Solicitation
C-5 MLG Trunnion Bearing
Department of Defense · Department of the Air Force
AI summary Beta
This summary may miss requirements: 2 of 14 attachments weren't read (A001 (CAV) End Item Reporting DI-MGMT-81838 27-00013 .pdf, DD FORM 1653 Transportation Requirements.pdf). Check the attachments on SAM.gov.
The Air Force (Air Force Sustainment Center, Robins AFB area) wants a depot-level remanufacture of the C-5 main landing gear trunnion bearing, NSN 3120-00-766-2056UC, in a 5-year requirements contract: 1 basic year plus four 1-year ordering periods. Only firms already on the Government's qualified source list, or that send a complete source approval request (SAR) package, can be considered. The response due date is November 30, 2026, 5:00 PM Eastern, and the award is planned as lowest price technically acceptable.
Who can bid (4)
- Be on the Government's pre-approved qualified source list, or submit a complete source approval request (SAR) package that meets the Source Pre-Qualification Requirements document and the PWS
- Registered in the Joint Certification Program and approved to view export-controlled data, to obtain the technical data packages
- Perform at least 75 percent of the remanufacturing workload in-house (part of source approval) From Source_Pre-Qualification_Trunnion_Bearings.pdf
Show all 4Show fewer
- Quality program certified to at least ISO 9001:2000 From PWS.pdf
Things to watch (8)
From the version posted Nov 18, 2026.
- Serious: Only approved sources or firms with a complete source approval package can win. A new firm must send a full SAR package (manufacturing plan, quality plan, source records) and pass a one-time first article test for full status, which takes time and money; all qualification costs are paid by the applicant.
- Serious: Technical data is export controlled. A firm must hold Joint Certification Program (JCP) registration, a DoD check that a U.S. or Canadian firm may receive export-controlled data, before it can get the drawings.
- Worth checking: Date passed (Mar 2, 2026): Source approval dates differ between documents. The Source Pre-Qualification document gives March 2nd 2026 for source approval responses, while the notice lets firms send a SAR package with the proposal. Ask the contracting officer which governs. From Source_Pre-Qualification_Trunnion_Bearings.pdf
Show all 8Show fewer
- Worth checking: New balls required; no reworked balls. Every unit needs newly made bearing balls, which raises material cost and lead time compared with earlier contracts. From PWS.pdf
- Worth checking: Urgent orders on 120 or 150 day schedules. Urgent (MICAP) and surge orders are worked on top priority; long-lead aluminum races must be expedited. From PWS.pdf
- Worth checking: Quantities are estimates only. The Government does not promise to order the 64 EA estimated for each period; orders are placed only as funded. From Amendment FA853826R0019 0002.pdf
- Minor: Response due date extended twice. Amendment 0001 moved it from October 27, 2026 to November 13, 2026, and Amendment 0002 moved it to November 30, 2026, 5:00 PM EST. The notice text's last sentence still shows October 27, 2026.
- Minor: Strict quality and data performance thresholds. At least 95 percent of units must pass first inspection, with no more than one failure per contract year, and late or rejected data deliverables are counted. From PWS.pdf
Read from the notice and 12 attachments. 2 of 14 not read. Show which files.
- PWS.pdf (read)
- Amendment FA853826R0019 0002.pdf (read)
- Amendment FA853826R0019 0001.pdf (read)
- Source_Pre-Qualification_Trunnion_Bearings.pdf (read)
- A006 RFV SESS-80640E.pdf (read)
- AFMC 158 Packaging Requirements.pdf (read)
- FA853826R0019.pdf (read)
- GFP ATTACHMENT.pdf (read)
- A005 ACCIDENT INCIDENT REPORT SAFT-81563.pdf (read)
- A004 IUID Marking Activity Report -MGMT-81804A .pdf (read)
- A003 GOV. PROPERTY ANNUAL INV REPORT MGMT-80441D.pdf (read)
- A002 CDM Production Report Monthly DI-PSSS-81995A.pdf (read)
- A001 (CAV) End Item Reporting DI-MGMT-81838 27-00013 .pdf: not summarized: open it on SAM.gov
- DD FORM 1653 Transportation Requirements.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Remanufacture the C-5 main landing gear trunnion bearing assembly (Part No. 4F23832-103A) from Government-furnished worn units: inspect, test and install a remanufactured spherical bearing in the existing housing
- Best estimated quantity: 64 EA in the basic period and 64 EA in each of four ordering periods; it is an estimate, not a guarantee
- Use new bearing balls only; no reworked balls on this contract
- Meet the C-5 original manufacturer acceptance tests and pass Government (DCMA, the Defense Contract Management Agency) final breakaway torque inspection
- Ship finished units by fast transportation; urgent (MICAP, aircraft-down) and surge orders are due within 150 calendar days of the order or receipt of repairable units, whichever is later, or 120 calendar days when order and units are already on hand
- Send monthly production reports and other required data deliverables through Wide Area WorkFlow (WAWF, the Government's electronic invoicing and receiving system)
- Track and report Government-furnished property in PIEE (the Procurement Integrated Enterprise Environment)
- Contract type
- Requirements contract (best estimated quantities, orders placed as needed)
- Period of performance
- 5 years: 1 basic year + 4 one-year ordering periods
- Place of performance
- Warner Robins, GA, USA per SAM.gov; the PWS says the services are performed at the contractor's facility
- Estimated value
- Not stated
- How they'll choose
- Lowest price technically acceptable. Technical factor (source qualification) is rated acceptable or unacceptable; the award goes to the lowest total evaluated price among acceptable offers.
