Dike B Generator Installation, Mansfield Hollow Dam, Mansfield Center, CT
Department of Defense · Department of the Army
AI summaryThe U.S. Army Corps of Engineers New England District wants a small business to build and commission a propane-powered 15-kilowatt (kW) generator system for the Dike B sluice gate operator at Mansfield Hollow Dam, Mansfield Center, CT (solicitation W912WJ27QA001). Only small businesses may send quotes, and the response due date is November 5, 2026, 5:00 PM Eastern. The work covers a concrete pad, security fence, generator, propane tank and wiring, to be finished within 300 days of the notice to proceed (the Government's start-work order). More in the summary
AI summary Beta
The notice looks incomplete: About 14,000 characters in the middle of the solicitation PDF (part of the contract clauses in Section I) weren't read, so some contract clauses may be missing from this brief. Check the attachments on SAM.gov.
The U.S. Army Corps of Engineers New England District wants a small business to build and commission a propane-powered 15-kilowatt (kW) generator system for the Dike B sluice gate operator at Mansfield Hollow Dam, Mansfield Center, CT (solicitation W912WJ27QA001). Only small businesses may send quotes, and the response due date is November 5, 2026, 5:00 PM Eastern. The work covers a concrete pad, security fence, generator, propane tank and wiring, to be finished within 300 days of the notice to proceed (the Government's start-work order).
Who can bid (5)
- Small business under NAICS 238290, the small business size standard of $22 million; this is a total small business set-aside.
- Active SAM.gov registration at the time the quote is submitted.
- A licensed electrician and a licensed plumber must do the electrical and plumbing work; electrician and plumber licenses are also listed as preconstruction submittals.
Show all 5Show fewer
- If asked before award, a Letter of Bond Ability from a surety listed on U.S. Treasury Circular 570, stating your single and aggregate bond limits.
- Comply with Federal Acquisition Regulation (FAR) clause 52.240-93, Basic Safeguarding of Covered Contractor Information Systems; no cybersecurity assessment is required.
How to submit: Email the quote to the Contract Specialist (Alicia.N.LaCrosse@usace.army.mil), by the closing date and time. What to include is under Full summary below. Check the solicitation's instructions on SAM.gov.
Things to watch (13)
From the version posted Oct 22, 2026.
- Serious: Small business set-aside only. Only small businesses that meet the $22 million size standard for the North American Industry Classification System (NAICS) code 238290 can bid; larger firms cannot.
- Serious: Missing paperwork makes a quote non-responsive. A signed Standard Form 18 (SF 18, the request for quotation form), signed amendments, a fully priced bid schedule, and the completed Solicitation Survey are all required, or the quote is removed from consideration.
- Serious: Payment and performance bonds required. Bonds equal to 100% of the contract price are due within 10 days after award, and the Government may ask for a Letter of Bond Ability before award.
Show all 13Show fewer
- Serious: Licensed electrician and plumber required. The firm needs a licensed electrician and licensed plumber (or subcontractors with a signed teaming arrangement), and the propane system must be tested by a licensed propane technician.
- Serious: Active SAM.gov registration required. Quotes from firms without an active registration in SAM.gov (the federal contractor database) are rejected, and registration takes about three weeks. Check a SAM.gov registration.
- Worth checking: Section L and Section M disagree on $0 or NSP prices. Section L allows $0 or Not Separately Priced (NSP) entries on a bid schedule, but Section M rejects them; ask the contract specialist and price every line.
- Worth checking: Site visit strongly recommended, none scheduled. No site visit dates are posted; contact the technical point of contact to arrange one, and no visits are allowed after the solicitation closes. Amendment 0001 adds a second technical contact.
- Worth checking: Date passed (May 18, 2026): Davis-Bacon construction wage rules apply. The project follows federal construction wage rules (Davis-Bacon) through wage determination CT20260025 (modification 2, revised May 18, 2026), so workers must be paid at least the listed rates.
- Worth checking: Past performance must be the prime's own. Only the prime contractor's past performance counts unless a signed teaming arrangement from the subcontractor is submitted.
- Worth checking: Remote site with no utilities. The site has no available utilities, and the existing 230 feet of conduit holds no wire, so wiring must be pulled through it.
