Solicitation
Mississippi River, New Orleans Harbor Cutterhead Dredge No. 1-2025
Department of Defense · Department of the Army
AI summary Beta
The notice looks incomplete: Bid opening date and time (to be set by a future amendment). Check the attachments on SAM.gov.
The Army Corps of Engineers New Orleans District wants a contractor to supply one fully crewed hydraulic pipeline cutterhead dredge (a stationary dredge with a rotating cutter that pumps sediment through a pipeline) for the New Orleans Harbor reach of the Mississippi River and the Algiers, Harvey and Inner Harbor lock forebays of the Gulf Intracoastal Waterway. It is a fixed-price sealed bid in the $5 million to $10 million range, with 31 to 56 contract days for the base dredging depending on dredge size. The bid opening date will be set by a later amendment.
Who can bid (8)
- Dredge proven to meet the minimum production rate for the region, shown by 30 days of performance on a single contract within three years before bid opening From W912P825BA009 Solicitation.pdf
- Dredge able to operate in high river stages From W912P825BA009 Solicitation.pdf
- Completed Cutterhead Dredge and Attendant Plant Data Sheet showing the dredge meets the equipment requirements, plus a pre-award survey From W912P825BA009 Solicitation.pdf
Show all 8Show fewer
- Active SAM registration From W912P825BA009 Solicitation.pdf
- Performance and payment bonds from the winning bidder after award From W912P825BA009 Solicitation.pdf
- Dredge and plant crewed, in operating status and not committed to other work that would delay this job From W912P825BA009 Solicitation.pdf
- Work done to the Army Corps safety manual EM 385-1-1, including Chapter 19 on floating plant From W912P825BA009 Solicitation.pdf
- No set-aside; small business size standard shown as $37,000,000 for NAICS 237990 From W912P825BA009 Solicitation.pdf
How to submit: Sealed bid (IFB) to the Army Corps of Engineers New Orleans District; delivery address and opening date are not legible in the form text, questions go to the contract specialists listed in the notice. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (10)
From the version posted Apr 22, 2025.
- Serious: Needs a specialized cutterhead dredge with proven output. Only firms with a qualifying dredge (24 inch or larger discharge) that has already run at the required production rate can bid, so most small businesses would need to partner with a dredge owner.
- Serious: 30-day production rate history within three years. The dredge must have a documented 30-day run at or above the minimum output on one contract in the last three years, or the bidder is found non-responsible. From W912P825BA009 Solicitation.pdf
- Worth checking: Pre-award survey and plant inspection. If the apparent low bidder's dredge fails the data sheet review or the inspection, it is dropped and the Government moves to the next bidder, so you can lose after bidding low. From W912P825BA009 Solicitation.pdf
Show all 10Show fewer
- Worth checking: Bonds and possible bid guarantee. Performance and payment bonds are required after award, and a bid bond form is in the package, which takes surety backing on a multi-million dollar job. From W912P825BA009 Solicitation.pdf
- Worth checking: Start dredging within 120 hours of Notice to Proceed. The dredge has to be delivered and working very quickly after bonds are accepted. From W912P825BA009 Solicitation.pdf
- Worth checking: Bidder carries production and site-condition risk. The Government's production rates are conservative estimates for variable shoaling, and bidders must judge actual dredging conditions themselves. From W912P825BA009 Solicitation.pdf
- Worth checking: Non-responsive bid traps. Skipping any bid item or choosing the wrong bid lot gets the whole bid thrown out, and unreasonable or unbalanced prices can be rejected. From W912P825BA009 Solicitation.pdf
- Worth checking: Davis-Bacon wages likely apply (a general rule). This is the general rule, not something the notice says: federal construction over $2,000 in the U.S. pays at least the Davis-Bacon wage rates in the wage determination attached to the solicitation. This summary doesn't name one: find it on SAM.gov and price your labor from it.
- Minor: Bid date unclear. SAM.gov shows a 2027 response date but the solicitation says the bid opening will be set by a future amendment, so watch for amendments.
- Minor: Site visit urged. Offerors are expected to inspect the site, which means travel to New Orleans before bidding. From W912P825BA009 Solicitation.pdf
Read from the notice and 1 attachment. Show which files.
