Solicitation
JB Charleston Multiple Award Construction Contract
Dept of Defense · Dept of the Air Force · Sol. FA441826R0009
AI summary Beta
Some details weren't available to this summary, so it may miss requirements. Check the attachments on SAM.gov.
The Air Force (628th Contracting Squadron, Joint Base Charleston) plans to award several firm-fixed-price construction contracts (a Multiple Award Construction Contract, or MACC) for repair, renovation, new construction, demolition and utility work at JB Charleston, SC and a few nearby or outlying bases. Awardees then compete for individual task orders generally worth $1M to $30M, with a combined ceiling of $400 million over about 5.5 years including options. Amendment 002 extended proposals to 14 Oct 2026 and limits the set-aside to HUBZone or SDVOSB firms. Funds are not yet available.
Watch out for
- Set-aside conflict in the notice data. The SAM.gov field says no set-aside and Section A says 'Small Business', but Amendment 002 and the SF 1442 limit the competition to HUBZone or SDVOSB firms only; an ordinary small business would not be eligible.
THIS SOLICITATION IS ISSUED AS A COMPETITIVE HUBZone AND SDVOSB BUSINESS SET-ASIDE USING TRADE-OFF PROCEDURES AND THE PROVISIONS OF SECTIONS L &
- Funds are not available. No award will be made until funding exists, and the Government can cancel before or after the closing date without paying proposal costs.
FUNDS ARE NOT PRESENTLY AVAILABLE FOR THIS EFFORT.
- Large bid guarantee and bonds. A bid bond of up to $3 million is needed with the offer, plus performance and payment bonds on a seed project over $10 million, which is hard for a small firm to obtain.
The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.
- Heavy past performance bar. Relevant past performance must be Southeast-region work of $1M-$30M scale; projects elsewhere count as Not Relevant, and weak or missing references drop you to a Neutral rating.
Past Performance submitted for projects occurring outside the SE Region will be evaluated as Not Relevant.
- Must bid on 75% of task orders. Failing to submit responsive proposals on 75% of task order requests in a 12-month period can get you removed, and all proposal and site visit costs are unpaid.
Contractors are required to submit responsive proposals on 75% of Task Order Proposal Requests (TOPRs)
- Mandatory site visits for task orders. Skipping a task order site visit makes that proposal non-responsive, and travel costs cannot be billed separately.
Site Visit attendance shall be required for Task Order Proposal Submission unless otherwise specified.
- Only a $3,000 guaranteed minimum. Work depends on winning later competitions; the guaranteed minimum is a $3,000 orientation task order, and proposals may be requested before funding exists.
all JB CHS MACC awardees will receive a $3,000 Post-Award Orientation
- Liquidated damages. Typical late-completion damages were set at $567 per calendar day by Amendment 002.
Update the typical JB Charleston Liquidated Damages rate to
- Pricing documents and Q&A not provided. The seed project price schedule, specifications, drawings, completed Q&A and wage determinations were not in the text, so the price proposal cannot be fully understood from this brief.
- Inconsistent past performance wording. Amendment 0001 says out-of-region past performance is rated Not Relevant, while Section M says it will not be evaluated; the later amendment also changed the recency standard, so check the final Section L and M.
which occurred outside the SE Region, i.e. non-responsive as to relevancy, shall not be evaluated.
Read from the notice and 12 attachments. 37 not read in full.
