Solicitation
WWYK260004 - Repair Structural Integrity, B1134, Post 34 & North Wall
Department of Defense · Department of the Air Force
Small business set-aside · Tinker AFB, OK
A newer version of this notice was posted Nov 18, 2026. It moves the due date from Nov 23, 2026 to Dec 15, 2026, which is the date shown on this page. See the latest version.
AI summary Beta
Summary of another version of this notice: check what changed on SAM.gov. This summary may miss requirements: 23 of 35 attachments weren't read (32 13 14.pdf, 10 14 00.10.pdf and 21 more). Check the attachments on SAM.gov.
Only Tinker AFB MAC BOA holders (businesses with a standing ordering agreement for construction work there) can bid on solicitation FA813727R0001, and a bidder had to attend the October 22, 2026 (passed) initial site visit. The Air Force (DEPT OF DEFENSE / DEPT OF THE AIR FORCE / FA8137 AFSC PZIOC) wants repairs to the failing base of Post 34 and the shear braces on the north wall of Building 1134 at Tinker AFB, Oklahoma. The work is a small business set-aside, firm-fixed-price (FFP: one set price, whatever the work ends up costing), with 195 calendar days to finish, and the response due date is December 15, 2026, 12:00 PM Eastern.
Who can bid
- Total small business set-aside: only small businesses can bid (size standard USD 19,000,000.00 annual receipts) From SAM.gov's set-aside field
- Must already hold a Tinker AFB MAC BOA; only prime BOA holders may respond, and subcontractors go through a prime From Solicitation - FA813727R0001.pdf
- Must have attended the initial site visit (October 22, 2026, 10 AM CT, Building 1134) to be eligible to propose
How to submit: Email to Melanie.ivie@us.af.mil and Tamra.torres@us.af.mil, per the RFI answers. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (8)
From the version posted Nov 18, 2026.
- Serious: Only Tinker AFB MAC BOA holders can bid. Businesses without this standing ordering agreement cannot send an offer; others could only take part as a subcontractor to a holder.
- Serious: Registration closed Oct 20, 2026. If registering was required to take part, ask the contracting officer whether late registration is allowed.
- Worth checking: Design responsibility is unclear. Section M asks for sole source responsibility for design and construction, but the RFI answer says only the design noted in the documents applies (delegated items for shoring, wood modifications, shop drawings). From Solicitation - FA813727R0001.pdf
Show all 8Show fewer
- Worth checking: Drawings are only 35% design. Bidders must price from 35% design documents as the complete scope, and some quantities are given only by pointing to drawing keynotes. From RFI QA RESPONSES - WWYK260004 - REPAIR STRUCTURAL INTEGRITY B1134 POST 34 NORTH WALL_COR.pdf
- Worth checking: Performance and payment bonds may be required. Item 12b shows 10 calendar days after award for bonds; the yes or no box in item 12a couldn't be read, so check the form on SAM.gov. From Solicitation - FA813727R0001.pdf
- Worth checking: Funds not yet available. The Government's obligation depends on funds being made available, and it may decide not to award at all. From Solicitation - FA813727R0001.pdf
- Worth checking: Stormwater plan required for excavations. New footings need excavation through the existing slab, and an approved stormwater pollution prevention plan (SWPPP) is needed before the excavation permit request. From RFI QA RESPONSES - WWYK260004 - REPAIR STRUCTURAL INTEGRITY B1134 POST 34 NORTH WALL_COR.pdf
- Minor: Base access for workers. Workers need base identification and vehicle passes, requested by letter through the contracting officer. From Solicitation - FA813727R0001.pdf
Read from the notice and 12 attachments. 23 of 35 not read. Show which files.
- RFI QA RESPONSES - WWYK260004 - REPAIR STRUCTURAL INTEGRITY B1134 POST 34 NORTH WALL_COR.pdf (read)
- Solicitation - FA813727R0001.pdf (read)
- 09 90 00.pdf (read)
- 07 41 13.pdf (read)
- 06 10 00.pdf (read)
- 07 42 13.pdf (read)
- 10 44 16.pdf (read)
- 31 23 15.pdf (read)
- 31 00 00.pdf (read)
- 32 01 14.pdf (read)
- 32 01 16.pdf (read)
- 32 01 17.pdf (read)
- 32 13 14.pdf: not summarized: open it on SAM.gov
- 10 14 00.10.pdf: not summarized: open it on SAM.gov
- 03 30 00.pdf: not summarized: open it on SAM.gov
- 02 41 00.pdf: not summarized: open it on SAM.gov
- 01 78 00.pdf: not summarized: open it on SAM.gov
- 00 72 00.pdf: not summarized: open it on SAM.gov
- 01 33 00.pdf: not summarized: open it on SAM.gov
- 01 50 00.pdf: not summarized: open it on SAM.gov
- 01 33 16.00 10.pdf: not summarized: open it on SAM.gov
- 00 71 00.pdf: not summarized: open it on SAM.gov
- 00 70 00.pdf: not summarized: open it on SAM.gov
- 01 78 23.pdf: not summarized: open it on SAM.gov
- 01 45 00.00 10.pdf: not summarized: open it on SAM.gov
- 000_TABLE OF CONTENTS.pdf: not summarized: open it on SAM.gov
- 00 80 05.pdf: not summarized: open it on SAM.gov
- 01 32 16.00 20.pdf: not summarized: open it on SAM.gov
- 01 42 00.pdf: not summarized: open it on SAM.gov
- 00 80 00.pdf: not summarized: open it on SAM.gov
- COPY of Site Visit Sign-in Sheet_10.22.2026.pdf: not summarized: open it on SAM.gov
- Att.8_260004_MACB_SOW.pdf: not summarized: open it on SAM.gov
