Solicitation
Fort Lee Vehicle Recovery Range
Dept of Defense · Dept of the Army · Sol. W9123626BA006
Due in 8 days8(a)
AI summary Beta
Some details are in the notice's attachments, which this summary didn't read. Check the attachments on SAM.gov.
The Army Corps of Engineers (Norfolk District) wants a contractor to build 24 concrete turning pads with site drainage and road alignment and repair at Fort Lee, Virginia. The work is split into three phases, with the contractor getting access to one phase at a time, and phases two and three are options. It is an 8(a) set-aside and the bid due date was extended by amendment 0007.
Watch out for
- Work phased around Army training. You only get access to one phase at a time and the Army trains in the other areas, which can limit scheduling and site access.
the Army will conduct training operations in the remaining two phases
- Phases are options. Phases two and three are only built if the Army chooses to exercise them, so the guaranteed work may be only phase one.
The remaining phases (two and three) will only be performed if the options for phases are exercised.
- Many amendments. Final drawings and specs are in amendment 0006 and the due date changed in amendment 0007, so you must use the latest documents.
Please see amendment 0006 for the final drawings and specifications.
Read from the notice text only.
Full brief
What they want
- Construct 24 concrete turning pads (excavate the existing roadbed and place concrete to the design specs)
- Install storm drainage systems for positive site drainage
- Regrade and align the connecting roads to match the pads, with road repair as needed
- Complete the work in three phases, finishing each phase before the next
- Build around ongoing Army training operations
- Contract type
- Construction with option phases (phases two and three are options); pricing type is not stated
- Period of performance
- Three phases; length not stated
- Place of performance
- Fort Lee, VA, USA
- Offers due
- 2026-10-13 2:00 PM Eastern (posted as 2026-10-13T14:00:00-04:00); extended by amendment 0007
What to include when you submit
- See amendment 0006 for the final drawings and specifications
- See SF30 amendment 0007 for the extended bid due date and bid opening date
You must have
- Must be an 8(a) program participant; this is an 8(a) set-aside (FAR 19.8).
Not in the notice text
- Estimated value or magnitude of the project
- Evaluation method and factors
- Bonding, insurance and other requirements (likely in the solicitation documents)
- Time allowed for each phase
- How bids must be submitted
Is this a fit for your business?
Create a free accountFedReady checks notices like this against your business profile, tracks deadlines, and alerts you to new matches. Creating an account is free.
Key facts
- Response due
- Oct 13, 2026, 6:00 PM UTC
- Posted
- Sep 29, 2026
- Notice type
- Solicitation
- Solicitation
- W9123626BA006
- Agency
- Dept of Defense · Dept of the Army
- Office
- W2SD Endist Norfolk
- Set-aside
- 8(a) Set-Aside (FAR 19.8)
- NAICS
- 236220
- Product/service code
- Y1PZ
- Business type
- Construction & renovation
- Place of performance
- Fort Lee, VA
- Contracting contact
- Michael Stevensonmichael.l.stevenson@usace.army.mil(757) 201-7233
- Versions
- 7 (amended since first posted)
Full notice text from SAM.gov
Note: Please see amendment 0006 for the final drawings and specifications. Amendment 0007: An amendment has been made to Solicitation W9123626BA0006. Please see attachment SF30, Solicitation Amendment W9123626BA006_0007, extending the bid due date and bid opening date. The purpose of this project is to construct 24 concrete turning pads, along with required site drainage improvements and road alignment and repair as necessary. The contract will be executed in three distinct phases, with the contractor granted access to only one phase at a time. Completion of each phase is required before proceeding to the next. The remaining phases (two and three) will only be performed if the options for phases are exercised. During construction activities in one phase, the Army will conduct training operations in the remaining two phases. Each turning pad, as identified in the project drawings, will require excavation of the existing roadbed and placement of concrete in accordance with the design specifications. Storm drainage systems will be installed to ensure positive site drainage throughout the construction process. Upon proper curing of the concrete turning pads, the connecting roads will be regarded and aligned to seamlessly integrate with the pads, as detailed in the contract drawings.
Similar open opportunities
- Barillas Peak & Encino Vista Lookout Tower Restoration, Santa Fe NFThe U.S. Forest Service (Southwest) wants quotes to design and replace the cab (the room at the top) of the Barillas Lookout Tower on the Santa Fe National Forest in New Mexico,…
- Trade and Cargo AcademyThe Army Corps of Engineers Charleston District wants a contractor to build a Trade and Cargo Academy and a Cargo Security and Seized Property Training Facility at the Federal…
- FCKY UEPH Barracks CM@RiskThe Army Corps of Engineers (Louisville District) is doing market research for construction of Unaccompanied Enlisted Personnel Housing (barracks) at Fort Campbell, KY, using a…
- P084 NEXT GENERATION TORPEDO INTEGRATION LAB, NAVAL STATION NEWPORT, NEWPORT RINAVFAC Mid-Atlantic wants a contractor to build a 12,920 SF multi-story steel-frame laboratory and office building for depot-level torpedo system testing at Naval Station…
- FY28 KC-46A Aircraft Beddown Infrastructure Program | Altus AFB, OklahomaThe U.S. Army Corps of Engineers, Tulsa District wants a design-build team for a roughly $235M program at Altus Air Force Base, Oklahoma.