Presolicitation
Design and Construction of Levee Access Manholes for Fairfax-Jersey Creek Levee Unit (Kansas City, Kansas)
Dept of Defense · Dept of the Army · Sol. PANNWD-26-P-0000028010-2
Track this notice by email. We'll email you if it's amended or awarded, and a week and two days before responses are due.
AI summary Beta
The U.S. Army Corps of Engineers, Kansas City District, plans a two-phase design-build solicitation for access manholes on existing seepage lines at the Fairfax-Jersey Creek Levee Unit on the Missouri River in Kansas City, Kansas. It will result in a firm-fixed-price contract with an estimated magnitude of $1,000,000 to $5,000,000 and 365 calendar days to complete after notice to proceed. This is a presolicitation notice; the solicitation is not out yet.
Things to watch
- Two-phase process: Phase 1 is a gate. Only the most highly qualified Phase 1 offerors are invited to submit Phase 2 technical and price proposals; a firm that misses or loses Phase 1 is shut out.
In Phase 2, a solicitation amendment will be issued only to the selected Phase 1 offerors, inviting
- Bonds required. A Phase 2 bid bond (up to $3,000,000) and 100% payment and performance bonds are required before NTP.
- Levee work restrictions and design-build risk. The contractor does its own design and any investigation, and trenching and other invasive mass excavation are not allowed, so methods are tightly limited.
INVASIVE MASS EXCAVATION METHODS
- Site visit planned. A site visit is planned; the notice does not say it is mandatory, and details will be in the solicitation.
There will be a site visit planned for this solicitation.
- PIEE registration needed in advance. Proposals go through PIEE and registration needs a supervisor or approving official and a CAGE code, so start early.
Read from the notice and 1 attachment.
- B_01_03__Presolicitation___Fairfax_Levee_Access_Manholes.pdf
Full brief
What they want
- Design and build access manholes on the landside levee slope and berm
- Manholes let the government inspect the existing seepage collection system
- Maximum hole depth is estimated at 25 feet
- Do your own investigations and survey if you think they are needed
- Follow USACE ER 1110-1-1807 for drilling and invasive activities; use minimally invasive excavation (no trenching)
- Contract type
- Firm-fixed-price design-build construction contract, negotiated, two-phase selection
- Period of performance
- 365 calendar days from notice to proceed (NTP), estimated
- Place of performance
- Fairfax-Jersey Creek Levee Unit on the Missouri River, Kansas City, Kansas
- Estimated value
- Between $1,000,000 and $5,000,000
- How they'll choose
- Two-phase design-build: Phase 1 picks the most highly qualified offerors; Phase 2 awards on a best value tradeoff using factors from both phases
- Offers due
- Not yet set. Phase 1 proposals are expected at least 30 days after the solicitation release; the Phase 2 date will come in an amendment sent only to selected offerors.
- How to submit
- PIEE Solicitation Portal; offerors must first register for the PIEE 'Proposal Manager' role
What they'll judge offers on
- Phase 1: offeror qualifications to execute the work (criteria to be in the RFP)
- Phase 2: technical proposal and price proposal (criteria to be in the RFP)
What to include when you submit
- Register in PIEE (SOL-Solicitation, Proposal Manager role; a CAGE code is needed for the location code)
- Phase 1: submit proposals demonstrating qualifications
- Phase 2 (selected firms only): technical and price proposals
- Technical question contact details will be in the solicitation
You must have
- Active SAM registration before submitting proposals (a joint venture must have one registration for the JV entity)
Proposals from contractors without an active SAM registration
- PIEE 'Proposal Manager' role registration to submit a proposal
contractors will first need to register for the PIEE
- Bid bond in Phase 2 of 20% of proposed price or $3,000,000, whichever is less; payment and performance bonds for 100% of the contract before NTP
Bid bonds will be required in Phase 2 in the amount of 20% of the offeror’s proposed price or
- Full and open competition (no set-aside)
This procurement will be conducted using full and open competition.
Not in the notice text
- Phase 1 and Phase 2 due dates
- Evaluation criteria and weights for each phase
- Site visit date and whether it is mandatory
- Contact for technical questions (to be in the solicitation)
- Solicitation release date (expected within 60 days of the notice, at least 15 days after)
FedReady checks notices like this against your business profile, tracks deadlines, and alerts you to new matches. Creating an account is free.
Key facts
- Posted
- May 28, 2026
- Notice type
- Presolicitation
- Solicitation
- PANNWD-26-P-0000028010-2
- Agency
- Dept of Defense · Dept of the Army
- Office
- W071 Endist Kansas City
- NAICS
- 237990
- Product/service code
- Y1PZ
- Business type
- Construction & renovation
- Place of performance
- 66115
- Contracting contact
- Erick Ottosonerick.s.ottoson@usace.army.mil8163893878
- Versions
- 2 (amended since first posted)
What similar contracts paid
731 contracts at this agency for the same NAICS and product/service codes had activity in the last 5 years, according to USAspending.gov. Small businesses won 26% of the dollars in this market over the last 3 fiscal years.
Before you respond
Full notice text from SAM.gov
Similar open opportunities
- Mary Rhodes Pump Station: Emergency Streambank Erosion ProtectionThe U.S. Army Corps of Engineers Galveston District is asking industry whether it can protect the Mary Rhodes Pump Station in Bay City, TX from Lower Colorado River bank erosion.
- Repair Aids to Navigation (ATON) - Southern Area of USCG District NortheastThe U.S. Coast Guard (Northeast District) wants a contractor to repair, replace or demolish seven aids-to-navigation structures (lights and towers) in New York, Connecticut and…
- Chief Joseph Dam (CJD) Intake Concrete Stairs RepairThe Army Corps of Engineers (Seattle District) is doing market research for repairing the concrete stair landings at the intake of Chief Joseph Dam in Bridgeport, WA. This is a…
- CHOH 326202 Repair Historic Potomac River Dams 4 aThe National Park Service (Denver Service Center) is doing market research, not asking for bids yet, for a design-build contract to repair two historic Potomac River dams (Dams 4…
- Sources Sought: The Dalles Dam Gate Repair Pit Fire Protection and Life Safety UpgradesThe U.S. Army Corps of Engineers Portland District is doing market research for electrical, life-safety and fire-protection upgrades to the Powerhouse Gate Repair Pit at The…