NASA Glenn Research Center plans several multiple-award indefinite delivery, indefinite quantity (IDIQ: a contract that sets a ceiling and orders work later through task orders) contracts for space nuclear power systems, mainly the Lunar Reactor 1 (LR-1) fission reactor for the Moon. It is full and open competition with no set-aside, and every bidder must also propose on the first LR-1 Phase 1 task order, which goes to no more than four companies. The response due date is December 21, 2026, 5:00 PM Eastern; the maximum across all awards is $350,000,000, with ordering from April 15, 2027 to December 31, 2031.
Who can bid (5)
- Draft Organizational Conflict of Interest (OCI) Plan with the proposal, covering conflicts tied to the LR-1 Phase 1 task order if the bidder intends to compete for it From SPARC RFP Cover Letter.pdf
- Bidders that are not small businesses must submit a Small Business Subcontracting Plan From Att J.2-03 - SPARC Small Business Participation.pdf
- Only U.S. citizens, protected individuals or lawful permanent residents can share proposal files with NASA through the Box process From Att J.2-01 - Instructions for Setting up a Box Account.pdf
Show all 5Show fewer
- Comply with U.S. export control laws (EAR and ITAR); everyone working on export-controlled goods or services must be eligible under them From Att J.1-01 - SPARC SOW.pdf
- Relevant experience and past performance, rated as a level of confidence From SPARC Final RFP- 80GRC027R0005.pdf
How to submit: NASA's Enterprise File Sharing and Sync Box (EFSS Box); set up a Box account and email the Contracting Officer first. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
From the version posted Nov 20, 2026.
- Serious: Every bidder must also propose on the Phase 1 task order. A proposal for the IDIQ is only evaluated if it also covers the first LR-1 task order, so a small business must price and plan a full hardware demonstration. From SPARC Final RFP- 80GRC027R0005.pdf
- Serious: Large, technically demanding nuclear space work. The task order calls for a 20 kWe fission power system design, a test unit and radiation testing, with a maximum of $350,000,000 across all awards, which favors well-resourced teams. From SPARC Final RFP- 80GRC027R0005.pdf
- Worth checking: Only up to four companies get the Phase 1 task order. Holding an IDIQ contract does not guarantee work; the first task order goes to a small group, and only SPARC awardees can win it. From SPARC Final RFP- 80GRC027R0005.pdf
Show all 10Show fewer
- Worth checking: Box account setup needed before submitting. Proposals go through NASA's Box system, which requires emailing the Contracting Officer, accepting a shared folder and setting up two-factor sign-in before upload. From Att J.2-01 - Instructions for Setting up a Box Account.pdf
- Worth checking: Government Task Agreement requests close before the response due date. A bidder that wants to use NASA facilities must start the request in writing early, or it will not be considered. From Att J.2-11 - GTA Instructions.pdf
- Worth checking: Cost-type accounting system readiness is evaluated. NASA checks whether a bidder's accounting system can handle cost-reimbursement task orders, and a bidder without an approved system may be limited to fixed-price orders. From SPARC Final RFP- 80GRC027R0005.pdf
- Worth checking: Past performance questionnaires go straight to NASA. References must send their questionnaires to the Contracting Officer before the response due date, so a bidder depends on others to finish its past performance file. From SPARC RFP Cover Letter.pdf
- Worth checking: Export control rules apply. Everyone working on export-controlled items must be eligible under the Export Administration Regulations and International Traffic in Arms Regulations (ITAR). From Att J.1-01 - SPARC SOW.pdf
- Minor: Subcontracting plan required for larger bidders. A bidder that is not a small business must file a small business subcontracting plan with goals and records; small businesses are exempt but may still need commitment documents. From Att J.2-03 - SPARC Small Business Participation.pdf
- Minor: Questions due December 4, 2026. Written questions must go to the Contracting Officer by email on or before this date. From SPARC RFP Cover Letter.pdf
Read from the notice and 12 attachments. 6 of 18 not read. Show which files.
