Solicitation
Mod/Mode/US Bypass Canal Repairs
Department of the Interior
HUBZone set-aside · AZ
AI summary Beta
This summary may miss requirements: 2 of 14 attachments weren't read (Attachment_04_MMB_Drawings_Set_20260910_675c8.pdf, Attachment_07_Wage_Determination.pdf). Check the attachments on SAM.gov.
Bureau of Reclamation (Interior Department) wants a contractor to replace and repair concrete canal panels on the MOD, MODE and US Bypass drainage canals in Yuma, Arizona (solicitation 140RR027R0009). Only HUBZone-certified small businesses (the Historically Underutilized Business Zone program) can bid. It is one firm-fixed-price (one set price, whatever the work costs) contract, and the Government puts the construction magnitude between $500,000 and $1,000,000.
Who can bid (4)
- HUBZone small business: this is a 100% HUBZone set-aside, so only certified HUBZone small businesses can bid From Solicitation_No_140RR027R0009.docx
- Bid guarantee with the offer, and performance and payment bonds for construction over $150,000 From Solicitation_No_140RR027R0009.docx
- Lead Construction Superintendent with prior experience on at least two similar projects, who stays onsite; key personnel (project manager, onsite safety representative, superintendent) must be approved From Attachment_01_MMB_SOW_20260910_2197e.pdf
Show all 4Show fewer
- Small business size under NAICS 237990 (size standard $45M) and compliance with the limitations on subcontracting clause for set-asides
How to submit: Email to the contract specialist, Ebonie Foskey-Anderson, at ebonie_foskey-anderson@ios.doi.gov. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
From the version posted Nov 12, 2026.
- Serious: HUBZone set-aside: only HUBZone small businesses can bid. A firm without current HUBZone certification cannot compete for this work. From Solicitation_No_140RR027R0009.docx
- Serious: Bid guarantee and bonds required. You need a bid guarantee with your offer and performance and payment bonds after award, so confirm your surety can cover a job of this size. The bid guarantee amount wasn't in the text read here. From Solicitation_No_140RR027R0009.docx
- Serious: In-canal work limited to the canal outage. Most physical work must happen while the canals are drained, March 1 to March 18, 2027, with work in the canals finished by the end of March 17, 2027. Crews, materials and equipment must be onsite before the outage. From Attachment_01_MMB_SOW_20260910_2197e.pdf
Show all 10Show fewer
- Worth checking: The site visit was Nov 17, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From Solicitation_No_140RR027R0009.docx
- Worth checking: Performance period stated two ways. The Statement of Work gives 120 calendar days from award. The Standard Form 1442 line items show January 18, 2027 to March 17, 2027. Ask the contracting officer which governs. From Attachment_01_MMB_SOW_20260910_2197e.pdf
- Worth checking: Only two approved concrete suppliers. Concrete must come from a Reclamation-approved source, and only two suppliers in the Yuma area are listed, so confirm price and delivery with them before bidding. From Attachment_01_MMB_SOW_20260910_2197e.pdf
- Worth checking: Subcontractor experience needs a signed Letter of Commitment. If you rely on a subcontractor's past performance, the offer must include a letter signed by both parties. From Solicitation_No_140RR027R0009.docx
- Worth checking: Wage determination attached but not read. The solicitation includes the Construction Wage Rate Requirements (Davis-Bacon) clause, so set wages by the attached wage determination, which was not read here. Check it on SAM.gov before pricing.
- Minor: Technical proposal capped at 50 pages. Pages over the limit are not read or considered. From Solicitation_No_140RR027R0009.docx
- Minor: Quantities may change after field check. Extra quantities found when measuring on the first day of the outage need a price proposal and the contracting officer's written approval before you proceed. From Attachment_01_MMB_SOW_20260910_2197e.pdf
Read from the notice and 12 attachments. 2 of 14 not read. Show which files.
- Solicitation_No_140RR027R0009.docx (read)
- Sol_140RR027R0009.pdf (read)
- Attachment_03_MMB_Specifications_20260910_1425d.pdf (read)
- Attachment_01_MMB_SOW_20260910_2197e.pdf (read)
- Attachment_02_MMB_SOW_Appendix_1_20260910_db389.pdf (read)
- Attachment_08_-_DI-137_Release_of_Claims.pdf (read)
- Attachment_10_-_Performance_Bond_SF25-23a.pdf (read)
- Attachment_11_-_Bid_Bond_SF24-23a.pdf (read)
- Attachment_06_-_LC-035_HazMaterialAuthorization.pdf (read)
- Attachment_09_-_Payment_Bond_SF25A-23a.pdf (read)
- Attachment_12_-_Past_Performance_Questionnaire.pdf (read)
- Attachment_05_-_LC-045_Form_E_WasteDiversionTable.pdf (read)
- Attachment_04_MMB_Drawings_Set_20260910_675c8.pdf: not summarized: open it on SAM.gov
- Attachment_07_Wage_Determination.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Saw cut, remove and dispose of damaged canal panels (9,915 SF) and replace them with new 3 1/2 inch thick concrete panels (9,915 SF)
- Furnish, place and compact backfill (146 Ton) and fill erosion voids behind panels with controlled low-strength material (optional line, 10 CY)
- Install concrete groove joints (638 LF) and Type 2 expansion joints (1,681 LF), and seal cracks in existing lining (300 LF)
- Remove and dispose of debris and vegetation (10 Ton) and test the backfill and new concrete
- Provide traffic control, bonds and insurance, preparatory work (construction plan, safety program), and mobilization and demobilization
- Finish all in-canal work during the planned canal outage, which ends March 17, 2027
- Contract type
- Firm-fixed-price, negotiated Request for Proposal (RFP); one award; the Government anticipates award without discussions
- Period of performance
- Statement of Work: 120 calendar days from contract award. Standard Form 1442 line items show January 18, 2027 to March 17, 2027. Canal outage March 1 to March 18, 2027. No option years.
