Presolicitation
RFI U-10Mo Fuel Fabrication
Department of Energy
Response due Dec 21, 2026 · No set-aside · Richland, WA
Market research, not a bid. Replying is free and tells Department of Energy who could do this work. Send a short reply to the contracting contact; no price is needed. See the contact
A newer version of this notice was posted Nov 16, 2026. See the latest version.
AI summary Beta
Summary of the version posted Oct 9, 2026. The notice was amended Nov 16, 2026. Check what else changed on SAM.gov.
Battelle, which runs Pacific Northwest National Laboratory for the Department of Energy, is asking industry whether it could make uranium-molybdenum (U-10Mo) nuclear research reactor fuel for the National Nuclear Security Administration (NNSA). This is a Request for Information, not a bid request; companies reply with a letter of interest by 21 December 2026. The work would need a licensed nuclear materials facility, with the government supplying the uranium and possibly major equipment.
Who can bid (5)
- A facility that is an NRC Category II Special Nuclear Material facility or a DOE Hazard Category III facility From RFI for U-10Mo Monolithic Fuel Fabrication Final.pdf
- Quality assurance experience meeting NQA-1 nuclear quality requirements or equivalent From RFI for U-10Mo Monolithic Fuel Fabrication Final.pdf
- Experience in nuclear material handling and fabrication (research or power reactor fuel preferred)
Show all 5Show fewer
- Nuclear material control, criticality safety, physical and cyber security, environmental, radiological and worker-safety programs
- US businesses preferred; foreign-owned firms need a plan to address Foreign Ownership, Control or Influence
How to submit: Written letter of interest; the notice does not name a portal. Questions go to Chris Martin, Contracting Specialist, Christopher.martin@pnnl.gov, 509-372-6026. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (4)
- Serious: Needs a licensed nuclear facility. Respondents must have or plan a Category II special nuclear material facility, which takes major licensing, capital and time that few small businesses have. From RFI for U-10Mo Monolithic Fuel Fabrication Final.pdf
- Serious: Large scale operation. The concept assumes about 25,000 sq ft of floor space, a roughly 30 ft high bay, about 45 staff, and about 10,000 plates and 200 elements per year. From RFI for U-10Mo Monolithic Fuel Fabrication Final.pdf
- Worth checking: Long timeline and no award yet. This is only market research, and actual supplier development is not expected to start until the late 2020s. From RFI for U-10Mo Monolithic Fuel Fabrication Final.pdf
Show all 4Show fewer
- Minor: Requirements may change. The government warns that technical details in its answers are not final. From Technical Questions - Repsonse - RFI-966967 - 10-1-2026.pdf
Read from the notice and 2 attachments. Show which files.
- Technical Questions - Repsonse - RFI-966967 - 10-1-2026.pdf (read)
- RFI for U-10Mo Monolithic Fuel Fabrication Final.pdf (read)
Full summary
What they want
- Letters of interest from companies able to make U-10Mo alloy, fuel plates and fuel assemblies (alloy plus plates and assemblies in one facility is preferred)
- Facilities that are, or could become, an NRC Category II Special Nuclear Material facility or DOE Hazard Category III facility
- Rough timeline and order-of-magnitude cost for developing the facility, assuming NNSA provides major equipment
- Experience with nuclear material handling and fuel fabrication, and a plan for NQA-1 (nuclear quality assurance) or equivalent
- Safety, security, criticality, environmental and radiological program descriptions
- Team arrangements are welcome (for example casting, rolling, HIP, radioactive material handling)
- Contract type
- Request for Information (market research); no contract is being awarded
- Period of performance
- Not stated. The need is expected to exceed existing capacity in the mid-2030s, with supplier development starting in the late 2020s
- Place of performance
- Richland, WA is listed for the RFI; the fabrication facility would be the respondent's own
- Estimated value
- No contract value. The RFI estimates the annual U-10Mo fuel market at about $100-$175M per year (preliminary)
- How they'll choose
- Not stated; information-gathering only
- Offers due
- Dec 21, 2026 4:00 PM Pacific (letters of interest) (from the version posted Oct 9, 2026; amended since)
- How to submit
- Written letter of interest; the notice does not name a portal. Questions go to Chris Martin, Contracting Specialist, Christopher.martin@pnnl.gov, 509-372-6026
- Page limits
- Less than 20 pages
What to include when you submit
- Mark proprietary information as needed; reviewers include NNSA/DOE and its FFRDC contractors
- Second round of questions due to Battelle by 12 November 2026, answers by 19 November 2026
- Include organization name, address, contact, year established, ownership and locations
- Include a Foreign Ownership, Control or Influence (FOCI) plan, including export control, if applicable
- Note any transportation needed to distant facilities
Not in the notice text
- How letters of interest are to be submitted (email address or portal is not stated)
- Specification SPC-70872 (U-10Mo fuel fabrication) is referenced and was said to be attached but is not in the text provided
- Contract type, contract length, and whether any procurement will follow
- Whether any set-aside will be used later
Notice details
Notice type, codes, versions and files
- Posted
- Oct 9, 2026
- Notice type
- Presolicitation
- Office
- PNNL Contracts - DOE Contractor, Richland, WA
- Product/service code
- 1140 · Nuclear Components
- Business type
- Manufactured parts & equipment (FedReady's grouping, from NAICS 325180)
- Versions
3 versions have been posted, newest first.
- Nov 16, 2026 · Amendment 0002Due Dec 21, 2026
- Oct 9, 2026 · Amendment 0001 (this version)Due Dec 21, 2026
- Sep 17, 2026 · PresolicitationDue Dec 21, 2026
- Attachments
Before you respond
Terms on this notice: Solicitation