- SPARC RFP Cover Letter.pdf (read)
- SPARC Final RFP- 80GRC027R0005.pdf (read)
- Att J.1-01 - SPARC SOW.pdf (read)
- Att J.2-05 - LR-1 Phase 1 ASTO SOW.pdf (read)
- SPARC Technical Reference Materials.pdf (read)
- Att J.2-01 - Instructions for Setting up a Box Account.pdf (read)
- Att J.2-02 - SPARC OCI Plan - Instructions.pdf (read)
- Att J.2-11 - GTA Instructions.pdf (read)
- Att J.1-02 - SPARC Sec Reqs for Unclassified IT Resources.pdf (read)
- Att J.2-03 - SPARC Small Business Participation.pdf (read)
- Att J.2-04 - LR-1 Phase 1 ASTO Model TO.pdf (read)
- Att J.2-06 - LR-1 Phase 1 ASTO DPD.pdf (read)
- Att J.1-06 - NF533M Template.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- Att J.1-07 - NF533Q Template.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- Att J.2-10 Price Volume Template.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- Att J.2-09 - PPQ Instructions and Template.pdf: not summarized: open it on SAM.gov
- Att J.1-05 - Government Task Agreement (GTA) Form.pdf: not summarized: open it on SAM.gov
- Att J.2-07 - PreAward Survey of Prospective Contractor Accounting System.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Win a place on the IDIQ for design, development, analysis, fabrication, assembly, test, evaluation, delivery and operation of space nuclear systems, hardware, materials and software
- LR-1 Phase 1 task order: a preliminary design review (PDR)-level design of LR-1, a 20 kWe fission power system with closed-Brayton power conversion
- Build and run an engineering test unit (ETU): an electrically heated, integrated system test in a relevant environment
- Run component-level radiation exposure testing for both reactor-induced and lunar-surface radiation
- Deliver ETU hardware and software: reactor simulator, heat transport assembly, Brayton power conversion units, heat rejection system, power management equipment, data acquisition and control software
- Run the contract: cost reporting, organizational conflict of interest controls, IT security, small business subcontracting, safety and mission assurance, systems engineering, configuration and risk management
- Support task order meetings: kickoff, system requirements review, project management reviews, weekly virtual status meetings, and the PDR at NASA Glenn in month 17
- Deliver the data items listed in the task order's contract data requirements list
- Contract type
- Multiple-award IDIQ that can issue firm-fixed-price (FFP: one set price), fixed-price incentive, cost-plus-fixed-fee and cost-plus-incentive-fee task orders; the LR-1 Phase 1 task order is FFP
- Period of performance
- IDIQ ordering period April 15, 2027 to December 31, 2031 (estimated, subject to the award date); LR-1 Phase 1 task order estimated April 15, 2027 to October 14, 2028, to be completed within 18 months of award
- Place of performance
- Cleveland, OH, USA per SAM.gov; the cover letter says the contract will primarily be performed offsite at the Contractor's facilities
- Estimated value
- Maximum ordering amount of $350,000,000.00 across the contracts; minimum guarantee of $30,000.00 per contract
- How they'll choose
- Mission Suitability is more important than Relevant Experience and Past Performance, which is more important than Price (task order level). Price is evaluated only for the Phase 1 task order. NASA intends to award SPARC contracts to each and all qualifying offerors.
