Solicitation
UT NP ARCH 100(2) Bridges on Delicate Arch Road
Department of Transportation · Federal Highway Administration
AI summary Beta
This summary may miss requirements: 5 of 16 attachments weren't read (Sign-in Sheet.pdf, UT NP ARCH 100(2) Pre-Show Powerpoint 10-8-2026.pdf and 3 more). Check the attachments on SAM.gov.
Solicitation 6982AF27B000005: the Federal Highway Administration (Central Federal Lands Highway Division) wants a contractor to build three 100-foot-span concrete bridges, raise and rebuild about 0.99 miles of Delicate Arch Road, and repave two parking lots in Arches National Park near Moab, UT. It is a sealed-bid Invitation for Bids (IFB) with full and open competition, a HUBZone price preference, and a stated price range of $10,000,000 to $20,000,000. SAM.gov gives the response due date as December 1, 2026, 2:00 PM Mountain, for paper bids only, with a bid bond.
Who can bid
- Bid guarantee: an original bid bond with original signatures and corporate seals must come with the bid From 6982AF27B000005.pdf
- Active registration in the System for Award Management (SAM) when the bid is submitted and at award, with NAICS 237310 in the SAM profile and annual representations and certifications done From 6982AF27B000005.pdf
- Steel bridge railing must come from a plant certified under the American Institute of Steel Construction (AISC) quality program; the Certified Bridge Fabricator level is adequate From QnA 10.15.26.pdf
How to submit: Printed, sealed paper bid delivered to Laura Slauter, Contract Specialist, Federal Highway Administration, Central Federal Lands Division Office, 12300 W. Dakota Avenue, Lakewood, CO 80228. Electronic bids are not accepted. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (7)
From the version posted Nov 17, 2026.
- Serious: Original bid bond required with the bid. A bid bond with original signatures and corporate seals must be in the sealed envelope; a photocopy or fax makes the bid non-responsive, and a $10 to $20 million job means a large bonding capacity is needed. From 6982AF27B000005.pdf
- Worth checking: Paper bids only. Bids must be mailed or delivered in a sealed envelope to Lakewood, CO, and arrive by the response due date; email or portal bids are not accepted. From 6982AF27B000005.pdf
- Worth checking: HUBZone price preference. Prices from firms that are not HUBZone small businesses get a 10% evaluation factor added, which can lift a non-HUBZone bidder's total above a HUBZone bidder's. From 6982AF27B000005.pdf
Show all 7Show fewer
- Worth checking: Performance and payment bonds within 10 days of award. The winner must have performance and payment bonds in place quickly after award on a project of this size. From 6982AF27B000005.pdf
- Worth checking: Steel bridge railing from an AISC-certified plant, no alternatives. The railing must be made in a certified plant and the contracting officer will not consider alternatives or changes to the welding rules. From QnA 10.15.26.pdf
- Minor: Work inside a busy national park. There is one park entrance with a kiosk that is 13 feet 11 inches high, no water is available from the Park, the drive from Moab to the site is about 40 minutes, and traffic control may be needed for tall deliveries. From QnA 10.15.26.pdf
- Minor: The site visit was Oct 8, 2026. Check the notice and its amendments for whether attendance was required, and whether another visit is offered. From 6982AF27B000005.pdf
Read from the notice and 11 attachments. 5 of 16 not read. Show which files.
- 6982AF27B000005.pdf (read)
- Amendment A002.pdf (read)
- Amendment A001.pdf (read)
- QnA 10.15.26.pdf (read)
- UT PRA ARCH 100(1) As-Builts.pdf (read)
- UT NP ARCH 100(2) - Cross Sections-Option Y.pdf (read)
- UT NP ARCH 100(2) - Cross Sections-Option X.pdf (read)
- UT NP ARCH 100(2) - Cross Sections-Schedule A.pdf (read)
- UT NP ARCH 100(2) Bridges on Delicate Arch Road Pavement Memo.pdf (read)
- UT NP ARCH 100(2) Bridges on Delicate Arch Road-Delineators-JOFOC.pdf (read)
- UT NP ARCH100(2) Bridges on Delicate Arch Road Final Hydraulics Report_Signed.pdf (read)
- Sign-in Sheet.pdf: not summarized: open it on SAM.gov
- UT NP ARCH 100(2) Pre-Show Powerpoint 10-8-2026.pdf: not read (it couldn't be opened): open it on SAM.gov
- UT NP ARCH 100(2) - PLANS.pdf: not read (it couldn't be opened): open it on SAM.gov
- UT.NP.ARCH.100(2).Bridges on Delicate Arch Road.Geotech Rpt FINAL.February 2025.pdf: not read (it couldn't be opened): open it on SAM.gov
- UT NP ARCH 100(2) Physical Data.zip: not read (the AI doesn't read this file type yet): open it on SAM.gov
Full summary
What they want
- Build 100-foot-span concrete bridges at Salt Valley Wash, Salt Wash and Winter Camp Wash, with drilled shafts and steel bridge railing
- Raise the road profile at each wash and realign the road and new bridge at Salt Valley Wash, north of the existing crossing
- Rebuild the remaining road sections by full depth reclamation (grinding up the old pavement and base) or pavement removal, then a 4-inch pavement overlay, including parking areas
- Embankment: 10,000 CUYD; riprap, Class 3: 1,725 CUYD; roadway aggregate: 5,140 TON; asphalt concrete pavement: 8,300 TON
- Structural concrete, Class A: 752 CUYD; epoxy-coated reinforcing steel: 138,000 LB; drilled shafts: 750 LNFT (24-inch) and 890 LNFT (30-inch)
- Bridge railing: 642 LNFT; guardrail: 1,290 LNFT; reinforced colored concrete curb: 3,921 LNFT; flagger traffic control: 5,800 HOUR
- Price Schedule A (0.99 miles, 2 parking lots), Option X (0.35 miles) and Option Y (1 parking lot)
- Use the Government's Masterworks web system for daily reports and pay notes, and attend its training (after award)
- Contract type
- Sealed-bid Invitation for Bids (IFB) for construction, priced by unit prices on a bid schedule (Schedule A plus Option X and Option Y)
- Period of performance
- Start within 10 calendar days after the notice to proceed; completion date is set in Special Contract Requirement (SCR) Section 108.01, which was not read. The notice's anticipated schedule gives Notice to Proceed December 2026 and Contract Completion December 2028
- Place of performance
- Arches National Park, Grand County, Utah (Delicate Arch Road); the Park entrance is about 5 miles north of Moab, UT
- Estimated value
- The Government's price range for the work is between $10,000,000 and $20,000,000
- How they'll choose
- Sealed bidding: bidders price Schedule A, Option X and Option Y, and the Government evaluates the total of all three first; the rest of the award rule was cut off in the text read. A 10% price evaluation factor applies to offers from firms that are not HUBZone small businesses
- Offers due
- December 1, 2026, 2:00 PM Mountain
- How to submit
- Printed, sealed paper bid delivered to Laura Slauter, Contract Specialist, Federal Highway Administration, Central Federal Lands Division Office, 12300 W. Dakota Avenue, Lakewood, CO 80228. Electronic bids are not accepted
What they'll judge offers on
- Price: the total of Schedule A, Option X and Option Y
What to include when you submit
- Send the bid in a sealed envelope or package showing the time and date for receipt, the solicitation number, and the bidder's name and address (also the project number and name)
- Standard Form 1442 (SF-1442, the form you sign and return as your bid), pages A-1 and A-2, in original with 0 copies
- Bid schedule pages A-7 through A-17, with a unit price and amount for every pay item and the totals
- Indication of interest in formal partnering (page A-6)
- Completed Authority to Bind certificate (pages A-18 through A-22)
- Buy American Act and Hazardous Materials pages (A-23 and A-24)
- Bid guarantee under RFO Clause 52.228-1: original bid bond with original signatures and corporate seals; photocopies and faxes make the bid non-responsive