- W912P825BA009 Solicitation.pdf (read)
Full summary
What they want
- Provide one fully crewed, fully equipped hydraulic pipeline cutterhead dredge for the contract period
- Dredge shoaling in the New Orleans Harbor reach and the Algiers, Harvey and Inner Harbor Navigation Canal lock forebays; base dredging is priced per pay-time hour (343 to 860 hours depending on bid lot)
- Mobilize and demobilize the dredge (one lump-sum job) and start dredging within 120 hours of Notice to Proceed
- Option items the Government may or may not use: additional dredging hours and dredge towing service (priced per mile, 30 miles)
- Submit a Cutterhead Dredge and Attendant Plant Data Sheet and pass pre-award survey and plant inspection
- Show the dredge has met the minimum production rate for 30 days on one contract within the past three years
- Work to EM 385-1-1 safety rules and finish required submittals and meetings before physical work begins
- Contract type
- Firm-fixed-price, sealed bid (IFB), unit prices per hour plus lump-sum mobilization and per-mile towing, with option items
- Period of performance
- About 31 to 56 contract days for the base dredging item depending on bid lot, plus the same number of days again if the option dredging item is fully exercised; dredge must start within 120 hours after Notice to Proceed
- Place of performance
- New Orleans Harbor reach of the Mississippi River and adjacent lock forebays of the Gulf Intracoastal Waterway (Algiers, Harvey, Inner Harbor Navigation Canal), Orleans and Jefferson Parishes, Louisiana
- Estimated value
- Magnitude of construction stated as between $5,000,000 and $10,000,000
- How they'll choose
- Lowest-priced responsive bid from a responsible bidder, regardless of which of the five bid lots (dredge classes) is used; the apparent low bidder must also pass a pre-award survey of its dredge
- Offers due
- SAM.gov lists Apr 21, 2027 11:00 AM Central, but the solicitation says the bid opening date will be set by a future amendment
- How to submit
- Sealed bid (IFB) to the Army Corps of Engineers New Orleans District; delivery address and opening date are not legible in the form text, questions go to the contract specialists listed in the notice
What they'll judge offers on
- Price (lowest total of base and option items)
- Responsiveness (bid on all items, correct bid lot)
- Responsibility (dredge data sheet, dredge meets equipment requirements, proven production rate, capital and experience)
What to include when you submit
- Bid on one bid lot only, chosen by the smallest inside diameter among the main pump discharge, submerged pump discharge, booster pump discharge and discharge pipeline, and by whether a submerged pump is used
- Price every item including the option items; leaving out both unit price and extended amount makes the bid non-responsive
- Include the completed Cutterhead Dredge and Attendant Plant Data Sheet (if missing, the apparent low bidder gets 24 hours after bid opening to provide it)
- Complete the SF 1442 and the representations and certifications (SAM reps and certs can be used)
- A bid bond form (SF 24) is part of the package, but the offer guarantee blank on the SF 1442 did not come through, so confirm the requirement in the full solicitation
- Acknowledge any amendments
Current contractor
No incumbent is named. The Algiers, Harvey and Inner Harbor lock forebay section says dredging occurs annually or near annually in this region and refers bidders to the contract specialist for information on previous dredging contracts.
Not in the notice text
- Bid opening date and time (to be set by a future amendment)
- Whether an offer (bid) guarantee is required and its amount; the SF 1442 blank and the bid bond form details did not come through
- Exact bond deadline, bid acceptance period and performance period entries on the SF 1442
- Contents of the middle of the solicitation, which was not provided (about 329,000 characters, including the main Hydraulic Dredging section's equipment requirements, payment terms and the New Orleans Harbor region details)
- Whether the National Dredging Quality Management certification is required of the contractor (section listed, requirement text not read)
- Whether a site visit is scheduled
- Hours of work and prior contract prices
Notice details
Notice type, codes, versions and files
- Posted
- Apr 22, 2025
- Notice type
- Solicitation
- Office
- W07V ENDIST New Orleans, LA
- Product/service code
- Y1KF · Construction of Dredging Facilities
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 237990)
- Related notices
Other notices that name this solicitation, or that this one names.
- Mississippi River, New Orleans Harbor Cutterhead Dredge No. 1-2025 · W912P825BA002Posted later Apr 30, 2025 · Due May 11, 2027
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation
Full notice text from SAM.gov
Similar open opportunities
- Mississippi River, Baton Rouge to Gulf of Mexico, Southwest Pass Maintenance Dredging, Non-Continuous Mile 6.0 AHP to Mile 19.5 BHP, Cutterhead Dredge No. 2-2025 (OM25276)The Army Corps of Engineers New Orleans District plans to solicit a fully crewed cutterhead dredge to do maintenance dredging in the Mississippi River Southwest Pass.
- Mississippi River, Baton Rouge to Gulf of Mexico, Southwest Pass Maintenance Dredging, Non-Continuous Mile 6.0 AHP to Mile 19.5 BHP, Cutterhead Dredge No. 1-2025 (OM25275)The U.S. Army Corps of Engineers New Orleans District wants one fully crewed cutterhead dredge for maintenance dredging of the Mississippi River Southwest Pass in Plaquemines…
- Mississippi River, Baton Rouge to Gulf of Mexico, Southwest Pass Maintenance Dredging, Non-Continuous Mile 6.0 AHP to Mile 19.5 BHP, Cutterhead Dredge No. 3-2025 (OM25277)The Army Corps of Engineers New Orleans District wants one fully crewed cutterhead dredge (30 inch or larger discharge) to maintenance-dredge the Mississippi River at Southwest…
- Mississippi River, Baton Rouge to Gulf of Mexico, Southwest Pass Maintenance Dredging, Non-Continuous Mile 6.0 AHP to Mile 19.5 BHP, Cutterhead Dredge No. 4-2025 (OM25278)The U.S. Army Corps of Engineers New Orleans District wants a contractor to supply one fully crewed cutterhead dredge for maintenance dredging of the Mississippi River Southwest…
- Mississippi River, Baton Rouge to Gulf of Mexico, Southwest Pass Hopper Dredge Contract No. 2-2025 (OM25002)The Army Corps of Engineers New Orleans District plans to buy one fully crewed, self-propelled trailing suction hopper dredge to work in the Mississippi River Southwest Pass and…