- Solicitation Amendment - FA441826R00090002.pdf
- Solicitation Amendment FA441826R00090001.pdf
- Solicitation - FA441826R0009.pdf
- Statement of Work - JB CHS MACC.pdf
- Statement of Work - Attachment 17 - 01 78 00 - Closeout Requirements.docx
- Statement of Work - Attachment 16 - 01 45 00 - Quality Control.docx
- Statement of Work - Attachment 15 - 01 35 26 - Governmental Safety Requirements.docx
- Statement of Work - Attachment 14 - 01 35 26 - Attachment A Accident Investigation (CIRS).pdf
- Statement of Work - Attachment 8 - 01 32 00 - Project Schedule.docx
- Statement of Work - Attachment 6 - 01 32 00 - Attachment A - Schedule- Pay Calendar Example 1.pdf
- Statement of Work - Attachment 5 - 01 30 00 - Administrative Requirements.docx
- Statement of Work - Attachment 4 - 01 14 00 - Work Restrictions.docx
- Solicitation Attachment YS Seed Project Specifications_Mark Up.pdf: too large
- Solicitation Attachment YS Seed Project Specifications.pdf: too large
- Statement of Work - Attachment 7 - 01 32 00 - Attachment A - Schedule-Pay Calendar Example 2.xlsx: spreadsheet: not read yet
- Statement of Work - Attachment 3 - 01 11 00 - Summary of Work.docx: over the file limit for one brief
- Statement of Work - Attachment 2 - Architectural Compatibility Plan.pdf: over the file limit for one brief
- Statement of Work - Attachment 1 - JB Charleston Statement of Work for (A_E).pdf: over the file limit for one brief
- Solicitation Attachment - B466 Mechanical RFIs.pdf: over the file limit for one brief
- Solicitation Attachment - Hydrant Flow Test Data.pdf: over the file limit for one brief
- Solicitation Attachment - Pre-Proposal Conference Slides 2026.pptx: .pptx files aren't read yet
- Solicitation Attachment - Salvage Storage List.docx: over the file limit for one brief
- Solicitation Attachment - Site Visit Sign-In Sheet.pdf: over the file limit for one brief
- Solicitation Attachment XZ - Past Performance Project List.xlsx: spreadsheet: not read yet
- Solicitation Attachment XY - On and Off-Ramp Procedures (1).pdf: over the file limit for one brief
- Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.xlsx: spreadsheet: not read yet
- Solicitation Attachment XX - Task Order Proposal Request (TOPR) Seed Project.pdf: over the file limit for one brief
- Solicitation Attachment XW - JB Charleston MACC Work Load Estimate.pdf: over the file limit for one brief
- Solicitation Attachment XU - Past Performance Customer Questionnaire.pdf: over the file limit for one brief
- Attachment YU - Seed Project Schedule B.pdf: over the file limit for one brief
- Statement of Work - Attachment 13 - 01 33 00 - Submittal Procedures.docx: over the file limit for one brief
- Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).pdf: over the file limit for one brief
- Statement of Work - Attachment 12 - 01 33 00 - Attachment D - Form 4289-R (RFI Register).xlsx: spreadsheet: not read yet
- Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).pdf: over the file limit for one brief
- Statement of Work - Attachment 11 - 01 33 00 - Attachment C - Form 4288-R (Submittal Register).xlsx: spreadsheet: not read yet
- Statement of Work - Attachment 10 - 01 33 00 - Attachment B - JB CHS RFI Form.pdf: over the file limit for one brief
- Statement of Work - Attachment 9 - 01 33 00 - Attachment A - JB CHS Transmittal Form 4025.pdf: over the file limit for one brief
- Solicitation Attachment - 1999 As-Built Drawings_20260918.pdf: over the file limit for one brief
- Solicitation Attachment - Geotechnical Report 14 April 2025.pdf: over the file limit for one brief
- Solicitation Attachment YT Seed Project Drawings.pdf: over the file limit for one brief
- Solicitation Attachment XV - Past Performance Survey.pdf: over the file limit for one brief
- Solicitation Attachment XT - JB Charleston - Question and Answer Form.xlsx: spreadsheet: not read yet
- Attachment XT - JB Charleston Question and Answer Form (Completed).xlsx: spreadsheet: not read yet
- B466 Photos.pdf: over the file limit for one brief
- B464 Photos.pdf: over the file limit for one brief
- Solicitation Attachment - Wage Determination NC20260012 - Wayne County.pdf: over the file limit for one brief
- Solicitation Attachment - Wage Determination SC20260030 - Sumter County.pdf: over the file limit for one brief
- Solicitation Attachment - Wage Determination SC20260022 - Berkeley County.pdf: over the file limit for one brief
- Solicitation Attachment - Wage Determination SC20260023 - Charleston County.pdf: over the file limit for one brief
Full brief
What they want
- Construction firms for a multiple-award contract that competes task orders for maintenance, repair, alteration and minor construction
- Whole-building renovation (mechanical, electrical, plumbing, fire protection, building envelope) and water, wastewater and electrical utility work
- Design-build task orders, from concept up to 100% design, as well as design-bid-build
- A priced proposal for the 'Seed Project' (Repair Dormitory B464, estimated over $10 million)
- Past performance on similar-size projects in the Southeast (SBA Region IV) within the last 5 years
- Responsive proposals on at least 75% of task order requests over 12 months, or risk removal from the MACC
- Furnishing all labor, materials, equipment, transportation, supervision and testing, with the required safety, quality control, schedule and closeout submittals
- Contract type
- Firm-fixed-price Multiple Award Construction Contract (MACC); work is ordered through competed task orders
- Period of performance
- Base period plus Option Periods 1 to 4 and an option to extend services (Option 5). The maximum task order value is $400M over 5 years and 6 months including options. Amendment 002 states orders may be issued from June 27 2026 through December 26, 2032. The length of each period is not stated in the text provided.
- Place of performance
- Joint Base Charleston (Air Base and Naval Weapons Station), Short Stay Recreational Area (Moncks Corner), Defense Fuel Supply Point (Charleston), and North Auxiliary Airfield, SC. Outlying areas: Seymour Johnson AFB, NC and Shaw AFB, SC (no more than 10% of task orders).
- Estimated value
- Task orders generally $1M to $30M each (raised from $25M by Amendment 002). Total of all task orders not to exceed $400,000,000. Seed Project estimated at more than $10,000,000. Minimum guarantee is a $3,000 Post-Award Orientation Task Order.
- Contract vehicle
- New standalone solicitation FA441826R0009 (JB CHS MACC 2.0); no existing schedule or contract vehicle is required
- How they'll choose
- Trade-off procedures (best value). Two factors are named: a Seed Project price proposal and past performance. Past performance is evaluated in ascending order of price until nine offerors are rated Substantial Confidence or all are evaluated.
- Offers due
- 14 Oct 2026, 12:00 PM Eastern (extended by Amendment 002 from 21 Sep 2026)
- How to submit
- Electronically through DoD SAFE only. Non-DoD offerors must first email lauren.parker.4@us.af.mil (cc robert.melton.6@us.af.mil, the Contracting Officer) to be granted drop-off access, which lasts 14 days. Amendment 002 says the point of contact is now Daniel Teeter, but his contact details are not in the text provided.
- Page limits
- Part II (Past Performance) is limited to 50 pages, not counting the past performance questionnaires. Pages over the limit are not read. 8.5 x 11 paper (fold-outs up to 11 x 17), type not smaller than 12 pitch.
What they'll judge offers on
- Factor 1 - Seed Project Price Proposal (Repair Dormitory B464)
- Factor 2 - Past Performance (recency, relevancy, then a confidence rating)
What to include when you submit
- Proposal has two parts: Part I Seed Project Price Proposal and Part II Past Performance Information
- Proposal must be valid for 180 days
- Acknowledge Amendments 0001 and 0002 on the SF 1442
- Past performance write-ups must list contract number, customer, value, role, percent of work performed, and references
- Include completed Past Performance Questionnaires, or at least page 1 of each if the client has not returned it
- Teaming or joint venture partners must give a consent letter authorizing release of their past performance information
- Exceptions to terms must be raised with rationale 5 business days before the closing date
- Do not use zip files or file suppression utilities for DoD SAFE proposal modifications
- Offer guarantee (bid bond) is 20% of the bid price or $3,000,000, whichever is less; performance and payment bonds are due within 10 days of award
You must have
- Must be a HUBZone or SDVOSB small business. You do not need both certifications, and award may go to some or all of either group.
