Solicitation
WFE Solenoid/Corrector Magnet Spares
Department of Energy
A newer version of this notice was posted Nov 17, 2026. See the latest version.
AI summary Beta
Summary of another version of this notice: check what changed on SAM.gov. This summary may miss requirements: 2 of 5 attachments weren't read (F00484505---DWG1.pdf, F10009710_-_PDF_1.pdf). Check the attachments on SAM.gov.
Fermi Forward Discovery Group, which runs Fermi National Accelerator Laboratory (Fermilab, a Department of Energy lab) in Batavia, IL, wants firm-fixed-price proposals to design and build 2 solenoid magnet packages with built-in dipole steering coils for its proton source. Proposals are due January 5, 2027, 5:00 PM Central, and the award is a best-value trade-off.
Who can bid
- Be able to complete the factory acceptance tests, including general inspection and magnetic measurement, at the subcontractor's facility; Amendment 01 allows a lower-tier manufacturer's facilities if clearly identified From WFE Solenoid SOW 389116swk.pdf
- Past experience with similar fabrication and quality control (3 contracts in the past 5 years) From WFE Solenoid SOW 389116swk.pdf
- Complete and return the SARC (annual representations and certifications) and PROC-FRM-466 proposal certifications with the proposal From RFP 389116swk Rev 1.pdf
How to submit: Not clearly stated. The notice says the RFP outlines how to submit; the procurement contact is Spencer Keske, skeske@fnal.gov, 630-840-3323.. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (4)
From the version posted Nov 17, 2026.
- Worth checking: Questions due November 30, 2026. Questions about the RFP are due 5pm Central, November 30, 2026, to the procurement contact. From RFP 389116swk Rev 1.pdf
- Worth checking: Two design drawings attached but not read. The reference solenoid drawing and the mounting plate drawing are scanned and could not be read, so mechanical details are unchecked. From WFE Solenoid SOW 389116swk.pdf
- Worth checking: Subcontractor must do detailed design and magnetic testing. The offeror performs the final magnet design for approval and needs magnetic measurement capability, which small shops may lack. From WFE Solenoid SOW 389116swk.pdf
Show all 4Show fewer
- Minor: Failed magnets rejected at your expense. Magnets that fail site acceptance tests are returned to the subcontractor for repair at the subcontractor's expense. From WFE Solenoid SOW 389116swk.pdf
Read from the notice and 3 attachments. 2 of 5 not read. Show which files.
- WFE Solenoid SOW 389116swk.pdf (read)
- RFP 389116swk Amendment 01.pdf (read)
- RFP 389116swk Rev 1.pdf (read)
- F00484505---DWG1.pdf: not summarized: open it on SAM.gov
- F10009710_-_PDF_1.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Design and build 2 solenoid magnets, each with integrated dipole corrector coils (qty 2 in the statement of work, listed as "2 unit(s)" in the RFP)
- Do the final detailed design for Fermilab approval before fabrication; the reference design from Fermilab may be used
- Deliver design reports, drawings, material certifications, a quality control (QC) fabrication and inspection plan and reports, and magnetic measurement test plans and reports
- Run factory acceptance tests (FATs) on 100% of magnets, including general inspection and magnetic measurement, with Fermilab allowed to witness them
- Deliver both magnets in one batch to Fermilab Receiving Warehouse 2, FOB Fermilab (freight included), for site acceptance tests
- Send monthly written status reports and give 20 days' written notice before factory tests begin
- Preliminary schedule: delivery of production units 36 weeks after receipt of order, with contract closeout at 40 weeks
- Contract type
- Firm-fixed-price (FFP: one set price, whatever the work ends up costing) subcontract; FFDG General Terms and Conditions for Commercial Products and Commercial Services (10.2026)
- Period of performance
- Preliminary schedule in the statement of work: 40 weeks after receipt of order, including delivery at 36 weeks
- Place of performance
- Delivery to Fermilab Receiving Warehouse 2, Kirk Rd & Wilson Street, Batavia, IL 60510. The work is done at the subcontractor's facility.
- Estimated value
- Not stated
- How they'll choose
- Best value trade-off. Fermilab may accept other than the lowest price, deems the offeror responsible, and intends to award without discussions.
