  1. What is a sources sought notice?
  2. Why agencies post sources sought notices: the rule of two
  3. How is a sources sought notice different from an RFI or a solicitation?
  4. Do you have to respond to bid later?
  5. How to respond to a sources sought notice (with a template)
  6. Common mistakes to avoid
  7. What happens after you respond
  8. How to find sources sought notices
  9. Next steps
  10. Frequently asked questions

A sources sought notice is a market research notice a federal agency posts on SAM.gov to find out which businesses can do a job before it decides how to buy it, including whether to set the work aside for small businesses. It isn't a solicitation, no contract is awarded from it, and responding is voluntary. But a short, specific response can help the contracting officer decide to reserve the contract for businesses like yours.

Free sources sought response template

Responding to a notice now? Download the free response template (Word), then follow the sample response outline and the worked example below.

What is a sources sought notice?

Part 10 of the current Federal Acquisition Regulation (FAR) requires market research before an agency writes a new requirement or asks for offers above the $350,000 simplified acquisition threshold, and in smaller buys when adequate information isn't available. It says the results decide whether to use a small business program. The FAR overhaul text agencies have adopted keeps the requirement for new requirements, and for buys and orders above that threshold. It drops the smaller-buy rule, the small business wording and the list of methods. The Small Business Administration's (SBA's) own rules still require market research on small business participation.

A sources sought notice is one way to do that research in public. The agency describes the work, asks capable businesses to identify themselves, and lists its questions. A 2026 Department of Veterans Affairs (VA) notice put it plainly: "This is a Sources Sought notice only. This is not a request for quotes and no contract will be awarded from this announcement."

Neither FAR text requires a sources sought notice. It's one research method among several.

They're common, though. On September 26, 2026, FedReady's search of SAM.gov data showed 780 open sources sought notices. The Department of Defense posted 519 of them, about two in three, and the VA posted 86. See how many are open today.

Why agencies post sources sought notices: the rule of two

Many sources sought notices exist to answer one question: are there enough capable small businesses to set this contract aside?

That's the rule of two. Under the FAR overhaul text, a contracting officer must set aside a contract above the micro-purchase threshold (generally $15,000) for small businesses when they reasonably expect offers from two or more responsible small businesses that are competitive on price, quality and delivery. The current FAR adds that market research isn't the only factor, but your response is part of the evidence.

Above the simplified acquisition threshold, SBA's rules tell the contracting officer to consider the 8(a), HUBZone, service-disabled veteran-owned (SDVOSB) and women-owned (WOSB) programs first, with "no order of precedence" among them. SDVOSB and WOSB set-asides also need a reasonable expectation, based on market research, of two eligible offers. When a notice asks about your socioeconomic status, it's collecting that evidence.

That's why most notices don't name a set-aside yet. Of the 780 open on September 26, 2026, 680 listed none, which is normal: deciding is the point. A typical VA notice says the work may be set aside for SDVOSBs, veteran-owned small businesses (VOSBs) or small businesses, or opened to full and open competition, based on the responses.

The flip side matters too. If too few capable small businesses respond, the work may not be set aside. A September 2026 Army notice warned that without enough information, it might award a sole-source contract instead.

How is a sources sought notice different from an RFI or a solicitation?

Table with columns: Notice, What it means, Can a contract come from it?, Your move
NoticeWhat it meansCan a contract come from it?Your move
Sources SoughtMarket research: who can do this work?NoSend a short response
RFI (request for information)Market research on capabilities, prices or approachesNo. Responses aren't offersAnswer the questions asked
PresolicitationA solicitation is coming soonNoGet ready and watch for it
Solicitation or combined synopsis/solicitationThe actual request for offers or quotesYesDecide and bid by the deadline

Sources sought vs. RFI

In practice, they're nearly the same thing. SAM.gov has no separate RFI notice type, so agencies post an RFI as a sources sought notice (or sometimes a special notice). The General Services Administration (GSA) describes the two together as "a market research tool used to obtain price, delivery, capabilities, interest, etc. for planning purposes."

The FAR says the same thing in both its current and overhaul texts: responses to RFIs aren't offers, and the government can't accept one to form a contract. The label matters less than the questions, so answer what the notice asks.

Sources sought vs. solicitation

A solicitation asks for an offer, with a price and a deadline, and the agency evaluates offers and awards a contract. A sources sought notice asks only whether and how you could do the work. There's no price proposal, no evaluation and no award.

Do you have to respond to bid later?

Generally, no. No FAR rule makes a response a condition of bidding, and many notices say so. A September 2026 Army notice said, "Not responding to this Sources Sought Notice does not preclude participation in any future Request for Quote (RFQ)." An Army Corps of Engineers notice called responses "strictly voluntary."

Skipping one still has a cost. If you don't respond, the agency can't count you when it decides whether to set the work aside. The contract you wanted to bid on as a small business could come out as full and open competition instead.

SBA also tells contracting officers they're required to search its Small Business Search (SBS) as part of market research. SBS is filled from your SAM.gov registration, so a complete registration helps even for notices you miss.

A response isn't a bid

Responding doesn't commit you to anything, and it doesn't guarantee a set-aside. The contracting officer decides.

How to respond to a sources sought notice (with a template)

What agencies usually ask for

Read the whole notice first. Notices posted in 2026 commonly asked for:

  • Your Unique Entity ID (UEI), CAGE code, legal name and address
  • Your business size and socioeconomic status under the NAICS code in the notice
  • A capability statement
  • Relevant experience, often two or three similar projects
  • Answers to specific questions about how you'd do the work
  • A page limit, such as 5, 8 or 10 pages

Some notices tell large businesses not to respond at all. SBA advises contracting officers to "ask only for key pieces of information" and to set a page limit, so short is what they expect.

Writing your response, step by step

  1. Check fit first. Note the NAICS code, place of performance and deadline. Confirm you're small under that code, and that you could do the work or a meaningful part of it.
  2. Put your company data at the top. Your legal name and address as in SAM.gov, UEI, CAGE code, a named contact, and your size under the notice's code, such as "Small under NAICS 561730." List only SBA certifications you actually hold.
  3. Say you're interested, if it's true. One sentence: you plan to submit an offer if a solicitation is issued. The rule of two turns on whether the agency expects offers, so saying you'll bid matters as well as showing you can do the work.
  4. Answer every question in order. Use the notice's numbering and words. Be specific about staff, equipment, locations and how you'd do the work.
  5. Show similar work. Give two or three projects closest in scope and size: federal first, then state, local or commercial. Include the customer, dates, value and what made it similar.
  6. Attach a tailored capability statement if the notice allows one, and check whether attachments count toward the page limit.
  7. Send it the way the notice says: to the named contact, before the deadline, in the format it asks for. If it doesn't say, a PDF named with the notice ID and your company name is a safe choice.

Free sources sought response template

Free sources sought response template (Word)

A two-page response outline with every section a contracting officer usually asks for. Replace the sample text with yours.

Download (.docx)

When a notice sets its own format or page limit, follow the notice.

Sample sources sought response outline

Use this outline whether or not you download the template. It's the same structure, section by section:

  1. Header. "Response to Sources Sought Notice," the notice title and ID exactly as on SAM.gov, the agency and office, the contact you're sending it to, and the date.
  2. Company information. Legal name and physical address as in SAM.gov, UEI and CAGE code, a point of contact, your size under the notice's NAICS code, only the socioeconomic statuses you actually hold, and any contract vehicles.
  3. Interest. One or two sentences saying you plan to submit an offer if a solicitation is issued, if that's true.
  4. Answers to the notice's questions. Every question, in the notice's order and numbering, with specifics on staff, equipment and location.
  5. Relevant experience. Two or three similar projects, with the customer, contract number, dates, value, how it's similar, and a reference.
  6. Suggestions. Only if the notice asks, for example on the NAICS code or whether the work could be set aside.
  7. Attachments. A one-page capability statement tailored to the agency, plus anything else the notice asks for. No pricing unless asked.

Before you send it, replace every placeholder, check the page limit, and save it as a PDF named with the notice ID and your company name.

Paid FedReady plans include a sources sought response tool that builds this same outline for a notice you've saved, pulls the notice's questions out as headings, and fills in your company details from your profile.

Sources sought response example (fictional)

Here's a short example from an invented company answering an invented notice for grounds maintenance at a federal site.

Bramblewick Grounds LLC. Response to Sources Sought [notice ID], Grounds Maintenance Services

1. Company information. Legal name and physical address as in SAM.gov · UEI and CAGE code · Owner's name, direct phone and email · Small under NAICS 561730 ($9.5 million size standard) · No SBA certifications.

2. Interest. Bramblewick Grounds plans to submit an offer if a solicitation is issued.

3. Answers. Q1, weekly maintenance of 18 acres: two crews maintain a 14-acre office park weekly today and maintained 9 county ball fields through 2025. Q2, snow response within 2 hours: two company-owned plow trucks based 12 miles from the site.

4. Experience. Office park, 14 acres, commercial, 2021 to present, about $60,000 a year: weekly mowing, renewed three times. County parks department, 9 ball fields, 2023 to 2025, about $40,000 a year: no missed visits.

5. Attachment. A one-page capability statement tailored to grounds maintenance.

Notice what's missing: marketing adjectives, pricing and unrelated services.

