This summary may miss requirements: 5 of 12 attachments weren't read (Plans - MS NP NATR 3N19 3H28 ETC.pdf, MS NP NATR 3N19 3H28 ETC_RIP_Rpts.pdf and 3 more). Check the attachments on SAM.gov.
The Federal Highway Administration's Eastern Federal Lands Highway Division is taking sealed bids (solicitation 693C73-27-B-000006) for Pavement Rehabilitation between MP 121 and MP 204 (Phase 3) on the Natchez Trace Parkway, in Attala, Choctaw, Leake, Madison and Webster Counties, Mississippi. Any business may bid: there is no set-aside, but eligible HUBZone firms get a 10% price evaluation preference. The work is estimated at $60,000,000 to $70,000,000 and takes 284 calendar days; the response due date is December 22, 2026, 2:00 PM Eastern.
Who can bid (4)
- Open to all businesses (unrestricted); HUBZone small businesses on the SBA list get a 10% price evaluation preference From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
- Bid guarantee of at least 20 percent of the bid price or $3 million, whichever is less From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
- Project Labor Agreement (PLA), a pre-hire agreement with labor unions, submitted by the apparent successful bidder before award From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
Show all 4Show fewer
- Active SAM.gov registration when bidding and at award From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
How to submit: Email to EFLHD.Contracts@dot.gov only (no cloud links, no fax); mailing to FHWA EFLHD, Quantum Park, 22001 Loudoun County Parkway, Suite E2-3-300, Ashburn, VA 20147 is allowed but hand delivery isn't recommended. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (8)
From the version posted Nov 20, 2026.
- Serious: Project Labor Agreement required before award. The low bidder must submit a union Project Labor Agreement meeting Executive Order 14063 before award, which can add cost and time for non-union firms. From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
- Serious: Large bid bond. On a $60 to $70 million job, you need a surety willing to bond 20 percent of your bid, up to $3 million, or the bid is rejected. From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
- Serious: Very large project for a small business. The expected price range is $60,000,000 to $70,000,000, with heavy paving equipment and bonding capacity needed. From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
Show all 8Show fewer
- Worth checking: Must self-perform half the work. You must do at least 50% of the work with your own crews, so you can't subcontract most of it. From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
- Worth checking: Every pay item must be priced. A bid that leaves out a price for any pay item isn't eligible for award. From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
- Minor: Subcontracting plan timing differs. The notice says large businesses' plans must be approved before award; the SF 1442 continuation says provide it within 7 days of award; ask the contracting officer. From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
- Minor: No survey done for the plans. The plans were drawn from land-use plans and as-builts, and stationing must be confirmed in the field, so quantities may shift. From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
- Minor: Schedule B may come later. Schedule B is a Government option the agency may award at the start or exercise later, so part of the work isn't guaranteed. From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf
Read from the notice and 7 attachments. 5 of 12 not read. Show which files.
- IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf (read)
- Subcontracting Plan - MS NP NATR 3N19 3H28 ETC.pdf (read)
- Natchez Trace No Passing Zones Memo_v3.pdf (read)
- FP14_Eng.pdf (read)
- VETS-4212 Form.pdf (read)
- Categorical Exclusion Form (NEPA) - NPS.pdf (read)
- Categorical Exclusion Form (NEPA).pdf (read)
- Plans - MS NP NATR 3N19 3H28 ETC.pdf: not read (it couldn't be opened): open it on SAM.gov
- MS NP NATR 3N19 3H28 ETC_RIP_Rpts.pdf: not read (it couldn't be opened): open it on SAM.gov
- Natchez Trace Trail.zip: not read (the AI doesn't read this file type yet): open it on SAM.gov
- MS NP NATR 3N19 3H28 etc Pavment Memo June_2026.pdf: not read (it couldn't be opened): open it on SAM.gov
- ADV_Bidders Qualifications Form.doc: not read (the AI doesn't read this file type yet): open it on SAM.gov
Full summary
What they want
- Full depth reclamation with cement, 8-inch depth (178,000 SQYD) on the parkway, ramps, access roads and parking or pull-off areas
- Asphalt pavement milling: 2-inch depth (955,000 SQYD) and 4-inch depth (178,000 SQYD)
- Asphalt concrete pavement, 1/2-inch gyratory mix (149,360 TON), plus wedge and leveling course and pavement patching
- Pavement markings, sign removal and replacement, and concrete curb work
- Traffic control, detours, erosion control and turf establishment
- Schedule A is the base contract; Schedule B is a Government option the agency may award later
- Contract type
- Unit-price construction contract awarded by sealed bid (Invitation for Bids, IFB): you are paid your bid unit prices for the quantities actually built
- Period of performance
- 284 calendar days from the notice to proceed for Schedule A, or Schedules A and B together; 166 calendar days for Schedule B if it is exercised later
- Place of performance
- Natchez Trace Parkway, milepost 121 to 204, in Attala, Choctaw, Leake, Madison, and Webster Counties, Mississippi
- Estimated value
- $60,000,000 to $70,000,000 (expected price range for the entire project)
- How they'll choose
- Sealed bid: award to the responsive, responsible bidder with the lowest Evaluation Total Price (Schedule A bid total plus Schedule B bid total)
- Offers due
- December 22, 2026, 2:00 PM Eastern
- How to submit
- Email to EFLHD.Contracts@dot.gov only (no cloud links, no fax); mailing to FHWA EFLHD, Quantum Park, 22001 Loudoun County Parkway, Suite E2-3-300, Ashburn, VA 20147 is allowed but hand delivery isn't recommended
What they'll judge offers on
- Price: Schedule A (base) plus Schedule B (Government Option 1), with a 10% price evaluation preference for eligible HUBZone small businesses
- Responsibility, judged from the Bidder's Qualifications Form
What to include when you submit
- Put the solicitation number, project number and ATTN: Ms. Emily McCleary in the email subject line
- Complete and sign Standard Form 1442 (SF 1442), the bid form: name, address, phone, amendments acknowledged in block 19, signature in block 20
- Enter a unit price and amount for every pay item on bid schedule pages B-1 through B-5, for both Schedule A and Schedule B
- Include a Standard Form 24 (SF 24) bid bond for at least 20% of the bid or $3 million, whichever is less, with a valid power of attorney; send a scanned copy if bidding by email
- Complete, sign and send the Bidder's Qualifications Form with the bid
- Check the HUBZone waiver box in provision 52.219-4 if it applies to you
- Large businesses: a subcontracting plan isn't required with the bid but is encouraged
- Have an active SAM.gov registration with representations and certifications, and a current VETS-4212 report; if your SAM record isn't public, send a copy
After award, you must have
- Perform at least 50% of the work on site with your own organization From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf:
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 50%.
- Performance and payment bonds; the notice to proceed follows receipt of acceptable bonds From IFB Solicitation - MS NP NATR 3N19 3H28 ETC.pdf:
Furnish performance and payment bonds in accordance with FAR Clause 52.228-15.
Not in the notice text
- Much of the bid package is attached but not read: the plans, the pavement memo, the RIP reports, the Natchez Trace Trail zip file, the Bidder's Qualifications Form, and the middle of the IFB solicitation (Sections E through K) and FP-14 specifications.
- The wage rates (minimum wage schedules, pages F-6 through F-40, the Davis-Bacon wage determination) are in the part of the solicitation that wasn't read; check them on SAM.gov.
- Site visits are by request under Section E of the solicitation, which wasn't read; the documents read don't call a site visit required.
- No deadline for questions appears in the parts read.
- Work limits such as night work, no-work periods and closures are in Special Contract Requirements Sections 108 and 156, which weren't read.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 20, 2026
- Notice type
- Solicitation
- Office
- 693C73 Eastern Fed Lands Division, Ashburn, VA
- Product/service code
- Y1LB · Construction of Highways, Roads, Streets, Bridges, and Railways
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 237310)
- Versions
2 versions have been posted, newest first.
- Nov 20, 2026 · Solicitation (this version)Due Dec 22, 2026
- Nov 5, 2026 · PresolicitationDate Dec 22, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation