Solicitation
Child Development Center Playgrounds
Department of Defense · Department of the Air Force
AI summary Beta
This summary may miss requirements: 9 of 21 attachments weren't read (Attachment 2 - Playground 3D Cutsheets.pdf, Attachment 4 - Storm Sewer Pipe.pdf and 7 more). Check the attachments on SAM.gov.
The Air Force's 81st Contracting Squadron wants a contractor to design and build new playgrounds at the Keesler Air Force Base Child Development Center and School Age Care/Youth Programs center in Biloxi, Mississippi (request for quote, RFQ, FA301027Q0002). It is open to all businesses (unrestricted) and paid with non-appropriated funds (NAF), so FAR and DFARS rules don't apply. The base work is design (120 days) plus the preschool playground (60 days), with four optional playgrounds; the response due date is January 5, 2027, 10:00 AM local time.
Who can bid (6)
- Company experience: at least five years of playground construction and three years of playground maintenance From Attachment 15 - CDC Playground SOW.pdf
- An independent third-party Certified Playground Safety Inspector (NRPA certification, at least three years of child care inspection experience, not employed by the manufacturer or installer) From Attachment 16 - CDC Playground Technical Factors.pdf
- Factory-certified surfacing installer with at least five similar playground projects in the past three years, and a factory-certified equipment installer with at least three installs in the past three years
Show all 6Show fewer
- A licensed Professional Landscape Architect (PLA) to prepare the planting and shade plan
- Cybersecurity Maturity Model Certification (CMMC) Level 1 self-assessment, checked in the Supplier Performance Risk System (SPRS) From Solicitation - FA301027Q0002.pdf
- Bonding: submit bonding as the offer guarantee block specifies; item 12b gives 10 calendar days after award for performance and payment bonds From Solicitation - FA301027Q0002.pdf
How to submit: Email to the two contacts in block 7 (Zachary Willard and Tiffany Aultman) and 81CONS.PKA.Flight@us.af.mil. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (8)
From the version posted Nov 20, 2026.
- Serious: Many specialist credentials required with the quote. The technical pass/fail needs a separate independent safety inspector, certified installers, a landscape architect and a subcontractor roster, all documented up front.
- Serious: Bonds likely needed. Section L asks for bonding per the offer guarantee, and item 12b gives 10 days after award for bonds; confirm on the SF 1442 which bonds are required. From Solicitation - FA301027Q0002.pdf
- Worth checking: Base pass names due November 30, 2026. To attend the December 9, 2026, site visit, each attendee's full name must reach the contract specialist by November 30, 2026, at 12:00 P.M. CST for a background check. From Solicitation - FA301027Q0002.pdf
Show all 8Show fewer
- Worth checking: Site visit on December 9, 2026. The organized site visit is December 9, 2026, at 9:00 AM CST at Building 4705, 508 L Street; it isn't called mandatory. From Solicitation - FA301027Q0002.pdf
- Worth checking: Option playgrounds depend on funding. Award is all, some or none, so a bidder may win only the design and preschool playground; price each option so it stands alone. From Solicitation - FA301027Q0002.pdf
- Minor: Fence curb width differs between documents. The SOW calls for a 6-inch-wide concrete mow strip under the fence, while the technical factors call for posts and fabric set 3 inches into a 12-inch-wide curb; ask which governs. From Attachment 15 - CDC Playground SOW.pdf
- Minor: No loud work during nap time. The child care center stays open, and heavy machinery and loud work are prohibited during nap time, typically 12:00 PM to 2:00 PM, which slows the schedule. From Attachment 16 - CDC Playground Technical Factors.pdf
- Minor: Price kept out of the technical volume. Any price or cost in Part II can make the quote unacceptable. From Solicitation - FA301027Q0002.pdf
Read from the notice and 12 attachments. 9 of 21 not read. Show which files.
- Solicitation - FA301027Q0002.pdf (read)
- Attachment 7 - UFGS Standard Specifications.pdf (read)
- Attachment 12 - Specifications 18-1083 Replace Exterior Fencing w CDC Requirements.pdf (read)
- Attachment 15 - CDC Playground SOW.pdf (read)
- Attachment 1 - NAF Standard and Construction Clauses.pdf (read)
- Attachment 3 - Existing Utilities.pdf (read)
- Attachment 5 - GFE List Playground Equipment.pdf (read)
- Attachment 8 - UFC 4 470 14 - Child Development Centers.pdf (read)
- Attachment 13 - GFE List Musical Equipment.pdf (read)
- Attachment 14 - LSI Trash Receptacle.pdf (read)
- Attachment 16 - CDC Playground Technical Factors.pdf (read)
- Attachment L-01 Past Performance Reference List.pdf (read)
- Attachment 2 - Playground 3D Cutsheets.pdf: not summarized: open it on SAM.gov
- Attachment 4 - Storm Sewer Pipe.pdf: not summarized: open it on SAM.gov
- Attachment 11 - Playground Equipment Areas.pdf: not summarized: open it on SAM.gov
- Attachment 6 - Construction Document Drawings.pdf: not summarized: open it on SAM.gov
- Attachment 9 - Civil Drawings Playground - As Built.pdf: not summarized: open it on SAM.gov
- Attachment 10 - Drawings - Topo.pdf: not summarized: open it on SAM.gov
- Attachment 18 - Submittal Prodcedures.pdf: not summarized: open it on SAM.gov
- Attachmen L-02 Past Performance Questionnaire.pdf: not summarized: open it on SAM.gov
- Attachment 17 - Wage Determination.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- 100% design of all playgrounds, including the four optional areas (CLIN 0001: contract line item, one priced line), capped at 10 percent of construction cost
- Build the core preschool playground and install the Government-furnished play equipment (CLIN 0002)
- Options: infant (CLIN 0003), pretoddler (0004), toddler (0005) and school-age/youth playground with basketball court (0006)
- Site and topographical surveys, grading and drainage, concrete, poured-in-place rubber surfacing, fencing, shade structures, sidewalks and evacuation pads
- Demolition of existing equipment and surfacing, storage shed pads and relocation, sod and site restoration
- A quality control plan with a final safety audit by an independent Certified Playground Safety Inspector (CPSI)
- Work around the operating child care center: separation fencing, no loud work during nap time, and safe haul routes
- Contract type
- Firm-fixed-price (FFP: one set price, whatever the work ends up costing) design-build contract, NAF-funded
- Period of performance
- Base: 180 calendar days (120 days design + 60 days preschool playground); options: infant 45, pretoddler 45, toddler 45, school-age/youth 75 calendar days
- Place of performance
- Keesler AFB, MS: Child Development Center, 604 J St, and SAC/YP, 603 J St, Keesler AFB, MS 39534
- Estimated value
- Not stated
- How they'll choose
- Lowest price technically acceptable (LPTA): the lowest-priced quote that passes technical and past performance wins
- Offers due
- January 5, 2027, 10:00 AM local time (CST)
- How to submit
- Email to the two contacts in block 7 (Zachary Willard and Tiffany Aultman) and 81CONS.PKA.Flight@us.af.mil
- Page limits
- Whole quote: no more than 150MB; each scanned file no more than 50MB
What they'll judge offers on
- Price: ranked by total evaluated price (TEP), awarded on an all, some or none basis
- Technical (pass/fail per Attachment 16): (A) schedule, phasing and security, (B) equipment compliance and age separation, (C) impact surfacing, (D) fencing and gates, (E) non-toxic landscaping and shade, (F) grading and drainage, (G) quality control and safety audit, (H) site restoration; plus key personnel credentials
- Past performance (acceptable/unacceptable): recent (last five years) and relevant projects
What to include when you submit
- Send three separate files: Part I Price, Part II Technical, Part III Past Performance; all but price as searchable PDF, no zipped or password-protected files
- Part I: price every CLIN in Section B, complete and sign Standard Form 1442 (SF 1442: the construction offer form), and acknowledge amendments
- Part I: submit bonding as specified in the offer guarantee block, and keep your SAM.gov representations and certifications current
- Keep all price information out of the technical volume, or it may be found unacceptable
- Part II: a technical narrative covering sub-sections A through H of Attachment 16, including a Gantt-style progress schedule
- Part II: manufacturer cut sheets and IPEMA certifications for all play equipment, and lab test reports for the surfacing (ASTM F1292 / F355)
- Part II: proof of credentials for the independent CPSI, certified surfacing installer, licensed landscape architect and certified equipment installer, plus a roster of all trade subcontractors and a signed base-access and background-check compliance statement
- Part III: a Past Performance Reference List (Attachment L-01) of no more than five recent, relevant contracts; send questionnaires (Attachment L-02) to references, who return them directly to the contract specialist
After award, you must have
- All on-site staff and subcontractor workers must clear base access (DBIDS) and Air Force child-care background checks
Not in the notice text
- Several files are attached but not read here: the construction drawings, as-built civil drawings, topo drawings, submittal procedures, past performance questionnaire and wage determination (Attachment 17), plus scanned cut sheets, storm sewer and equipment-area files; the middles of the solicitation, SOW, specifications and clauses were also left out. Check them on SAM.gov.
- Which wage rule applies: a wage determination (Attachment 17) is attached but not read here.
- Whether an offer guarantee (bid bond) is required can't be read from the form's boxes; check block 13b on SAM.gov.
- Required insurance amounts are not in the parts read.
- No estimated value or budget is given.
- Whether the site visit is mandatory is not stated.
- No incumbent is named.
More to check before you bid
- The AI summary also reads the notice as naming requirements:
- The AI summary's reading of the notice and its attachments says a bidder needs: CMMC certification. The summary's list is under Who can bid; check it in the notice before you bid.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 20, 2026
- Notice type
- Solicitation
- Office
- FA3010 81 CONS, Keesler AFB, MS
- Product/service code
- Y1PA · Construction of Recreation Facilities (Non-Building)
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 238990)