This acquisition is set aside for HUBZone or SDVOSB (a total small business set aside to these socioeconomic categories only)
- Small business under NAICS 236220 (size standard $45 million average annual receipts)
NAICS Code: 236220 Size Standard: $45,000,000
- Recent and relevant past performance on whole-building renovation or utility projects of $1M-$30M, located in the Southeast Region (AL, FL, GA, KY, MS, NC, SC, TN), with at least one day of performance in the last 5 years
Past Performance submitted for projects occurring outside the SE Region will be evaluated as Not Relevant.
- Bid guarantee and performance and payment bonds
The amount of the bid guarantee shall be 20 percent of the bid price or $3,000,000.00, whichever is less.
- Minimum insurance during performance: general liability $500,000 per occurrence, automobile liability, workers' compensation, and employer's liability of $100,000
a. Comprehensive general liability: $500,000 per occurrence
- Must follow the limits on subcontracting (self-perform a minimum share of the work) and the SBA rules for joint ventures
performance requirements of 13 CFR 124.513(d) and RFO 52.219-14, Limitations On Subcontracting, as applicable.
- A proposed superintendent with at least 5 years of experience on similar projects, who is fluent in English, plus a project scheduler with 5 years of CPM scheduling experience
Current contractor
Not named. The title 'JB CHS MACC 2.0' suggests a follow-on to an earlier Joint Base Charleston MACC, but the text provided does not say who holds it.
Not in the notice text
- Section M evaluation details: the relative importance of price and past performance, and how many awards will be made (most of Section M was left out of the text provided)
- Most of Section L (2.2 and the first part of 2.3, including how many past performance projects to submit) and Sections F through K, including full clause text and the Section H liquidated damages clause
- Seed Project pricing details: Attachment YU Schedule B CLIN structure, seed project drawings and specifications (too large to read)
- Daniel Teeter's contact information (Amendment 002 replaced the point of contact but the new details are not in the text)
- Length of the base period and each option period; Amendment 002 gives an ordering window of June 27 2026 to December 26, 2032 while the cover page says $400M over 5 years and 6 months
- Davis-Bacon wage determinations (Charleston, Berkeley, Sumter, Wayne counties), completed Q&A form, pre-proposal slides, on and off-ramp procedures and work load estimate were not read
- Whether the offer guarantee box on the SF 1442 is checked (the form text is ambiguous); the notice amendment sets the bid guarantee at 20% or $3M, whichever is less
FedReady checks notices like this against your business profile, tracks deadlines, and alerts you to new matches. Creating an account is free.
Key facts
- Response due
- Oct 14, 2026, 4:00 PM UTC
- Posted
- Sep 18, 2026
- Notice type
- Solicitation
- Solicitation
- FA441826R0009
- Agency
- Dept of Defense · Dept of the Air Force
- Office
- FA4418 628 Cons PK
- NAICS
- 236220
- Product/service code
- Y1JZ
- Business type
- Construction & renovation
- Place of performance
- 0, SC, 29404
- Contracting contact
- Daniel Teeterdaniel.teeter@us.af.mil8439637744
- Versions
- 4 (amended since first posted)
Full notice text from SAM.gov
Similar open opportunities
- Barillas Peak & Encino Vista Lookout Tower Restoration, Santa Fe NFThe U.S. Forest Service (Southwest) wants quotes to design and replace the cab (the room at the top) of the Barillas Lookout Tower on the Santa Fe National Forest in New Mexico,…
- Trade and Cargo AcademyThe Army Corps of Engineers Charleston District wants a contractor to build a Trade and Cargo Academy and a Cargo Security and Seized Property Training Facility at the Federal…
- FCKY UEPH Barracks CM@RiskThe Army Corps of Engineers (Louisville District) is doing market research for construction of Unaccompanied Enlisted Personnel Housing (barracks) at Fort Campbell, KY, using a…
- Lease Fit-Out Construction in Nuuk, Greenland - Sources Sought/Market ResearchThe U.S. Department of State (Bureau of Overseas Buildings Operations) is doing market research for a construction contract to fit out three floors of a leased, occupied building…
- Fort Lee Vehicle Recovery RangeThe Army Corps of Engineers (Norfolk District) wants a contractor to build 24 concrete turning pads with site drainage and road alignment and repair at Fort Lee, Virginia.