- VETS-4212 declaration (page A-ii) and Bidders' Information (pages B-5 through B-8)
- HUBZone small businesses that want to waive the price preference must complete RFO Clause 52.219-4 in Section C
- Acknowledge every amendment in Item 19 of the SF-1442 by the date and hour set in the solicitation, or the bid may be rejected
- Offers must allow at least 60 calendar days for Government acceptance after the date offers are due
- Technical questions go in one Word document by email to CFLContracts@dot.gov; answers are posted on SAM.gov
After award, you must have
- Performance and payment bonds are due within 10 calendar days after award (Item 12B lists 10 days; see RFO Clause 52.228-15) From 6982AF27B000005.pdf:
Item 12A: PERFORMANCE AND PAYMENT BONDS: See RFO Clause 52.228-15…
- A large business that is the low bidder on an award above $2.0 million must submit an acceptable small business subcontracting plan within 7 days of the contracting officer's request From 6982AF27B000005.pdf:
RFO Clause 52.219-9, Small Business Subcontracting Plan, Alternate I, requires that the large…
Current contractor
No incumbent is named. A justification for other than full and open competition covers one item only, 100 Shur-Flex delineators (item 63309-0100), as the only source that meets the Park's need for the same model already used in Arches National Park; it says no market research was done and no firms expressed written interest. The rest of the work is full and open competition.
Not in the notice text
- Most of the IFB text (Basis for Award, bid schedule, provisions, clauses, wage rates and Special Contract Requirements) was cut off in the text read, and the plans, geotechnical report and physical data were attached but not read, so requirements may be missing from this brief.
- The exact response due date on page A-1 of Amendments A001 and A002 did not come through in the text; SAM.gov gives December 1, 2026, 2:00 PM Mountain.
- The bid bond amount (RFO Provision 52.228-1) and the number of calendar days to finish the work (SCR Section 108.01) are not stated in the text read.
- The solicitation lists a Department of Labor construction wage rate requirement (Section D-1); the text read does not name Davis-Bacon or give the wage rates.
- The sign-in sheet, the site visit presentation, the plans, the geotechnical report and the physical data zip file are attached but not read.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 17, 2026
- Notice type
- Solicitation
- Office
- 6982AF Central Federal Lands Divisi, Lakewood, CO
- Product/service code
- Y1LB · Construction of Highways, Roads, Streets, Bridges, and Railways
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 237310)
- Versions
5 versions have been posted, newest first.
- Nov 17, 2026 · Amendment 0004 (this version)Due Dec 1, 2026 (changed)
- Oct 22, 2026 · Amendment 0003Due Nov 19, 2026 (changed)
- Oct 15, 2026 · Amendment 0002Due Nov 10, 2026
- Oct 6, 2026 · Amendment 0001Due Nov 10, 2026
- Oct 6, 2026 · SolicitationDue Nov 10, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- ID FLAP CLEAR 4783(1), Dent Bridge Road ImprovementsOnly the six named holders of the Idaho, Montana, and Surrounding Areas multiple award task order contract (MATOC) can send proposals on solicitation 69056726R000009.
- NPS Repair or Alteration of Highways, Roads, Streets, Trails and Bridges MultipSources sought notice 140PP027R0017: the National Park Service Denver Service Center is asking small businesses for capability statements for a possible nationwide multiple-award…
- NM FLAP SR35(1) Grant County BridgesPresolicitation: the Federal Highway Administration's Central Federal Lands Division plans to rebuild three bridges and a concrete box culvert on State Route 35 near Mimbres,…
- WA ERFO NPS OLYM 2022-1(3), OLYMPIC NPS ERFO REPAIRS 2022 Road 107 MP 0.3 TO 0.5 & MP 0.8Western Federal Lands Highway Division (Federal Highway Administration) is asking for sealed bids on an invitation for bids (IFB), a sealed-bid construction buy, to repair Upper…
- Humbolt Pacific Crest Trail Bridge ReplacementThe Forest Service (White River National Forest on SAM.gov), for the Humboldt-Toiyabe National Forest's Bridgeport Ranger District, wants a contractor to replace the Pacific…