Combined Synopsis/Solicitation
RF Roof Replacement Project
Department of Energy
AI summary Beta
This summary may miss requirements: 2 of 14 attachments weren't read (Payment Bond SF25A-23a.pdf, 7. PPPL PQA Supplier Quality Survey R2 Construction.pdf). Check the attachments on SAM.gov.
Princeton Plasma Physics Laboratory, run for the Department of Energy by Princeton University, wants a firm to replace two failing built-up roofs (buildings C40 and C41) in Princeton, NJ, under RFP27-005JR. To take part, the notice says firms must send the acknowledgment form NLT 4:00 PM on November 9, 2026 (passed). It is full and open competition with no set-aside. The response due date is December 10, 2026, 4:00 PM Eastern. A 20% bid bond is due with the proposal, and the award goes to the lowest-priced technically acceptable offer.
Who can bid (5)
- Send the signed acknowledgment form to PPPL by 4:00 PM on November 9, 2026; the notice makes this a condition of taking part
- Bid bond or certified check for at least 20% of the total proposed price, submitted with the proposal From RFP 27-005JR Invitation Cover Letter.pdf
- Registration as a Princeton University supplier (the acknowledgment form also asks you to affirm registration in Princeton Prime)
Show all 5Show fewer
- Safety record: three-year average EMR of 1.00 or less and injury rates at or below 85% of the industry rate for heavy construction From RFP 27-005JR Instructions for Proposal Preparation.pdf
- Key personnel (Project Manager, Construction Superintendent, Certified Safety Professional) with experience on two or more similar projects within the past ten years From RFP 27-005JR Evaluation and Basis for Award.pdf.pdf
How to submit: One electronic PDF copy emailed to the PPPL Procurement Specialist, Jimmy Russell (jrussell@pppl.gov); no faxed proposals. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (15)
From the version posted Nov 9, 2026.
- Serious: Date passed (Nov 9, 2026): Acknowledgment form was a condition of taking part. The notice says a firm must submit the acknowledgment form NLT 4:00 PM on November 9, 2026 to be eligible, and drawings are released only after that and other steps, so a firm that missed it may be shut out.
- Serious: 20% bid bond with the proposal. A bid bond or certified check for at least 20% of the total price must come with the proposal, and a missing one may make the proposal nonresponsive. Many small firms need a surety to arrange this. From RFP 27-005JR Invitation Cover Letter.pdf
- Serious: 100% performance and payment bonds after award. The winner must furnish both bonds at the full subcontract price within 10 calendar days of award, plus insurance certificates. From RFP 27-005JR Invitation Cover Letter.pdf
Show all 15Show fewer
- Serious: Strict safety record screen. Offers are judged on a three-year average EMR of 1.00 or less and injury rates at or below 85% of the industry rate; a weaker record must be explained and may fail the technical review. From RFP 27-005JR Instructions for Proposal Preparation.pdf
- Serious: Drawings not posted; released on request. The project drawings are sent only after you email your intent to join the pre-proposal meeting, a signed acknowledgment, a lead proposal manager's name and a written drawings request. Pricing depends on them.
- Worth checking: Construction wage rules apply. The Davis-Bacon wage rules (federal minimum construction wages) apply, with weekly certified payroll reports. The wage determination is in RFP Section V, which was not among the files read. From RFP 27-005JR Invitation Cover Letter.pdf
- Worth checking: The site visit was Nov 17, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From RFP 27-005JR Instructions for Proposal Preparation.pdf
- Worth checking: Documents disagree on how many past projects to list. The instructions ask for at least three prior projects, while the evaluation document asks for at least two. Plan for three and ask the Procurement Specialist which governs. From RFP 27-005JR Instructions for Proposal Preparation.pdf
- Worth checking: Documents disagree on which years of OSHA forms to send. The instructions ask for OSHA Forms 300 and 300A for 2022 to 2024, while the evaluation document asks for 2024 to 2026. Ask which years are required. From RFP 27-005JR Instructions for Proposal Preparation.pdf
- Worth checking: Proposal validity period differs: 100 days or 90 days. The instructions say proposals stay firm for 100 calendar days, while the pricing form says 90 days from the closing date. Ask which governs. From RFP 27-005JR Instructions for Proposal Preparation.pdf
- Worth checking: Asbestos work coordination. PPPL handles any asbestos removal, and the roofer must follow right after its abatement contractor and coordinate with PPPL. The design calls for cutting existing asbestos panels in the field, which PPPL arranges separately. From SOW RF Roof Replacement Work.pdf
- Minor: Three phases named for two buildings. The statement of work asks for pricing for Phase A, B and C, but names two buildings and the pricing form has a single line. Ask what each phase covers. From SOW RF Roof Replacement Work.pdf
- Minor: Questions were due Nov 24, 2026. Check the amendments for the agency's answers. From RFP 27-005JR Instructions for Proposal Preparation.pdf
- Minor: Daytime work hours only. Work is expected 7:00 AM to 3:30 PM, Monday through Friday; off-hours work needs PPPL approval and may carry noise limits. From SOW RF Roof Replacement Work.pdf
- Minor: Long warranty. The roofer must issue a manufacturer's 30-year warranty and a 2-year installer's warranty, which affects the choice of roofing system and supplier. From SOW RF Roof Replacement Work.pdf
Read from the notice and 12 attachments. 2 of 14 not read. Show which files.
