AI summary Beta
This summary may miss requirements: 14 of 26 attachments weren't read (Turnout_Site_Tour_Sign-in_Sheet_26_AUG_2026_0001.pdf, NGWSP_-_FCWR_Turnout_Buildings_Prebid__Site_Visit_-26_AUG_2026_0001.pdf and 12 more). Check the attachments on SAM.gov.
The Department of the Interior (Reclamation Contracting Activity), for the Bureau of Reclamation's Four Corners Construction Office, is taking sealed bids under invitation for bids (IFB) 140R4026B0002 to build seven water turnout buildings for the Navajo-Gallup Water Supply Project in northwest New Mexico. The response due date is December 1, 2026, 10:00 AM Mountain, and award goes to the lowest priced compliant bidder. The project magnitude is $18,000,000.00 to $23,000,000.00, and bidders must give a bid guarantee and later bonds.
Who can bid
- Offer guarantee (bid guarantee) with the bid, in the appropriate form. From Sol_140R4026B0002_Amd_0005.pdf
- Small business subcontracting plan from the apparent low bidder, if the contracting officer asks, with minimum goals including 45.87 percent small businesses. From IFB_140R4026B0002_NGWSP_Turnout_Buildings.pdf
How to submit: Email to the two contracting staff named in the IFB, mail, or hand delivery to the Four Corners Construction Office, 1235 La Plata Highway, Farmington, NM 87401. Bids are publicly opened there, or on Microsoft Teams.. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (8)
From the version posted Nov 9, 2026.
- Serious: Bid guarantee, then performance and payment bonds within 21 days. On a project of $18,000,000.00 to $23,000,000.00, you need a surety able to issue the bid guarantee and both bonds. From Questions___Answers_0002.pdf
- Worth checking: Contractor designs the precast concrete buildings and foundations. The contractor must do the soil investigation and the building and foundation design, and only precast concrete is accepted, so you need a design engineer and a precast supplier. From Sol_140R4026B0002_Amd_0004.pdf
- Worth checking: Indian Preference clauses listed in the IFB. The table of contents lists Indian Preference and an Indian Preference Program. Their text wasn't read, so check what they require of bidders and subcontractors. From IFB_140R4026B0002_NGWSP_Turnout_Buildings.pdf
Show all 8Show fewer
- Worth checking: Strict stormwater and cultural resource rules. A stormwater pollution prevention plan (SWPPP) is required, and finds of archaeological items can bring a temporary stop-work order and added time or cost. From Questions___Answers_0002.pdf
- Worth checking: Full-time licensed land survey support and quantity surveys. Survey notes and quantity surveys must go with each monthly invoice; missing them has caused payment disputes on past Reclamation jobs. From IFB_140R4026B0002_NGWSP_Turnout_Buildings.pdf
- Minor: Taxes kept separate from the bid price. New Mexico Gross Receipts Tax and Navajo Nation tax are estimated and reimbursed on invoices, and need proof of payment, so plan the paperwork. From IFB_140R4026B0002_NGWSP_Turnout_Buildings.pdf
- Minor: Response due date moved to December 1, 2026. Amendment 0005 moved the bid due and opening date from November 10, 2026 to December 1, 2026. The IFB's page 97 still shows November 12, 2026 for opening, so use the amended date. From Sol_140R4026B0002_Amd_0005.pdf
- Minor: Specifications and drawings revised through Amendment 0006. Amendment 0006 revises three specification sections and one drawing, and earlier amendments changed the price schedule, so check you have the current set. From Sol_140R4026B0002_Amd_0006.pdf
Read from the notice and 12 attachments. 14 of 26 not read. Show which files.