- Minor: 300-day schedule and limited work hours. Work runs 300 days from the notice to proceed, Monday to Friday 7:00 AM to 3:30 PM, and field work cannot start until submittals are accepted.
- Minor: Possible quote verification before award. The Government may ask questions after the solicitation closes, and late or incomplete answers can remove a quote from consideration.
- Minor: Firm fixed price only. Quotes with a sliding price scale or escalation for any contingency are not accepted, so price in material and fuel risk up front.
Read from the notice and 4 attachments. Show which files.
- Solicitation W912WJ27QA001.pdf (read)
- Amendment W912WJ27QA001-0001.pdf (read)
- Attachments 27QA001.pdf (read)
- Solicitation Survey 27QA001.pdf (read)
Full summary
What they want
- Prepare the site at Dike B: stake the layout, excavate, and compact a 30 ft by 30 ft gravel platform at least 6 inches deep; trench and lay underground PVC (plastic) conduit.
- Pour a 20 ft by 20 ft reinforced concrete pad (4,000 pounds per square inch, at least 6 inches thick, 2 inches above grade) and let it cure at least 7 calendar days before setting equipment.
- Install a 15 kW, three-phase 277/480 volt, liquid-cooled, propane-fueled standalone generator in a locking, sound-attenuated enclosure, plus a 120-gallon propane tank, piping, and a lockable fuel shutoff valve; fill the tank.
- Build a 24 ft by 24 ft by 8 ft black chain-link security fence with three strands of barbed wire and a 96-inch double-swing gate, with all fence metal grounded.
- Install pedestal panelboards (breaker boxes), a step-down transformer, wiring through the existing conduit of about 230 feet, two 10-foot light poles with LED floodlights, and two weatherproof ground-fault circuit interrupter (GFCI) outlets; connect to the existing Flowserve/Limitorque sluice gate operator. Amendment 0001 allows independently supported light poles with concrete foundations.
- Test and commission: propane pressure test certified by a licensed propane technician, manufacturer-approved generator commissioning, and a live full-load test of the sluice gate operator on generator power.
- Close out: at least one on-site training session by a factory-authorized representative, two hard copies and one PDF of the operations and maintenance manual, and electrical as-built drawings of the generator pad.
- Safety paperwork before field work: Accident Prevention Plan (ENG Form 6293), activity hazard analyses, a designated Level 3 Site Safety and Health Officer (SSHO), and product data, all due within 21 days of the notice to proceed.
- Contract type
- Firm-fixed-price construction; the Government will award a purchase order (only firm fixed price quotes are evaluated)
- Period of performance
- 300 days from Notice to Proceed; work allowed Monday to Friday, 7:00 AM to 3:30 PM
- Place of performance
- Mansfield Hollow Dam, Dike B, Mansfield Center, CT
- Estimated value
- Not stated
- How they'll choose
- Best value: the Government may compare quotes to each other and award a purchase order to the responsible vendor whose quote is most advantageous, price and other factors considered. The weight of each factor isn't stated.
- Offers due
- November 5, 2026, 5:00 PM Eastern
- How to submit
- Email the quote to the Contract Specialist (Alicia.N.LaCrosse@usace.army.mil), by the closing date and time
What they'll judge offers on
- Technical: the Government reviews key personnel, subcontractor teaming arrangements, documents and certifications, using the information in the Solicitation Survey
- Price: responsive quotes are ranked from lowest to highest price, including options; every bid schedule line must be priced, and $0 or Not Separately Priced entries are rejected under Section M
- Past Performance: successful contracts within the past three years, with relevant work rated higher; no past performance is rated neutral; only the prime's history counts unless a teaming arrangement is submitted
What to include when you submit
- Fill in the whole bid schedule: Phase 1; Phase 2 (gravel foundation, concrete pad); Phase 3 (generator, propane tank, fencing); Phase 4; Phase 5. Each line is priced as JOB, QTY 1. Blank lines make the quote non-responsive.
- Sign the SF 18 in block 14.
- Return signed copies of all material amendments (SF 30, the amendment form), including Amendment 0001.
