Solicitation
Administrative Parking Lot Repairs
Department of Agriculture · Forest Service
Small business set-aside · CO
A newer version of this notice was posted Nov 23, 2026. It moves the due date from Dec 1, 2026 to Dec 18, 2026, which is the date shown on this page. See the latest version.
AI summary Beta
Summary of the version posted Nov 17, 2026. The notice was amended Nov 23, 2026. The due date moved from Dec 1, 2026 to Dec 18, 2026. Check what else changed on SAM.gov. This summary may miss requirements: 3 of 9 attachments weren't read (Attachment 1 - C05 Schedule of Items.xlsx, Attachment 3 - C05 Site Maps.pdf and 1 more). Check the attachments on SAM.gov.
The U.S. Forest Service (USDA-FS, Intermountain Region contracting office) wants a contractor to repair and resurface three administrative parking lots in Colorado: crack sealing, pavement patching, seal coating and re-striping. This is a total small business set-aside under a firm-fixed-price (FFP: one set price) contract, with one award planned. The response due date is December 1, 2026, 2:00 PM Eastern (Amendment 0001; was November 23, 2026 (passed)).
Who can bid
- Small business set-aside: only small businesses can bid. Size standard is $45 million under NAICS 237310.
- Active registration in the System for Award Management (SAM.gov) From C05 1240LT27Q0019.pdf
How to submit: Email to Contract Specialist Jordan Carlsen at Jordan.Carlsen@usda.gov, due December 1, 2026, 2:00 PM Eastern (Amendment 0001; the earlier date was November 23, 2026, 2:00 PM Eastern). What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (8)
- Serious: Total small business set-aside. Only small businesses (size standard $45 million) can bid; larger firms cannot.
- Serious: Payment bond or letter of credit required. A payment bond or irrevocable letter of credit for 100% of the contract price is due within 10 days of award; the bond must be on SF 25A. From C05 1240LT27Q0019.pdf
- Worth checking: Response due date moved by Amendment 0001. The response due date is now December 1, 2026, 2:00 PM Eastern; the original solicitation form still shows November 23, 2026. Use the later date.
Show all 8Show fewer
- Worth checking: Wage determination attachment not read. Davis-Bacon construction wage rates apply, and the wage determination is a scanned file that was not read; check the posted wage determination for pay rates. From C05 1240LT27Q0019.pdf
- Worth checking: Work must be phased around occupied offices. Offices need parking open during work, so a hybrid or phased closure is required, and each site must be done within one week. From C06_Questions and Clarifications R.docx
- Minor: The site visit was Nov 3, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From C05 1240LT27Q0019.pdf
- Minor: Page limit mentioned two ways. The solicitation text mentions a 10-page criterion, but the answers say the limit is 3 pages for the technical approach. From C06_Questions and Clarifications R.docx
- Minor: Weekly progress reports required. Written progress reports are due each week for the whole project. From Attachment 4 - C05 Statement of Work.pdf
Read from the notice and 6 attachments. 3 of 9 not read. Show which files.
- 1240LT27Q0019.pdf (read)
- C05 1240LT27Q0019.pdf (read)
- Attachment 5 C06 416 Specifications Administrative parking lot repairs.pdf (read)
- Attachment 4 - C05 Statement of Work.pdf (read)
- C06_Questions and Clarifications R.docx (read)
- Attachment 2 - C05 FSSS.pdf (read)
- Attachment 1 - C05 Schedule of Items.xlsx: not read (the AI doesn't read this file type yet): open it on SAM.gov
- Attachment 3 - C05 Site Maps.pdf: not summarized: open it on SAM.gov
- Attachment 6 C06 Wage Determination C0202600002.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Clean all surfaces and fill cracks at three parking lots: Boulder, Clear Creek (Idaho Springs) and Fort Collins
- Remove and replace damaged pavement areas
- Seal coat the entire surface after repairs, to specification section 416 (slow setting asphalt emulsion, minimum 1.0 pound residue per square yard)
- Re-stripe the lots after seal coating
- Phase the work so offices keep some parking open; finish each site within one week
- Send written progress reports every week and submittals for all asphalt products
- Contract type
- Firm-fixed-price (FFP) contract; one award intended; commercial construction request for quotation (RFQ)
- Period of performance
- Period of performance June 15, 2027 to August 15, 2027; start work within 10 calendar days after notice to proceed and finish no later than August 15, 2027
- Place of performance
- Colorado: Boulder Ranger District Office (Boulder), Clear Creek Ranger District Office (Idaho Springs) and Fort Collins Administrative Site, on the Arapaho and Roosevelt National Forest and Pawnee National Grassland
- Estimated value
- Project magnitude between $25,000 and $100,000 (as stated in the solicitation)
- How they'll choose
- Best value to the Government, with no formal trade-off procedures; the price must also be fair and reasonable
- Offers due
- December 1, 2026, 2:00 PM Eastern (Amendment 0001; the earlier date was November 23, 2026, 2:00 PM Eastern) (from the version posted Nov 17, 2026; amended since)
- How to submit
- Email to Contract Specialist Jordan Carlsen at Jordan.Carlsen@usda.gov
- Page limits
- Quote: no more than 3 pages, not including the Schedule of Items; technical approach narrative 1 to 3 pages (Times New Roman 12). The answers say the limit is 3 pages, not 10.