- Sol_140R4026B0002_Amd_0006.pdf (read)
- Sol_140R4026B0002_Amd_0005.pdf (read)
- Sol_140R4026B0002_Amd_0004.pdf (read)
- Sol_140R4026B0002_Amd_0003.pdf (read)
- Sol_140R4026B0002_Amd_0002.pdf (read)
- Sol_140R4026B0002_Amd_0001.pdf (read)
- Sol_140R4026B0002.pdf (read)
- IFB_140R4026B0002_NGWSP_Turnout_Buildings.pdf (read)
- 140R4026B0002_-_Attachment_1_1_00_00_01__Specifications__20261009_0002.pdf (read)
- _1_Attachment_00_00_01_NGWSP_TURNOUT_BLDGS_Specifications_20260707.pdf (read)
- Questions___Answers_AMD_0006_0006.pdf (read)
- Questions___Answers_0002.pdf (read)
- Turnout_Site_Tour_Sign-in_Sheet_26_AUG_2026_0001.pdf: not summarized: open it on SAM.gov
- NGWSP_-_FCWR_Turnout_Buildings_Prebid__Site_Visit_-26_AUG_2026_0001.pdf: not summarized: open it on SAM.gov
- 140R4026B0002_Attachment__1_2_00_00_01_Specs_AMD_No__006_20261106_0006.pdf: not summarized: open it on SAM.gov
- 140R4026B0002_-__Attachment_3_1_00_00_02A_Test_Pit_Log_TPTB-25-2_20261008_0002.pdf: not summarized: open it on SAM.gov
- _4_Attachment_Small_Business_Subcontracting_Plan.docx: not summarized: open it on SAM.gov
- 140R4026B0002_Attachment__2_2_Drawing_1695-D-62558_20261106_0006.pdf: not summarized: open it on SAM.gov
- Attachment__8_WD_NM20260024_Building_-_McKinley_County__NM_0002.pdf: not summarized: open it on SAM.gov
- 140R4026B0002_-_Attachment_2_1_00_00_02_-Drawings_-20261009_0002.pdf: not summarized: open it on SAM.gov
- Attachment__7_WD_NM20260011_Heavy_-_McKinley_County__NM_0002.pdf: not summarized: open it on SAM.gov
- 140R4026B0002_-_Attachment_3_1_00_00_02B_Corrosivity_Report_NGWSP_Turnout_Bldgs_20261009_0002.pdf: not summarized: open it on SAM.gov
- _2_Attachment_00_00_02_Drawings_Combined_34x22_20260707.pdf: not summarized: open it on SAM.gov
- _3_Attachment_00_00_02A_-_Geology_Drawings_04032026.pdf: not summarized: open it on SAM.gov
- _5_Attachment_WD_NM20260040_Heavy_-_San_Juan_County__NM.pdf: not summarized: open it on SAM.gov
- _6_Attachment_WD_NM20260046_Building_-_San_Juan_County__NM.pdf: not summarized: open it on SAM.gov
Full summary
What they want
- Contract line item number (CLIN) 00010: QTY 1, Unit of Measure AU (Activity Unit), firm-fixed-price, to build a potable water delivery turnout building and improvements at each of 7 sites between Gallup and Shiprock, New Mexico.
- Sitework at each site: buried piping, valves and accessories, steel fencing with gate, gravel surfacing, drainage, and access roads at Coyote Canyon and Window Rock only.
- Steel piping connections to the existing steel supply (lateral) pipe and distribution (delivery) pipe, with buried thrust blocks (concrete anchors that hold pipe in place).
- Precast concrete building and foundation at each site, including geotechnical (soil) investigation, foundation design and building design by the contractor.
- Inside each building: exposed piping and valves, heating and cooling, electrical, controls, instrumentation and security. Electrical work starts at the meter socket.
- Fiber-optic cable from the existing lateral alignment to each building, and controls integration with the existing San Juan Lateral SCADA system (remote monitoring and control).
- Flush, test and disinfect the installed piping, including furnishing and disposing of the water, plus commissioning.
- Full-time safety and quality control representatives, survey support with quantity surveys, and as-built drawings in .dwg format.