- Complete and return the Solicitation Survey issued for this solicitation: years of experience, any terminated work, subcontractor name and contact, licenses, and three past performance references.
- Past performance: experience must be completed within the past three years; give the prime's own contracts. Subcontractor experience counts only with a signed teaming arrangement from the subcontractor.
- Name any subcontractor with contact information; the survey rejects 'to be determined' for subcontractors.
- Attach electrician and plumber license documents, as the survey marks them applicable; plans for any certificates not yet held must name the course, provider, dates, and a link.
- Give your unique entity identifier (UEI) and CAGE code (Commercial and Government Entity code), and keep your SAM.gov registration active; representations and certifications are completed in SAM.gov.
- Price as a single firm fixed price; a sliding scale or escalation tied to any contingency is not accepted.
After award, you must have
- Payment bond or irrevocable letter of credit for 100% of the contract price (contracts of $35,000 or more), plus a performance bond for 100% of the price if the total is $150,000 or more, due within 10 days after award. From Solicitation W912WJ27QA001.pdf:
A Performance Bond shall be required if the total price of the quote is $150,000.00 or above.
- At least one Level 3 Site Safety and Health Officer (SSHO) on site, and two employees certified in First Aid and cardiopulmonary resuscitation (CPR) on shifts with multiple employees. From Solicitation W912WJ27QA001.pdf:
The Contractor shall employ a minimum of one person to function as a Level 3, SSHO.
Current contractor
No incumbent is named; Section L says this work is considered "new".
Not in the notice text
- About 14,000 characters in the middle of the solicitation PDF (part of the contract clauses in Section I) weren't read, so some contract clauses may be missing from this brief.
- The notice and documents give no budget, Government estimate, or contract value.
- No site visit dates are given; the technical point of contact arranges visits.
- No deadline for questions is stated; questions go to the Contract Specialist, not the technical point of contact.
- The notice to proceed date and expected award date aren't stated.
- Which state licenses the electrician and plumber must hold isn't stated.
- The relative importance of the technical, price and past performance factors isn't stated.
Eligibility and how to respond
- Set aside for small businesses: only a business that counts as small under this notice's NAICS code can bid as the prime contractor. More open small business set-asides under NAICS 238290
- How to submit, from the AI summary: Email the quote to the Contract Specialist (Alicia.N.LaCrosse@usace.army.mil), by the closing date and time. Check it in the notice before you send anything.
- Construction contracts over $2,000 pay at least the local Davis-Bacon wage rates, from the wage determination in the solicitation. Price your labor from it: How to price a government contract, and how Davis-Bacon differs from the Service Contract Act.
Notice details
- Posted
- Oct 22, 2026
- Notice type
- Solicitation
- Office
- W2SD ENDIST New England, Concord, MA
- Product/service code
- Y1QA · Construction of Restoration of Real Property (Public or Private)
- Business type
- Construction & renovation (FedReady's grouping, from NAICS 238290)
- Versions
2 versions have been posted, newest first.
- Oct 22, 2026 · Amendment 0001 (this version)Due Nov 5, 2026
- Oct 15, 2026 · SolicitationDue Nov 5, 2026
- Attachments
Past awards and competition
Who has won work like this before, the likely incumbent, and what similar contracts paid, from USAspending.gov.
Before you respond
- How to respond to a solicitation (8 steps)
- How to read a government solicitation
- How to price a government contract
- Set-aside contracts explained
Terms on this notice: Solicitation, Set-aside
Full notice text from SAM.gov
Similar open opportunities
- Johnston Ridge Observatory Backup Generator Repairs Gifford Pinchot National ForestThe Forest Service is asking small businesses for quotes to inspect, maintain and repair the backup diesel generator at Johnston Ridge Observatory in Toutle, Washington.
- Install Generator- FCI BastropSmall businesses are the only firms that can bid on solicitation 15BBNF27Q50100001 according to SAM.gov, though one attached document calls it unrestricted.
- Eufaula Powerhouse Hydroelectric Generator Rewind
- Sources Sought -Building 493 Generator and Backup Power Installation- Red River Army Depot
- Sources Sought -Building 493 Generator and Backup Power Installation- Red River Army Depot