- Att.9_260004_Submittal Register.pdf: not summarized: open it on SAM.gov
- Att.10_260004_Drawings.pdf: not summarized: open it on SAM.gov
- Wage Determinations.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Repair or replace the eroded base of Post 34 and the eroded shear braces on the north wall of Building 1134
- Replace posts and footings at the north end wall and open east side; the RFI answer points to drawing S-101, keynote 1, for quantity and locations
- Repair or replace damaged truss bottom chords and decayed wood along the north wall; the RFI answer says only one location was observed
- Install new metal wall panels (24 ga minimum) and a vented opening at the base of the north wall, 1 foot maximum height by four bays
- Remove asphalt topping two feet from the north wall and grind the north face pavement to give positive drainage
- Provide five fire extinguishers mounted on posts at 75 feet on center (signage is not in scope)
- Submit shop drawings for concrete and wood work, plus delegated design for shoring and wood modifications
- Prepare a stormwater pollution prevention plan (SWPPP) for the excavations; the RFI answer says one is required
- Contract type
- Firm-fixed-price, one project line item (order under a basic ordering agreement)
- Period of performance
- 195 calendar days from receipt of notice to proceed; the form also shows 10 calendar days to begin performance
- Place of performance
- Tinker AFB, OK, USA
- Estimated value
- Government's magnitude of construction: $100,000 - $250,000
- Contract vehicle
- Tinker AFB MAC BOA (basic ordering agreement) holders only
- How they'll choose
- Lowest priced technically acceptable (LPTA): lowest evaluated price among offers rated acceptable on every technical subfactor. Price is checked for reasonableness, balance and realism.
- Offers due
- December 15, 2026, 12:00 PM Eastern (the notice text says 12PM CST)
- How to submit
- Email to Melanie.ivie@us.af.mil and Tamra.torres@us.af.mil, per the RFI answers
What they'll judge offers on
- Factor 1 Technical (rated acceptable or unacceptable): (a) Capability and Management, (b) Schedule and Planning
- Price: reasonableness, balanced pricing, realism
What to include when you submit
- Send the proposal by email to both contracting contacts named in the RFI answers, even though the SF 1442 form mentions sealed copies
- Price the work from the 35% design documents as the complete scope, per RFI 002
- Include a technical proposal covering Capability and Management and Schedule and Planning, with a construction schedule that meets the mandatory completion date
- Price every contract line item (CLIN: one priced line of the order) except any marked not separately priced
- Clearly state any exception to the solicitation terms, with supporting reasons
Not in the notice text
- Much of the solicitation is attached but not read: the statement of work (Att.8_260004_MACB_SOW.pdf), drawings (Att.10_260004_Drawings.pdf), submittal register, wage determinations, site visit sign-in sheet and many specification sections. Section L (instructions to bidders) was only partly read.
- Which wage rule applies (a Davis-Bacon wage determination, the pay rates required on federal construction) is likely in Wage Determinations.pdf, attached but not read.
- Whether performance and payment bonds are required (the yes or no box in item 12a couldn't be read) and whether an offer guarantee is required.
- Exact quantities of posts, footings and truss repairs: the RFI answers point to drawing keynotes that were not read.
- Page limits and the full list of what the proposal must contain.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 18, 2026
- Notice type
- Solicitation
- Office
- FA8137 AFSC PZIOC, Tinker AFB, OK
- Product/service code
- Z2GD · Repair or Alteration of Open Storage Facilities
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 238190)
- Versions
6 versions have been posted, newest first.
- Nov 18, 2026 · Amendment 0005Due Dec 15, 2026 (changed)
- Nov 18, 2026 · Amendment 0004 (this version)Due Nov 23, 2026 (changed)
- Nov 18, 2026 · Amendment 0003Due Nov 19, 2026
- Nov 16, 2026 · Amendment 0002Due Nov 19, 2026 (changed)
- Nov 9, 2026 · Amendment 0001Due Nov 16, 2026
- Oct 16, 2026 · SolicitationDue Nov 16, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Set-aside contracts explained
Terms on this notice: Solicitation, Set-aside
Full notice text from SAM.gov
Similar open opportunities
- Repair Taxiway Alpha & Bravo - North Auxiliary AirfieldThe Department of the Air Force (628 CONS PK, for Joint Base Lindsey Graham) wants a small business to repair Taxiways Alpha and Bravo at North Auxiliary Airfield in North, South…
- Design-Build Maintenance and Repair Army Reserve (MRAR) of Equipment Concentration Site (ECS), B-56767, at North Fort Hood, TXPhase II (invited firms only) of solicitation W912QR25RA013: the Army Corps of Engineers Louisville District seeks a design-build contractor to repair and add to the roughly…
- 550-26-121 FY27 NRM Emergent Repairs North Water Tower 71 & South Water Tower 94 CONPresolicitation 36C25227B0008: the Department of Veterans Affairs (Network Contract Office 12) plans an SDVOSB-only construction job to repair and paint two water towers (North…