- RFP 27-005JR Invitation Cover Letter.pdf (read)
- RFP 27-005JR Instructions for Proposal Preparation.pdf (read)
- RFP 27-005JR Evaluation and Basis for Award.pdf.pdf (read)
- RFP 27-005JR E-Verify Certification Document.pdf (read)
- Specification-RF Roof Replacement.pdf (read)
- SOW RF Roof Replacement Work.pdf (read)
- Performance Bond SF25.pdf (read)
- PPPL-PD-G Provisions and Conditions for FP Construction Subcontracts_ Rev 8_ 052022.pdf (read)
- PPPL-PD-T Provisions For Work Performed On The PPPL Site-Rev 6_Oct2026.pdf (read)
- RFP 27-005JR Request for Project Drawings.pdf (read)
- RFP 27-005JR Offeror Information and Pricing Form.pdf (read)
- RFP 27-005JR Acknowledgment Form.pdf (read)
- Payment Bond SF25A-23a.pdf: not summarized: open it on SAM.gov
- 7. PPPL PQA Supplier Quality Survey R2 Construction.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Tear off the existing membrane, cover board, insulation, metal trim, flashing and coping on the C40 RF Building and C41 CS Building roofs, and install new roofing
- Remove and recycle stone ballast, and replace roof drains, scuppers, curbs, guardrails and other roof parts as shown in the as-bid design drawings
- Remove, protect and reinstall roof fans, equipment and fall protection anchors, and add secondary drainage
- Follow behind PPPL's asbestos abatement contractor, and price an add alternate for ending the membrane without cutting the asbestos panels
- Price an add alternate line for metal duct protectors where ductwork changes
- Give a manufacturer's 30-year warranty and a 2-year installer's warranty when the work is done
- Work 7:00 AM to 3:30 PM, Monday through Friday, under PPPL safety rules, with weekly status meetings and daily inspection reports
- Contract type
- Firm-fixed-price (FFP: one set price, whatever the work ends up costing) subcontract under Princeton University's Department of Energy prime contract
- Period of performance
- Contract length not stated; the pricing form asks for a progress schedule that assumes a notice to proceed (the go-ahead to start work) on January 5, 2027
- Place of performance
- Princeton Plasma Physics Laboratory, 100 Stellarator Road, James Forrestal Campus, Princeton, NJ
- Estimated value
- Not stated
- Contract vehicle
- Subcontract under Princeton University's Department of Energy Prime Contract No. DE-AC02-09CH11466; not a schedule or contract-holder-only buy
- How they'll choose
- Lowest-price technically acceptable (LPTA: the cheapest offer that meets the minimum requirements). The evaluation document also calls the award a best value decision, but its basis for award is the lowest priced qualified and responsible offer.
