Solicitation
Increase Emergency Power
Department of Veterans Affairs
SDVOSB set-aside · RI
AI summary Beta
This summary may miss requirements: 1 of 9 attachments weren't read (S02_Wage Determination RI20260001 10012026.pdf). Check the attachments on SAM.gov.
Only the 17 holders of the VISN 1 Construction MATOC (a pre-awarded group of construction contractors) can bid on solicitation 36C24126Q0707, set aside for certified service-disabled veteran-owned small businesses (SDVOSBs). The Department of Veterans Affairs wants two diesel generators and new electrical distribution to add emergency power at the Providence, Rhode Island VA Medical Center main hospital. Work must finish within 630 calendar days of the notice to proceed. The response due date is December 18, 2026, 3:30 PM Eastern.
Who can bid (7)
- Limited competition: only the 17 holders of the VISN 1 Construction MATOC can bid, not every business that meets the set-aside.
- Be one of the VISN 1 Construction MATOC awardees listed in the solicitation; no other firm may submit an offer From S02_ Solicitation 36C24126Q0707.docx
- Be a certified service-disabled veteran-owned small business (SDVOSB) and small under the NAICS code, confirmed in the SBA Small Business Search From S02_ Solicitation 36C24126Q0707.docx
Show all 7Show fewer
- Provide a bid guarantee (bid bond on Standard Form 24) of 20 percent of the bid price or $3,000,000, whichever is less From S02_ Solicitation 36C24126Q0707.docx
- Provide performance and payment bonds (Standard Forms 25 and 25A) at 100 percent of the contract price if awarded From S02_ Solicitation 36C24126Q0707.docx
- Sign the limitations on subcontracting certificate: for general construction, no more than 85 percent of the amount paid may go to firms that are not certified SDVOSBs or veteran-owned small businesses From S02_ Solicitation 36C24126Q0707.docx
- Carry the minimum insurance required under the base MATOC for the whole task order From S02_ Solicitation 36C24126Q0707.docx
How to submit: Email to Andrew.Merical@va.gov, sent by the prime contractor. No hard copies or faxes. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
From the version posted Nov 4, 2026.
- Serious: Only MATOC holders can bid. Only the 17 awardees of the VISN 1 Construction MATOC may send offers. If you are not one of them, you cannot bid on this task order. From S02_ Solicitation 36C24126Q0707.docx
- Serious: Certified SDVOSB set-aside. The task order is reserved for certified service-disabled veteran-owned small businesses, and the VA checks the SBA certification database. From S02_ Solicitation 36C24126Q0707.docx
- Serious: Bid bond, then performance and payment bonds. A bid bond of 20 percent of the price or $3,000,000 (whichever is less) comes with the offer. Full performance and payment bonds follow at award, so surety capacity matters. From S02_ Solicitation 36C24126Q0707.docx
Show all 10Show fewer
- Serious: Proprietary paralleling gear from Russ Electric. The VA says only Russ Electric technicians can connect and program the existing paralleling gear, so the winner must hire them or have the controls installed under their direction. From S02_ Brand Name Justification - Russ Electric CO Final Redacted.pdf
- Serious: Large job with a demanding experience test. The VA puts the work between $5,000,000 and $10,000,000. It wants three similar projects, including diesel generators, medium voltage switchgear, duct banks and a stand-alone utility building. From S02_ Solicitation 36C24126Q0707.docx
- Worth checking: 630-day schedule inside an operating hospital. Utility shutdowns and noisy, dusty or smelly work must be done off hours at no added cost, and an infection control plan is required. From S02_Final SOW.docx
- Worth checking: The site visit was Nov 12, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From S02_ Solicitation 36C24126Q0707.docx
- Worth checking: Construction wage rules apply. The Davis-Bacon rule (now called Construction Wage Requirements) applies, using General Decision RI20260001 or the one current at award. That file is a scanned PDF that was not read. From S02_ Solicitation 36C24126Q0707.docx
- Worth checking: Subcontracting limit of 85 percent for general construction. No more than 85 percent of the amount paid may go to firms that are not certified SDVOSBs or veteran-owned small businesses, so most of the work needs a qualifying team. From S02_ Solicitation 36C24126Q0707.docx
- Minor: Questions were due Nov 20, 2026. Check the amendments for the agency's answers. From S02_ Solicitation 36C24126Q0707.docx
Read from the notice and 8 attachments. 1 of 9 not read. Show which files.