- Place of performance
- MOD, MODE and US Bypass canals, Yuma, Arizona
- Estimated value
- Magnitude of construction (Government's range): between $500,000 and $1,000,000
- How they'll choose
- Best value tradeoff: Factors 1 and 2 (Technical Plan for Construction, then Past Performance) combined are approximately equal to Factor 3, Price
- Offers due
- December 14, 2026, 12:00 PM Eastern
- How to submit
- Email to the contract specialist, Ebonie Foskey-Anderson, at ebonie_foskey-anderson@ios.doi.gov
- Page limits
- Technical proposal: 50 pages (pages over the limit are not read); 12-point type, one-inch margins, 8 1/2 x 11 inch paper
What they'll judge offers on
- Factor 1, Technical Plan for Construction: construction schedule (Gantt chart), narrative of construction sequence, staffing, equipment, quality control plan, demolition plan
- Factor 2, Past Performance: relevant projects completed in the last 5 years, similar in size, scope and complexity
- Factor 3, Price: total of Price Schedule Table 1, checked for reasonableness and unbalanced pricing
What to include when you submit
- Send three volumes: Volume I Business Proposal, Volume II Technical Proposal, Volume III Price Proposal. Put no price information in the other volumes.
- Volume I: a fully executed Standard Form 1442 (the construction solicitation, offer and award form) as the cover sheet, completed representations and certifications, and acknowledgment of all amendments. Alternate proposals are not permitted.
- Volume II: the Technical Plan for Construction with a construction schedule as a Gantt chart in Primavera P6 or MS Project, printable in color on 11x17 paper, using a Notice to Proceed date of February 22, 2027 for the schedule.
- Volume II narrative: for each work item say what is self-performed or subcontracted, labor and equipment, production rates, means and methods, and quality control testing. Include a staffing plan with key personnel and qualifications.
- Past performance: list the two most recent projects closest in scope, complexity and size from the last 5 years, with owner contact, contract amounts, percent self-performed, and problems and fixes. Give each reference a Past Performance Questionnaire to return to Reclamation.
- To have a subcontractor's past performance counted, include a Letter of Commitment signed by both parties.
- Volume III: price every line item in the Section B Price Schedule (Table 1) with unit prices, to the nearest whole dollar, plus a total price.
- Include a bid guarantee with the offer, and keep the proposal valid at least 60 calendar days from the response due date.
- Ask questions in writing only, to the contract specialist by December 1, 2026, 12:00 p.m. Arizona Time, with the solicitation number in the subject line.
After award, you must have
- Enroll in the Treasury Invoice Processing Platform (IPP) to send invoices, using the business contact listed in SAM.gov, once the contract is awarded
Not in the notice text
- Several documents were only partly read: the middle of the solicitation (including the bid guarantee clause), the specifications and the Statement of Work. The drawings (scanned) and the wage determination were attached but not read; check them on SAM.gov.
- The bid guarantee amount and the Davis-Bacon wage rates are not in the text read here.
- The required percentage of work the prime must self-perform under the limitations on subcontracting clause is not in the text read here.
- Whether the work may be done remotely: not stated (work is on canals in Yuma, Arizona).
- Whether any amendment changes dates or requirements: none appears in the text read.
More to check before you bid
- Not certified yet? Check whether your address is in a HUBZone. More open hubzone set-asides under NAICS 237990
- SAM.gov's text for this notice doesn't describe the work. The work is described in its attachments, listed under Notice details.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 12, 2026
- Notice type
- Solicitation
- Office
- Reclamation Contracting Activity, Denver, CO
- Product/service code
- Y1KB · Construction of Canals
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 237990)
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Open HUBZone set-aside contracts
Terms on this notice: Solicitation, HUBZone, Set-aside
Full notice text from SAM.gov
Similar open opportunities
- East Bulkhead Replacement, East Boat Basin, Cape Cod Canal, Sandwich MAThe U.S. Army Corps of Engineers, New England District plans an invitation for bids (IFB: a sealed bid for a fixed job) to replace the east steel sheet pile bulkhead at the East…