- Offers due
- November 30, 2026, 5:00 PM Eastern (the amendment writes 5:00PM EST)
What they'll judge offers on
- Factor One, Technical (Source Qualification): verifiable proof that the firm is a currently approved source, or a complete SAR package approved by the Government's engineering authority before award; rated acceptable or unacceptable
- Factor Two, Price: total evaluated price (unit prices times best estimated quantities, basic period plus the four ordering periods)
What to include when you submit
- Sign and complete the solicitation form (Standard Form 1447) blocks the offeror must fill in
- Fill in unit prices in the Supplies or Services and Prices section; offered prices stay firm for 120 days
- Send a written technical proposal (Volume II) showing proof of current approved source status, or a complete SAR package that meets the Source Pre-Qualification Requirements and the performance work statement (PWS)
- Complete the representations and certifications in the System for Award Management (SAM)
- Acknowledge each amendment (Amendments 0001 and 0002)
- To get the bid set and technical data, be registered in the Joint Certification Program (JCP) and send your CAGE code to both contacts named in the notice, Alyssa Tanner and Karen Beckford
- Send questions by email only; answers are posted as a Q&A document on SAM.gov
Current contractor
No incumbent is named. The PWS says the contractor is already a qualified source of remanufacture, and refers to the last two contracts and about the last fifteen years of reworked balls, which points to an existing source, but names none.
Not in the notice text
- Parts of the solicitation were attached but only partly read: FA853826R0019.pdf, both amendment files and PWS.pdf had their middle sections left out, and A001 (CAV) End Item Reporting and DD FORM 1653 Transportation Requirements were attached but not read. Proposal instructions, clauses, the price schedule and delivery terms may be in them; check them on SAM.gov.
- How to submit the proposal (email address or portal) is not stated in the text read
- Unit price, unit of issue details beyond EA, and clause list for the line items were not readable
- Whether any Government estimate of total value exists is not stated
- Date of award and start of the basic period are not stated
More to check before you bid
- The notice names requirements:
- The notice mentions an approved or qualified source list. Only listed sources may be eligible, so check that your company or product is on it.
- The notice mentions export-controlled data. You may need a Joint Certification Program (DD Form 2345) approval to see the drawings.
- Service contracts usually set minimum pay rates (the Service Contract Act). Price the labor with the SCA price calculator.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 18, 2026
- Notice type
- Solicitation
- Office
- FA8538 AFSC PZAAB, Robins AFB, GA
- Product/service code
- J031 · Maint/Repair/Rebuild of Equipment – Bearings
- Business type
- Aircraft, ship & vehicle parts (FedReady's grouping, from NAICS 336413)
- Versions
2 versions have been posted, newest first.
- Nov 18, 2026 · Amendment 0001 (this version)Due Nov 30, 2026 (changed)
- Jul 29, 2026 · SolicitationDue Oct 27, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- Housing, Bearing UniDefense Logistics Agency (DLA) Aviation at Oklahoma City is buying a bearing housing unit ("HOUSING, BEARING UNI") under solicitation SPRTA1-27-Q-0031.
- Support, BearingDLA Aviation at Philadelphia is buying a bearing support (SUPPORT,BEARING) by request for quotation, solicitation SPRPA126QRB55, under emergency acquisition flexibilities.
- Pin, Trunnion
- C-5 Fire Suppression System RepairPresolicitation FD206027-00036 from the Department of the Air Force (FA8538 AFSC PZAAB), set aside for small businesses: depot-level repair (overhaul) of nine C-5 aircraft fire…
- A-10 Rotor and Stator BrakesThe Air Force plans a solicitation (presolicitation FD2020270061) for A-10 Rotor and Stator Brakes and says it cannot seek competition because the technology is proprietary to…