- Offers due
- January 5, 2027, 5:00 PM Central
- How to submit
- Not clearly stated. The notice says the RFP outlines how to submit; the procurement contact is Spencer Keske, skeske@fnal.gov, 630-840-3323.
What they'll judge offers on
- Technical Proposal as per Specification/SOW Document (preliminary design, fabrication experience, infrastructure, schedule)
- Price
- Infrastructure Capabilities: in-house manufacturing and fabrication, magnetic testing, quality assurance program and equipment
- Schedule: Gantt chart (or similar) with all activities, milestones and delivery deadlines
- Past Experience: similar fabrication and quality control work
What to include when you submit
- Return a completed RFP page with unit price and delivery for the item
- Return the Subcontractor Annual Reps & Certs form (SARC, Rev. 8) if not completed in the last year
- Return the PROC-FRM-466 Proposal Certifications form
- Include F.O.B. Fermilab delivery terms, with all freight charges in the quoted price
- Clearly indicate any exceptions to specifications and extra charges for containers, tooling and similar items
- Fabrication experience: list 3 contracts completed in the past 5 years, of about the same dollar size and as similar as possible, each with contract title, date of award, amount, client name and address, client contact and a description of deliverables with photos if shareable
- Infrastructure: describe planned manufacturing and fabrication equipment, magnetic testing infrastructure, the general quality assurance program with certifications, and the QC program and equipment
- Preliminary design: show the preliminary magnetic and mechanical design, core, coil winding and epoxy impregnation procedures and tooling, simulations, and cooling calculations
- Schedule: include a computer-generated Gantt chart (or similar) of all activities and deliverables
- Say exactly which parts of the work are in-house and which go to lower-tier manufacturers, especially quality control (Amendment 01)
- Acknowledge Amendment 01 by completing the SARC and PROC-FRM-466, or by email
Not in the notice text
- Two drawings are attached but not read: F00484505---DWG1.pdf and F10009710_-_PDF_1.pdf are scanned PDFs with no text. They are the reference solenoid and mounting plate drawings.
- The set-aside is not stated on SAM.gov or in the documents read.
- The notice does not say how to send the proposal (email or portal); contact Spencer Keske at skeske@fnal.gov.
- The FFDG General Terms and Conditions (10.2026) are on the Fermilab procurement website and were not read.
- The statement of work says magnetic measurements may not be required for some units; the conditions are in the full statement of work.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 17, 2026
- Notice type
- Solicitation
- Office
- Fermilab - DOE Contractor, Batavia, IL
- Product/service code
- 5945 · Relays and Solenoids
- Business type
- Manufactured parts & equipment (FedReady's grouping, from NAICS 332999)
- Versions
3 versions have been posted, newest first.
- Nov 17, 2026 · Amendment 0002Due Jan 5, 2027
- Nov 17, 2026 · Amendment 0001 (this version)Due Jan 5, 2027 (changed)
- Nov 5, 2026 · SolicitationDue Dec 9, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- Advanced Light Source Upgrade (ALS-U) STORAGE RING (SR) BENDB AND BENDC MAGNETSThe University of California, for the Department of Energy's Lawrence Berkeley National Laboratory (LBNL), wants five BENDB and five BENDC bending magnets built to LBNL's…
- Electron Storage Ring D2 Dipole MagnetsRequest for proposal 462499 from Brookhaven Science Associates, LLC (BSA), which runs Brookhaven National Laboratory for the Department of Energy, for the design and production…
- Hose Assembly, NonmetalThe Defense Logistics Agency (DLA) office DLA WEAPONS SUPPORT wants quotes on national stock number (NSN: the federal catalog number for a part) 4720011296081, HOSE…
- Hose, NonmetallicDefense Logistics Agency (DLA) Weapons Support is asking for quotes on solicitation SPE7M227U0016: nonmetallic hose, national stock number (NSN, the government's item ID)…
- Hood, Engine CompartmenDefense Logistics Agency (DLA) Weapons Support wants quotes on NSN 2510016926731 HOOD,ENGINE COMPARTMEN under solicitation SPE7L327T2929: line 0001 QTY 15 EA. It is a combined…