- Contract type
- Firm-fixed-price, sealed bid (invitation for bids)
- Period of performance
- 12/16/2026 to 04/16/2029 as written on the solicitation; a question answer also refers to an 831-day performance period
- Place of performance
- Seven sites in northwest New Mexico between Gallup and Shiprock: Sanostee, Newcomb and Naschitti in San Juan County; BBN9, Coyote Canyon, Rock Springs and Window Rock in McKinley County
- Estimated value
- Magnitude between $18,000,000.00 and $23,000,000.00
- How they'll choose
- Sealed bid: award to the lowest priced bid from a responsible bidder that complies with the solicitation and presents proof of the bid guarantee; pricing is checked for balance and for being fair and reasonable
- Offers due
- December 1, 2026, 10:00 AM Mountain
- How to submit
- Email to the two contracting staff named in the IFB, mail, or hand delivery to the Four Corners Construction Office, 1235 La Plata Highway, Farmington, NM 87401. Bids are publicly opened there, or on Microsoft Teams.
What they'll judge offers on
- Total bid price: price schedules 1 through 7, not counting New Mexico Gross Receipts Tax or Navajo Nation tax amounts
What to include when you submit
- Fill out the price schedule (Schedule B) in total, using the updated Schedule B from Amendment 0002, or the bid cannot be considered for award.
- Make sure the total bid price line is filled in on page 25 of 96.
- Give New Mexico Gross Receipts Tax and Navajo Nation tax as estimates; these are reimbursed on invoices.
- Acknowledge Amendments 0001 through 0006 before the due time, on the SF 30 form, on the offer, or by letter or electronic message naming the solicitation and amendment numbers.
- Include the offer guarantee (bid bond or other guarantee) as the solicitation requires; electronic bonds are accepted.
- Confirm your bid was received by the due time; that is the bidder's responsibility whether sent by email, mail or in person.
- If asked as the apparent low bidder, send a small business subcontracting plan.
After award, you must have
- Performance and payment bonds within 21 days after award, the period the standard form SF 1442 gives. Earlier bonding documents are accepted. From Questions___Answers_0002.pdf:
The 21-day period specified on the SF 1442 takes priority.
- Survey work directed by a registered professional land surveyor licensed in New Mexico, where the work is done. From IFB_140R4026B0002_NGWSP_Turnout_Buildings.pdf:
…under the direction of a registered professional land surveyor licensed in the state where the work is being completed…
- Full-time safety representative, quality control representative and qualified survey personnel on the job. From Sol_140R4026B0002.pdf:
Full time safety representative and quality control representative…
Not in the notice text
- Much of the solicitation is attached but not read: the middle of the IFB (price schedule, Indian Preference clauses, liquidated damages, clauses), the full specifications, drawings, test pit log, corrosivity report and wage determinations are on SAM.gov.
- The set-aside is not stated on SAM.gov or in the text read.
- The amount of the bid guarantee and the bond amounts are not in the text read.
- The contract completion time in calendar days after notice to proceed is not clear from the text read; documents give 12/16/2026 to 04/16/2029 and an 831-day performance period.
- Wage rules: Department of Labor wage determinations (Heavy and Building) for San Juan and McKinley Counties are attached but not read.
- Whether the August 26, 2026 site visit was required is not stated; the sign-in sheet and slides are attached but not read.
Notice details
Notice type, codes, versions and files
- Posted
- Nov 9, 2026
- Notice type
- Solicitation
- Office
- Reclamation Contracting Activity, Denver, CO
- Product/service code
- Y1NE · Construction of Water Supply Facilities
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 237110)
- Versions
7 versions have been posted, newest first.
- Nov 9, 2026 · Amendment 0006 (this version)Due Dec 1, 2026
- Nov 4, 2026 · Amendment 0005Due Dec 1, 2026 (changed)
- Oct 27, 2026 · Amendment 0004Due Nov 10, 2026
- Oct 13, 2026 · Amendment 0003Due Nov 10, 2026
- Oct 13, 2026 · Amendment 0002Due Nov 10, 2026
- Aug 31, 2026 · Amendment 0001Due Nov 10, 2026
- Aug 13, 2026 · SolicitationDue Nov 10, 2026
- Attachments
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
Terms on this notice: Solicitation