What they'll judge offers on
- Technical Approach: 1 to 3 page narrative with an execution plan covering key tasks and milestones, plus a construction schedule (such as a Gantt chart); rated High, Some, Low or Neutral Confidence
- Price: all items priced on the Schedule of Items Excel spreadsheet, rounded up to whole dollars
What to include when you submit
- Send Technical Approach documentation: a detailed narrative with an execution plan for the work, addressing key tasks and milestones and showing a thorough understanding of the project
- Include a construction schedule (such as a Gantt chart) showing key tasks within the period of performance
- Price every item on Attachment 1, the Schedule of Items Excel spreadsheet; do not send pricing as a PDF
- Round each line-item price up to the nearest whole dollar, with no cents, and make the total match the line items
- Put the company name and Unique Entity ID (UEI) at the top of the Schedule of Items, in the yellow vendor block
- Acknowledge all amendments in Block 19 of the Standard Form 1442 (SF 1442, the construction solicitation and offer form); missing this gets the offer rejected
- Price all items: to be responsive, contractors must submit pricing for all items
- Hold prices firm for 60 calendar days after the date offers are due
After award, you must have
- Payment protection of 100% of the contract price (payment bond or irrevocable letter of credit), submitted within 10 days of award on SF 25A for a bond From C05 1240LT27Q0019.pdf:
(c) The submission of the payment protection is required within 10 days of contract award.
Current contractor
No incumbent is named. The notice does not give a count of responses or the number of awards beyond one.
Not in the notice text
- Attached but not read: Attachment 1 Schedule of Items.xlsx (line items and quantities), Attachment 3 Site Maps.pdf and Attachment 6 Wage Determination C0202600002.pdf (scanned files)
- Line-item quantities and the wage rates are in those unread files
- Whether work can be done remotely is not stated; this is on-site paving work at three locations
Notice details
Notice type, codes, versions and files
- Posted
- Nov 17, 2026
- Notice type
- Solicitation
- Office
- USDA-FS, CSA Intermountain 8, Ogden, UT
- Product/service code
- Y1LB · Construction of Highways, Roads, Streets, Bridges, and Railways
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 237310)
- Versions
5 versions have been posted, newest first.
- Nov 23, 2026 · Amendment 0004Due Dec 18, 2026
- Nov 23, 2026 · Amendment 0003Due Dec 18, 2026 (changed)
- Nov 17, 2026 · Amendment 0002 (this version)Due Dec 1, 2026 (changed)
- Oct 22, 2026 · Amendment 0001Due Nov 23, 2026
- Oct 21, 2026 · SolicitationDue Nov 23, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Set-aside contracts explained
Terms on this notice: Solicitation, Set-aside
Latest amendment note from SAM.gov
Similar open opportunities
- Parking Lots Repair, National Agricultural Library and Beltsville Agricultural Research Center WestTotal small business set-aside, solicitation 124PCA27Q0005: the Agricultural Research Service (ARS), part of the Department of Agriculture, wants two Beltsville, Maryland parking…
- W912EK27BA003 - Detroit Project Office Detroit, MI Wayne County Roads, Parking, and Grounds RenovationThe U.S. Army Corps of Engineers (Rock Island District, Detroit Project Office) plans to buy a renovation of roads, parking and grounds at a site in Wayne County, Detroit,…
- USDA Design/Build Perimeter Security Enhancement Parking Lot 9Phase 1 of 2 (solicitation 124PCA27Q0002): the U.S. Department of Agriculture (USDA) wants a design/build contractor (one firm does the design and the construction) to finish the…
- Sepa Parking Lot Repaving and RepairsThe Department of Energy's Southeastern Power Administration (SEPA) wants a contractor to repave and repair the parking lot at its office in Elberton, Georgia.