- S02_ Solicitation 36C24126Q0707.docx (read)
- S02_Specifications.pdf (read)
- S02_Final SOW.docx (read)
- S02_ Brand Name Justification - Russ Electric CO Final Redacted.pdf (read)
- S02_PCRA Signed.pdf (read)
- S02_Brand Name or Equal Memorandum - Caterpillar.docx (read)
- S02_Drawings.pdf (read)
- Past Performance Questionnaire.docx (read)
- S02_Wage Determination RI20260001 10012026.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Add two diesel generators with paralleling capability (they run together) near parking lot 8
- Install the matching distribution and control equipment in the basement mechanical room of Building 1
- Build two electrical duct banks in one trench from the new Control Building to Building 1, with a conduit to Building T18
- Tie new paralleling controls into the existing Russ Electric paralleling gear, which is proprietary
- Provide a 600 kW Caterpillar generator or approved equal, meeting NFPA 99 and NFPA 110 Level 1 rules
- Coordinate with ongoing hospital projects and do disruptive work off hours at no added cost
- Deliver submittals, an infection control plan, an interim life safety plan, as-built drawings and operation and maintenance manuals
- Contract type
- Task order under the VISN 1 Construction MATOC (Multiple Award Task Order Contract), lump sum line item, best value tradeoff
- Period of performance
- Start within 10 calendar days after the notice to proceed; finish no later than 630 calendar days
- Place of performance
- Providence VA Medical Center, 830 Chalkstone Ave., Providence, RI 02908
- Estimated value
- Magnitude of construction: between $5,000,000 and $10,000,000
- Contract vehicle
- PCAC VISN 1 Construction MATOC (awarded 12/16/2025 under solicitation 36C77624R0098); only its awardees may submit offers
- How they'll choose
- Best value tradeoff, single award. Technical factors and past performance are equal, and together significantly more important than price
- Offers due
- December 18, 2026, 3:30 PM Eastern
- How to submit
- Email to Andrew.Merical@va.gov, sent by the prime contractor. No hard copies or faxes
What they'll judge offers on
- Factor 1 Schedule: a project-specific schedule with a critical path and milestones, scheduling software and coordination of the team
- Factor 2 Management Approach: key personnel, sequence of work including the local utility and subcontractors, cost control successes, obstacles faced on similar projects
- Factor 3 Technical Expertise: up to three similar projects from the last five years in medium voltage electrical distribution
- Past Performance: quality, timeliness, problem resolution, cost control and business relations
- Price
What to include when you submit
- Include a cover page with the solicitation number and project title, company name, Tax ID number, and points of contact with address, phone and email; for a joint venture, the Tax ID and contact for each member
- Include the signed Standard Form 1442 (SF 1442, the construction offer form) and acknowledgement of any amendments
- Submit the offer guarantee (bid bond) with the price proposal
- Return the signed VAAR 852.219-75 limitations on subcontracting certificate with the proposal
- Send a technical proposal covering schedule, management approach and technical expertise, plus past performance, and a separate price proposal
- Submit a project-specific schedule showing the critical path, major milestones, and start and completion dates
- Describe a maximum of three similar projects finished or 90 percent complete in the last five years, with location, description, estimated and final cost, trades, dates and customer contact
- At least one project must show underground electrical duct banks, vaults and concrete equipment pads
- At least two projects must show diesel generators and medium voltage indoor or outdoor equipment, including indoor switchgear and cabling
- At least one project must show a stand-alone outdoor utility building
- Offers must stay open at least 120 calendar days for Government acceptance
- Send requests for information (RFIs) in writing by email only, from the prime contractor; no phone questions
After award, you must have
- Every employee, including subcontractor staff, must complete form SF85 (a background questionnaire) and be approved before entering the site From S02_ Solicitation 36C24126Q0707.docx:
Each employee involved with this requirement from the Contractor and any Subcontractor will be required to complete a SF85 form…
Current contractor
No incumbent is named. The justification says Russ Electric's existing paralleling gear is proprietary and only its technicians can tie into it, with no plan to compete that part. The MATOC was awarded 12/16/2025.
Not in the notice text
- Part of the solicitation (about 2,000 characters), most of the specifications, drawings and the scanned wage determination (RI20260001) were not read; check them on SAM.gov for requirements and the price evaluation
- Whether the site visit is mandatory is not stated
- The price proposal format and how price is evaluated were not in the text read
- Which firms are small under the NAICS code size standard is checked by the VA in the SBA database; the size standard itself is not given in the text
- Whether the work may be done remotely is not stated
More to check before you bid
- The notice names requirements: Not certified through VetCert yet? Apply on VetCert (SBA), or start with the SDVOSB guide.
- Limited competition: only the 17 holders of the VISN 1 Construction MATOC can bid, not every business that meets the set-aside.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 4, 2026
- Notice type
- Solicitation
- Office
- 241-Network Contract Office 01 (36C241), Togus, ME
- Product/service code
- Z2DA · Repair or Alteration of Hospitals and Infirmaries
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 236220)
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Open SDVOSB set-aside contracts
Terms on this notice: Solicitation, SDVOSB (service-disabled veteran-owned small business), Set-aside
Full notice text from SAM.gov
Similar open opportunities
- CON NRM 531-25-102 | Expand Emergency RoomSolicitation 36C26027R0002-0007 (Amendment 0007): the Department of Veterans Affairs wants a construction contractor to expand the Emergency Department at the Boise VA Medical…