMMC level, which is blank in the model contract
- Exact GEP site locations and the number of task orders expected beyond Task Order 1
- Whether there is a current contractor; the notice does not name one
- Why the notice lists PSC AC13 while the model contract lists AC33
More to check before you bid
- The AI summary also reads the notice as naming requirements:
- The AI summary's reading of the notice and its attachments says a bidder needs: DD 2345 export approval; CMMC certification. The summary's list is under Who can bid; check it in the notice before you bid.
Notice details
Notice type, codes, versions and files
- Posted
- Sep 29, 2026
- Notice type
- Solicitation
- Office
- FA2401 Space Development Agency SDA, Chantilly, VA
- Product/service code
- AC13 · National Defense R&D Services; Department of Defense – Military; Experimental Development
- Business type
- Engineering, architecture & research (FedReady's grouping, from NAICS 541715)
- Versions
9 versions have been posted, newest first.
- Nov 19, 2026 · AmendmentDue Dec 18, 2026
- Nov 13, 2026 · AmendmentDue Dec 18, 2026 (changed)
- Nov 6, 2026 · AmendmentDue Nov 23, 2026
- Nov 5, 2026 · AmendmentDue Nov 23, 2026
- Oct 27, 2026 · AmendmentDue Nov 23, 2026
- Oct 13, 2026 · AmendmentDue Nov 23, 2026 (changed)
- Sep 29, 2026 · Amendment 0001 (this version)Due Nov 2, 2026
- Sep 25, 2026 · AmendmentDue Nov 2, 2026
- Sep 18, 2026 · SolicitationDue Nov 2, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- SYSTEM DELTA 84 (SYD 84/MT) MEDIUM EARTH ORBIT MISSILE WARNING / MISSILE TRACKING EPOCH 3 and EPOCH 4, REQUEST FOR INFORMATION (RFI)A sources sought request for information (RFI) from Space Systems Command (SSC), Space Force, on building the Medium Earth Orbit Missile Warning/Missile Tracking Epochs 3 and 4…
- Tracking Layer Tranche 4 On-orbit Demonstrations and Operations Request for Information
- Missile Defense Agency - Nimble Options for Buying Layered Effects (NOBLE) AnnouncementMissile Defense Agency (MDA) umbrella announcement HQ0860-25-S-0001, Nimble Options for Buying Layered Effects (NOBLE), is not a bid opportunity itself: no white papers,…
- Mission System R and D Support for Blossom Point Tracking Facility (BPTF)
- Resilient Open & Agile Avionics System & Technology Development (ROAASTD)The Air Force Research Laboratory's Sensors Directorate (Wright-Patterson AFB, Ohio) wants research and development on resilient, open-standards, agile avionics and…