- Offers due
- December 10, 2026, 4:00 PM Eastern
- How to submit
- One electronic PDF copy emailed to the PPPL Procurement Specialist, Jimmy Russell (jrussell@pppl.gov); no faxed proposals
What they'll judge offers on
- Responsiveness: pass or fail on following the RFP's format and instructions
- Factor 1, Project Management Staffing: construction management methods, key personnel (Project Manager, Construction Superintendent, Certified Safety Professional) with two or more similar projects in the past ten years
- Factor 2, Relevant Projects: similar past projects completed within the past ten years, with owner references
- Factor 3, Safety Record and Program: three-year average experience modification rate (EMR: an insurance safety rating) of 1.00 or less, injury rates at or below 85% of the industry rate, corporate safety program
- Factor 4, Quality Assurance: corporate quality program and the completed PQA Supplier Quality Survey
- Price: checked for fair and reasonable; the lowest price among acceptable offers wins
What to include when you submit
- Send Part I (financial and administrative) and Part II (technical capability) separately; no pricing in Part II
- Part I: the Offeror Information and Pricing Form with a schedule of values and a progress schedule, initialing acceptance of the Sample Subcontract terms or listing exceptions
- Part I: the signed PPPL Representations and Certifications Booklet, the E-Verify flow-down certification, and confirmation of Princeton University supplier registration
- Include a bid bond or certified check for at least 20% of the total proposed price
- Price the roof work as one project (Phases A, B and C together) and as separate phases, per the statement of work's deliverables list
- Price the add alternates for the asbestos-panel termination detail and for metal duct protectors
- Part II: key personnel list (name, title, duties, full-time percentage, resume) for the Project Manager, Construction Superintendent and Certified Safety Professional
- Part II: at least three prior projects within the past ten years (the evaluation document says at least two), each with title, contract amount at start and finish, description and location, owner and architect contacts, and a discussion of delays and cost growth
- Part II: corporate quality program and the completed PQA Supplier Quality Survey
- Part II: OSHA (Occupational Safety and Health Administration) Forms 300 and 300A, experience modification rating (EMR) backup from the insurance carrier, corporate environment, safety and health (ES&H) program, and Part 1 of the Construction ES&H Plan (Section 013100)
- Joint ventures or teams send the safety and EMR information for each company
- Name files like XYZCompany_RFP_25-042R_Part_I.pdf
- Proposals are to be firm for 100 calendar days from the closing date
- Send questions by email to Jimmy Russell; oral answers are not binding
After award, you must have
- Performance and payment bonds, each for 100% of the subcontract price, within 10 calendar days of award From RFP 27-005JR Invitation Cover Letter.pdf:
…performance and payment bonds, each in an amount at least equal to 100% of the subcontract price…
Not in the notice text
- Much of the technical specification (Specification-RF Roof Replacement.pdf) was only partly read, and the project drawings (the as-bid design package) are not posted; they are released on request. Check them on SAM.gov or with PPPL.
- The Davis-Bacon wage determination, the Sample Subcontract (Section II) and the other RFP Section V forms are not in the files read.
- Payment Bond SF25A-23a.pdf and 7. PPPL PQA Supplier Quality Survey R2 Construction.pdf are attached but were not read; the survey must be completed with the proposal.
- The notice does not give the contract length or completion date; only a notice to proceed date of January 5, 2027 for the progress schedule.
- The notice gives no dollar value for the work.
- Whether the Pre-Proposal Videoconference is a site visit is unclear: the notice calls it a site visit or pre-bid meeting, and the cover letter says no site visit has been scheduled.
- The documents do not say whether any of the work may be done remotely.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 9, 2026
- Notice type
- Combined Synopsis/Solicitation
- Office
- Princeton Lab - DOE Contractor, NJ
- Product/service code
- Y1EZ · Construction of Other Industrial Buildings
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 238160)
- Versions
6 versions have been posted, newest first.
- Nov 9, 2026 · Amendment 0005 (this version)Due Dec 10, 2026
- Nov 5, 2026 · Amendment 0004Due Dec 10, 2026
- Nov 2, 2026 · Amendment 0003Due Dec 10, 2026
- Nov 2, 2026 · Amendment 0002Due Dec 10, 2026
- Nov 2, 2026 · Amendment 0001Due Dec 10, 2026
- Oct 30, 2026 · Combined Synopsis/SolicitationDue Dec 10, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- Dworshak Powerhouse Roof ReplacementThe U.S. Army Corps of Engineers, Walla Walla District, is taking bids under solicitation W912EF27BA001 to replace the Dworshak Dam powerhouse roofs near Ahsahka, Idaho, with…
- FCI Bastrop - Remove and Replace Housing Unit Roofs (10) 27Z5BB3The Federal Bureau of Prisons (FBOP) is doing market research for a firm-fixed-price roofing project at Federal Correctional Institution (FCI) Bastrop, Texas, to remove and…
- GAOA Mesa Falls VC Roof Repairs in Caribou-Targhee National Forest, IdahoThe USDA Forest Service (Caribou-Targhee National Forest) wants a small business roofing contractor to replace the corrugated metal roof and flashing on the Mesa Falls Visitor…
- Roof Assessment and Repair at the Albuquerque Area Indian Health Service Healthcare FacilitiesSolicitation 75H70727Q00004 is set aside for Indian Small Business Economic Enterprises (ISBEE), with a second tier open to other small businesses if there is too little…
- FMC Lexington - Remove and Replace Treadway RoofCombined synopsis/solicitation 15BBNF27R10900002: the Federal Bureau of Prisons (Field Acquisition Office) wants a small business to remove and replace the existing 9,500 sq. ft.…