Common mistakes to avoid

Training from the Alaska APEX Accelerator warns against "a 'one size fits all' response." Other mistakes to avoid:

Table with columns: Mistake, Fix
MistakeFix
Sending only a capability statementAnswer each question, then attach it as support
A generic responseUse the notice's words and its order
Going over the page limitStay under it, including attachments if they count
Leaving out your size under the notice's NAICS codeState it plainly, with the code
Claiming a certification you don't holdList only SBA certifications you have
Treating it like a proposalSkip pricing and sales copy unless asked
Missing the deadline or the right inboxSend it early, to the contact in the notice

What happens after you respond

Usually, nothing you can see. A VA notice said it plainly: "Respondents will not be notified of the results of the evaluation." The contracting officer weighs the responses with other research and decides how to buy. Next, you might see:

  • A solicitation set aside for small businesses or for one program.
  • A solicitation open to full and open competition.
  • A presolicitation notice, or another round of market research.
  • Nothing, because plans changed.

So keep watching. Follow the notice on SAM.gov, check the agency's other notices under the same NAICS code, and send your capability statement to its small business office.

How to find sources sought notices

On SAM.gov Contract Opportunities, filter by the notice type "Sources Sought," add your NAICS codes and state, and save the search. You can also use the same filter in FedReady's free search, updated daily from SAM.gov data, where a free account lets you get email alerts for a search and save the notices you want to follow.

Updated daily from SAM.gov

Open sources sought notices

Agencies doing market research right now. Responding is free, and it doesn't commit you to bid.

See sources sought notices

For more ways to spot work early, see how to find government contracts.

Next steps

Sharpen your capability statement so it's ready to tailor, and learn how each set-aside program works so you can state your status correctly. When a solicitation follows, use how to read a government solicitation to decide whether to bid.

Frequently asked questions

What should a sources sought response include?

Your company data (legal name, UEI, CAGE code and size under the notice's NAICS code), a sentence saying you plan to bid if that's true, an answer to every question in the notice's order, and two or three similar projects. Attach a short capability statement if the notice allows it, and stay within the page limit.

How long do I have to respond to a sources sought notice?

Each notice sets its own deadline, so check the response date on the notice. There's no FAR-wide minimum, though some agencies set one, such as 14 calendar days for sources sought notices at the Defense Information Systems Agency.

Can I respond if my business isn't registered on SAM.gov yet?

Usually yes, because a response isn't an offer. But many notices ask for your UEI and CAGE code, and in most cases you must have an active registration when you submit an offer. You can often get a UEI right away, but on SAM.gov a CAGE code comes only with a full registration. Registration is free, so start now.

Should I include prices in a sources sought response?

Only if the notice asks. Some RFI-style notices ask for rough pricing to help the agency plan. Otherwise leave prices out, since anything you send is information only and not an offer.

Should a large business respond to a sources sought notice?

Read the notice first. Some ask only small businesses to respond, and some tell other-than-small firms not to. If the notice invites all businesses, answering helps the agency understand the whole market.

Will the agency tell me whether my response made a difference?

Usually not. Many notices say respondents won't be notified of the results. Watch SAM.gov for a presolicitation or solicitation for the same work, which shows how the agency decided to buy.

Sources

Show all 10 sources
  1. FAR 10.001, Policy (market research), Acquisition.gov
  2. FAR Overhaul, Part 10: Market Research, Acquisition.gov
  3. FAR Overhaul, Part 19: Small Business Programs, Acquisition.gov
  4. FAR 15.201, Exchanges with industry before receipt of proposals, Acquisition.gov
  5. 13 CFR 125.2, SBA's and the procuring agency's responsibilities, eCFR (National Archives)
  6. Guidance for federal contracting officials, U.S. Small Business Administration
  7. Research active solicitations, GSA
  8. FAR Overhaul, Part 15: Contracting by Negotiation, Acquisition.gov
  9. Sources sought notice, Army (September 25, 2026), SAM.gov
  10. Sources sought notice, Department of Veterans Affairs (2026), SAM.gov

Founder, FedReady

Cyrus Hakimi is the founder of FedReady, which helps small businesses find and track federal contracts without hiring a consultant. These guides are written for business owners who are new to government work. More about FedReady · Cyrus on LinkedIn

This guide is general information, not legal or financial advice. Rules and thresholds change, so confirm details on SAM.gov and the official agency sites linked above before you act. AI tools help us research and draft these guides, so check the sources before you rely on a detail. FedReady is an independent company and is not affiliated with any government agency.

Find contracts that fit your business.

Free account. Save opportunities, track deadlines, and get matched to contracts that fit your business.