- Offers due
- December 21, 2026, 5:00 PM ET
- How to submit
- NASA's Enterprise File Sharing and Sync Box (EFSS Box); set up a Box account and email the Contracting Officer first
What they'll judge offers on
- Mission Suitability: subfactors MS1, MS2 (SPARC Small Business Participation) and MS3 (the only subfactor used to choose the task order awardees)
- Relevant Experience and Past Performance: rated as a level of confidence from Very High to Very Low, or Neutral, not numerically scored
- Price: task order only; compared with other prices and the Government's cost estimate, lower Total Government Cost viewed more favorably
What to include when you submit
- Set up a Box account, email the Contracting Officer the account address, accept the shared folder invitation and two-factor setup, then upload proposal files one by one; whole folders cannot be uploaded
- Volumes named in the documents: Volume I Mission Suitability, Volume IA Mission Suitability Appendix, Volume II Relevant Experience and Past Performance, Volume III Price (with the Price BOE Narrative), Volume IV Business
- Use the Excel Price Volume Template (Attachment J.2-10) for price
- Every bidder must submit a proposal addressing the first task order (the Awardable Sample Task Order, ASTO); a bidder that answers No to the K.2 representation does not need to return the model task order
- Bidders that answer otherwise fill in all offeror fill-ins in the Model Task Order (Attachment J.2-4), sign its cover page and return it in Volume IV
- Include a draft Organizational Conflict of Interest (OCI) Plan with the proposal; the final plan is due within 30 days after authority to proceed
- All bidders: documentation of any enforceable commitments to use small businesses (mentor-protege agreement, letters of commitment) in Volume IA
- Bidders that are not small: small business development information and a Small Business Subcontracting Plan with the proposal
- Submit all Government Task Agreements (GTAs: agreements to use NASA or other Government facilities) with the proposal, completing only Sections I and II of the GTA form, with the GTA letter of intent as an appendix to the Price BOE Narrative
- If proposing performance-based payments, include the PBP Summary Table and BOE Narrative
- Ask references to send their Past Performance Questionnaires directly to the Contracting Officer before the response due date
After award, you must have
- Contractor systems holding NASA non-public information must meet NIST SP 800-171 data protections, shown by a third-party audit or a certification such as CMMC Level 2, before NASA information is transferred From Att J.1-02 - SPARC Sec Reqs for Unclassified IT Resources.pdf:
…must meet the requirements for data protections detailed in NIST Special…
Current contractor
No incumbent is named. NASA intends to award SPARC contracts to each and all qualifying bidders, and the Phase 1 task order to no more than four companies.
Not in the notice text
- Most of the final RFP's Sections K, L and part of M were cut from the text read (28,218 of 257,945 characters included), so page limits, proposal formats and the Mission Suitability subfactor criteria could not be read; check the RFP on SAM.gov
- Attached but not read: Att J.2-09 PPQ Instructions and Template, Att J.1-05 Government Task Agreement (GTA) Form, Att J.2-07 PreAward Survey of Prospective Contractor Accounting System, and the Excel files Att J.1-06, Att J.1-07 and Att J.2-10 Price Volume Template
- The middle parts of the SOW, the Phase 1 SOW, the model task order, the small business attachment and the data procurement document were also cut, so some requirements may be missing here
- Page limits for each volume are not in the text read
- Whether facility clearances, nuclear material licenses or other approvals are needed is not stated in the text read
- The Government's cost estimate for the Phase 1 task order is not given
Notice details
Notice type, codes, versions and files
- Posted
- Nov 20, 2026
- Notice type
- Solicitation
- Office
- NASA Glenn Research Center, Cleveland, OH
- Product/service code
- AR15 · Space R&D SVCS; Space Flight, Research & Supporting Activities; R&D Facilities & Maj Equip
- Business type
- Engineering, architecture & research (FedReady's grouping, from NAICS 541715)
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- Government Requirement for Advanced Power and Energy (GRAPE)The Air Force Research Laboratory (AFRL) Energy Office in Ohio runs an open, ongoing call for white papers (short idea papers) on new energy and power technologies for the Air…
- Hydrosphere, Biosphere, & Geophysics (HBG) Support Services II - Final Request for Proposal (FRFP)NASA Goddard Space Flight Center wants science research support for its Earth Sciences Division laboratories in Greenbelt, Maryland, under a five-year ordering period.
- Defense Experimentation Using the Commercial Space InternetThe Air Force Research Laboratory (Wright-Patterson AFB, Ohio) runs a long-running research program called Defense Experimentation Using Commercial Space Internet (DEUCSI).
- Space Technology Advanced Research (STAR)The Air Force Research Laboratory's Space Vehicles Directorate (Kirtland AFB, NM) runs an open-ended Advanced Research Announcement called STAR. It asks companies to send short…
- Pioneering Aerospace Capabilities, Engineering and ResearchFA2391-23-S-2403 is the Air Force Research Laboratory's open research announcement (a broad agency announcement, or BAA) called PACER, for aerospace research and development.